QUARTERLY ACTIVITIES REPORT
Quarter ending 31 December 2023
Estrella Resources Limited
ABN 39 151 155 207
HIGHLIGHTS
•
•
ASX Code: ESR
•
Board and Management
Managing Director
Christopher Daws
Non-Executive Directors
Les Pereira
John Kingswood
•
•
Awarded three highly prospective Mining Concessions by the
Timor-Leste Government in the Country’s inaugural Minerals
Tender 2023
Signed a binding Memorandum of Understanding (MOU) with
state-run Murak Rai Timor (MRT) to create a joint venture
partnership to explore for and potentially exploit mineral
deposits in Timor-Leste
Next-generation helicopter-borne TargetEM system has
identified areas prospective for nickel sulphides at Carr Boyd
Spargoville 5A Interim Prefeasibility Study demonstrates the
viability of the 5A Underground Nickel Mine at higher nickel
prices
Well funded having completed $1.65 million placement to
advance exploration
Estrella Resources Limited (ASX: ESR) (“Estrella” or “the Company”)
is pleased to provide its activities report for the period ended 31
December 2023.
Commenting on the quarter, Managing Director Chris Daws said:
Company Secretary
Stephen Brockhurst
Benjamin Smith
Address
Level 8, London House
216 St Georges Terrace Perth
WA 6000
PO Box 2517 Perth WA 6831
“The December quarter was a milestone period for Estrella and our
shareholders as we sought to set up a new exploration front in the
highly prospective country of Timor-Leste with the signing of an
extremely important partnership with the Timor-Leste government
body, MRT, which is charged with stimulating and participating in the
country’s mineral exploration and mining developments.
The next steps will be to create a JV company and shareholder
agreement between our permanent branch office in Dili and the MRT
which will establish the framework of our working relationship going
forward in Timor-Leste.
While we will progress this JV, our focus will also continue developing
our highly prospective Western Australian projects.
Telephone: +61 8 9481 0389
Facsimile: +61 8 9463 6103
We also further uncovered the potential for LCT minerals at Carr Boyd
with a significant field of stacked, fractionating pegmatites discovered
in the Eastern tenements. Meanwhile, processing of geophysical
survey data continued to identify areas prospective for nickel sulphides.
info@estrellaresources.com.au
www.estrellaresources.com.au
With the Spargoville 5A deposit, we were encouraged by the interim
PFS report which outlined a small-scale mining operation of a highgrade resource body which presents an ideal operation for a company
of Estrella’s size. We are continuing to advance our way through the
DFS process and will keep you updated on our progress.
TIMOR-LESTE
Mining Concession Awarded
During the period, Estrella announced it had pre-qualified for Timor-Leste’s inaugural Minerals Tender
process and submitted bids for highly prospective mineral concessions (Mining Concessions). 1 The
Minerals Tender, for the first time, awarded mineral titles across the country, providing a unique first
mover advantage for those successful in securing concessions.
In November, Estrella was awarded three Mining Concessions in the Lautém Municipality of TimorLeste in the Country’s inaugural Minerals Tender 2023.2 The Award Ceremony took place in the TimorLeste capital Dili on November 30th, 2023, and was attended on Estrella’s behalf by Managing Director
Chris Daws and Chairman Les Pereira.
Of the four Mining Concessions that Estrella applied for, three were awarded in the mineral titles tender
process by the Timor-Leste Government. The Mining Concessions lie in the north-eastern part of the
country and cover an area of 121.5 km2 (Figure 1). Access to the Mining Concessions is 170km via
sealed all-weather roads from the capital city of Dili and then a further 10km on all-weather unsealed
roads south to the towns of Baduro or Daudere.
The Concessions lie over very accessible country consisting of rolling hills between 35m and 650m
above sea level, hosting vegetation that varies between open grasslands to tropical savannah woods.
Timor-Leste has a pronounced dry season which will greatly assist land access and exploration in more
remote areas.
Figure 1: Location of Mining Concessions ZA-01 to ZA-03 in Lautém Municipality, Timor-Leste
Memorandum of Understanding with Murak Rai Timor, E.P.
Estrella Resources Limited Representacao Permanente (ESR-RP) was registered in Dili in 2023 as
Estrella’s managing branch Company to allow Estrella to effectively operate mineral exploration and
development activities in Timor-Leste.
1 Refer to ASX announcement dated 10 October 2023
2
Refer to ASX announcement dated 4 December 2023
ESR-RP entered a binding Memorandum Of Understanding (MOU) with state-run Murak Rai Timor,
E.P. (MRT) where MRT is free-carried 30% in a joint-venture partnership with ESR-RP up to the
publication and approval of a Definitive Feasibility Study on a Mining Concession. 3 The MOU called
for, among other items, the creation of a formal joint-venture agreement between Estrella and MRT
within 90 days of the successful award of tender bids to ESR-RP.
