Carr Boyd Ni Presentation
Released
Released
Announcement PDF
Carr Boyd Ni Cu Project
THE HUNT IS ON……
August 2018
Capital Structure
Current Issued Share Capital
•
FPOS
- 471,883,292
•
Options
- 8,250,000
- 22,500,000
2.4c exercise Mar 2020
5c exercise June 2021
Post Placement / Loyalty Offer
•
•
FPOS
Options
- 491,883,292
- 8,250,000
- 206,461,098
42.6M escrowed
Major Shareholders
•
•
•
•
•
Apollo Phoenix Resources P/L
Mariner Mining
Guiyun Wang
Kylie Campbell
Douglas Daws
Top 50 =
15%
6.8%
5.2%
4.4%
3.1%
64.0%
2.4c exercise Mar 2020
5c exercise June 2021
Board
Senior Management
Ray Sharrocks
Stephen Brockhurst
John Kingswood
Chris Daws CEO
Estrella 6 month share price
Carr Boyd Update, August 2018
2
Carr Boyd- Introduction
•
100% owned Carr Boyd Ni/Cu Project, located 80km NNE of
Kalgoorlie. Acquisition completed June 2018
•
Highly differentiated layered igneous complex with breccia
hosted Ni/Cu mineralisation high up in the complex,
inferred basal contact/feeder source.
•
Discovered by a Great Boulder Mines Ltd and North Kalgurli
JV between 1969 – 1972.
•
Acquired by and mined by WMC from 1973 to 1975.
•
Ni / Cu sulphides throughout the complex (sulphur
saturation), where there is smoke….....
•
Previous explorers only tested the obvious targets.
•
Basal contact Voisey Bay style, or feeder dyke style
mineralisation not effectively tested.
Carr Boyd Update, August 2018
3
CBLC Targets on Interpreted Geology
Carr Boyd Update, August 2018
4
Carr Boyd- Work Completed
•
Diamond holes re-entered at Car Boyd mine and HPEM
surveyed, technique proven effective.
•
Yilgarn 1400m hole CBD022, re-logged geologically,
consultation with Dr Martin Gole, sulphur saturation and
high prospectivity of CBLC confirmed.
•
Historic detailed gravity and magnetic datasets re compiled,
re processed, and 3D inversion modelled.
•
Deep drilling at Tregurtha South and SWW have provided
valuable geological data.
•
Structural interpretation study completed.
•
Cobalt mineralisation discovered drilling at Scotia East.*
-
•
7m @ 0.21% Co from 7m downhole NCB0024*
11m @0.16% Co from 3m downhole NCB0023*
POW Approvals received for further drilling to commence.
*See ASX release dated 27 March 2018
Carr Boyd Update, August 2018
5
Carr Boyd Mineralisation Tenor
•
•
•
•
Pure massive sulphide typically grades 6% nickel and 2% Copper
Nickel tenor in a similar range to Nova-Bolloinger, but the copper ratio is higher
How many Fraser Range prospects have this after many years and $$$ expended?
Brownfields exploration has a much higher chance of success…..we are in the hunt!
Carr Boyd Update, August 2018
6
Carr Boyd Next Steps
• Complete Phase 2 high powered MLEM surveys;
- over immediate mine area
- Fosters Hill (historic GeoTEM and Cu anomaly)
- over NW interpreted basal contact area
• Undertake 2D seismic survey over Carr Boyd Mine
• Undertake drilling of high ranking nickel targets
• Undertake extensional drilling of Scotia East Cobalt
• Drill, Drill and keep Drilling……..
OUR AIM IS TO LOCATE THE SOURCE OF THE
MASSIVE Ni SULPHIDE.
Carr Boyd Update, August 2018
7
Carr Boyd Summary
• Confirmed fertile Mafic Layered Intrusion - RARE.
• High grade massive Ni / Cu sulphides exist.
• Target geological setting is compelling.
• The hunt is on……..
Carr Boyd Update, August 2018
8
Disclaimer & Declaration
This presentation has been prepared by Estrella Resources Limited (“ESR”) as a summary of the company’s exploration and development
activities, with particular reference to the Carr Boyd Ni/Cu Project near Kalgoorlie, WA.
No Offer of Securities
The presentation is not, and should not, be considered as an offer or invitation to subscribe for, or purchase any securities in ESR, or as
an inducement to make an offer or invitation with respect to those securities. No agreement to subscribe for securities in ESR will be
entered into on the basis of this presentation.
Forward Looking Statements
This presentation contains certain forward looking statements which have not been based solely on historical facts but, rather, on ESR’s
current expectations about future events and on a number of assumptions which are subject to significant uncertainties and
contingencies many of which are outside the control of ESR and its directors, officers and advisers.
Reliance on Third Party Information
Due care and attention has been taken in the preparation of this presentation. However, the information contained in this presentation
(other than as specifically stated) has not been independently verified nor has it been audited. Accordingly, the company does not
warrant or represent that the information contained in this presentation is accurate or complete. To the fullest extent permitted by law,
no liability, however arising, will be accepted by ESR or its directors, officers or advisers, for the fairness, accuracy or completeness of
the information contained in this presentation.
Competent Person Declaration
The information in this presentation that relates to Exploration Results, Mineral Resources or Ore Reserves is based on information
compiled by Mr Luke Marshall, who is a member of The Australasian Institute of Geoscientists. Mr Marshall has sufficient experience that
is relevant to the style of mineralisation and type of deposit under consideration and to the activity that he is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resource and
Ore Reserves”. Mr Marshall consents to the inclusion in the presentation of the matters based on his information in the form and context
in which it appears.
Carr Boyd Update, August 2018
9
Share your feedback