MRT was set up in September 2023 by the Timor-Leste Government as the Timor-Leste National
Mining Company to be capable of participating in the mining of mineral resources on behalf of the
Republic..
According to Decree-Law No. 64/2023, MRT is tasked to carry out mining activities, including
reconnaissance, prospecting and exploration, evaluation, development, operation, processing,
transportation and marketing of minerals, as well as mine closure activities. MRT is also tasked to
carry out auxiliary services to support mining activities.
MRT is a state-owned company incorporated to carry out commercial activities in the mining sector as
a part of the Government’s strategy to build institutions that stimulate the development of economic
sectors and have great potential to contribute to economic diversification.
A joint-venture partnership between MRT and ESR-RP is regarded as the best way forward for any
potential success from mineral exploration to flow through to both ESR shareholders and the TimorLeste people. The opening of Estrella’s branch Office in Dili will enable Estrella and the Government of
Timor-Leste to participate at all levels in the discovery and potential mining that may follow. This will
ensure environmental, economic and social benefits to the Republic and people in areas where the jointventure operates.
Mineral Potential of the Mining Concessions
The Timor Island (including Indonesian West Timor) is part of the Outer Banda Arc which formed through
the geologically recent collision of the Australian Continent with the Banda Island Arc (Asian microplate).
During this collision, the Timor Island was uplifted through a series of complex folds and thrusts, and
the geology of Timor-Leste is dominated by more recent marine and terrestrial sediments overlying
much older Australian continental greenstone crust. Recent, rapid weathering of the island has left
structural windows of Australian crustal greenstones exposed alongside and beneath the younger
marine sediments.
The distribution of metallic minerals is closely
associated with the structural domains now
exposed on the surface. Occurrences of gold,
silver, copper, manganese and chromite have
been noted across the Republic4 however no
modern exploration has been done to find,
map and quantify all of these occurrences.
During a recent field visit to the awarded
Mining Concessions, a large area of
manganese mineralisation was shown to ESR
personnel by local Timor-Leste community
members (Figure 2).
Figure 2: Managing Director Chris Daws with local farmers
and guides in a recent visit to the Timor-Leste concessions.
Figure 3 below shows a large boulder visually
containing around 60% Manganese Oxide
minerals (mainly Pyrolusite, MnO2), the
principal ore of manganese on the island. The
manganese mineralisation occurs within a
limestone marl in both pisolithic and platy
forms which have been precipitated directly
onto
the
sea-floor
by
metal-laden,
hydrothermally enriched sea-water. Previous
3 Refer to ASX announcement dated 4 December 2023
4 United Nations ESCAP-report 2003; Pacific Economic Cooperation Council Minerals Network
studies5 of other manganese deposits on the Timor Islands have concluded that the manganese formed
in a deep-sea environment before the major uplift event that now exposes the deposits at surface.
Figure 3: Boulder containing pisolitic pyrolusite within a limestone marl of the Bobonaro Complex. This large boulder
was one of many within in an extensive alluvial scree located in the area.
Figure 4: Platy Pyrolusite forming >90% of the
specimen found during field reconnasaince to the
Mining Concessions
Figure 5: Sub-cropping manganese
mineralisation in hillside scree of the Bobonaro
Formation within Mining Concession ZA-01
5 Characteristics and Origin of Sedimentary-Related Manganese Layers in Timor Island, Indonesia (2013) by Department of
Geological Engineering - Gadjah Mada University, Energy and Mineral Resources Agency - South Central Timor Regency,
Department of Mineralogy & Economic Geology - RWTH Aachen University, Germany
Manganese
Manganese is mined extensively in West Timor (Indonesia) and typically as a DSO product as the
grade is sufficient to feed directly into the smelting process. While some of the Timor-Leste deposits
are known about, none have been commercially exploited. Samples of the manganese-rich material
assayed by geologists working for the Timor-Leste Government saw most returning MnO2 grades well
above the 40% Mn level required by local Indonesian smelters.
It should be noted that Estrella has not performed any independent assay analysis of samples prior to
the granting of the Mining Concessions and is relying on information gathered by scientists associated
with the Office of the President, Ministry of Development and Environment and the ANPM. ESR-RP
will be conducting extensive mapping and sampling in due course to verify and build upon historical
mineral information.
Copper
In addition to manganese, the Mining Concessions awarded to Estrella have the potential to host
copper sulphide, gold and silver deposits. Within Timor-Leste, primary copper sulphides can be found
in the ultramafic rocks within the ophiolite sequences of the Lolotoi Formation. This rock type underlies
the limestone formation deposited over the majority of the island and is thought to represent ancient
Australian continental crust that has been upthrust during collision.
Cyprus-type copper-silver occurrences have also been identified within Timor-Leste by geological
consultants to the United Nations and the Timor-Leste Government. These VMS style deposits form
where hot fluids circulating through deeper rocks dissolve metallic elements and deposit them in
hydrothermal veins and vents within younger rocks, or directly onto the sea-floor along with zinc
minerals. The timing between these deposits and the manganese precipitation is yet to be fully
understood.
Moving Forward
With the award of the Mineral Concessions to ESR-RP and the MOU with MRT, ESR-RP will begin
building the joint-venture upon notifying the ANM of our acceptance of the concession awards. ESRRP will be required to submit a performance bond of US$60,000 that covers approximately 20% of the
expected phase one exploration program.
The terms of the concessions are such that ESR-RP will retain the Concessions so long as the jointventure actively conducts exploration, evaluation, mining or mine-closure activities within the
Concession.
Detailed mapping and sampling will be undertaken to fully identify mineral occurrences on surface
within the Mining Concessions and will be combined with further consultation with the local population
as to the possible next stages of exploration.
Further exploration will consist of airborne geophysical surveys followed by ground geophysics and
eventually drilling if warranted. It is not possible at this stage to say how these additional work phases
will unfold given the open nature of mineral potential in the area.
Estrella very much looks forward to working with the Timor-Leste Government, MRT, the Autoridade
Nacional Minerais, local communities and with our Timor-Leste contacts to build a strong and
successful minerals exploration and development sector.
CARR BOYD NICKEL PROJECT
Pegmatite field discovered
In November, Estrella reported the discovery of a significant field of stacked, fractionating pegmatites in
the Eastern tenements at Carr Boyd as part of an ongoing review at the project. 6 The review was
undertaken due to unsolicited approaches from third parties to evaluate the potential of Carr Boyd tenure
hosting LCT-type pegmatites.
6 Refer to ASX announcement dated 10 November 2023
Figure 6: Fractionated pegmatite from Carr Boyd East containing Albite (70%) + Quartz (25%) + Rb Muscovite (5%) and
Zinnwaldite (trace %).7
The pegmatites, which so far have been observed up to 16m in width (Figure 7), can be traced across
the surface for a few hundred metres before being obscured by the alluvial sediments that cross the
majority of the area. Locations of where the pegmatites can be seen outcropping on surface is shown
in Figure 8.
The Carr Boyd Rocks Monzogranite partially intrudes the northern section of the Carr Boyd layered
mafic intrusion. Monzogranites are associated with other Western Australian lithium deposits and this
precedence is an important factor in assessing the positive potential of Estrella’s tenure to host LCT
pegmatites.
7 It should be noted that this information simply shows fractionated pegmatites exist with potentially favourable geochemistry,
however there is no information as to their prospectivity for LCT minerals at this stage and is not a proxy for laboratory assay.
Figure 7: Extensive, fractionating pegmatites located in the eastern tenements at Carr Boyd
Figure 8: Location of outcropping, fractionated and stacked pegmatite fields in relation to the Carr Boyd
monzogranites, area of quartz sub-crop and float and site infrastructure
Associated with the monzogranite is a 14km long by 9km wide area of surficial quartz and pegmatite
float material within alluvial and colluvial sediments (Figure 8). The northern section of the
sedimentary plains consists of shallow cover through which numerous fractionated pegmatites can be
seen outcropping.
The outcropping pegmatites can be traced for a few hundred metres before going beneath the cover
again. Preliminary findings are that the fractionates are occurring in a late east-west fracture set
developed off a main north-south corridor of more granitic material.
The pegmatite mineralogy observed in the field is dominantly feldspar (>70%) with the majority of that
being albite with minor plagioclase and microcline. Muscovite is common and in several areas they
contain a green hue and are enriched in rubidium (analysis by portable Bruker XRF). Zinnwaldite has
been observed in field specimens indicating higher degrees of pegmatite fractionation. The pegmatites
show fairly clear zonation and a dominantly megacrystic texture.
It should be noted that this information simply proves extensive and thick, fractionated pegmatites
exist however there is no assay information as to their prospectivity for LCT minerals at this stage and
is not a proxy for laboratory assay.
A more complete mapping and sampling program has been initiated and is underway across the
tenements. A targeted soil sampling program will then follow to guide further exploration.
Estrella took a series of rock-chip samples and sent them to ALS Laboratories for sodium hydroxide
fusion analysis. The assays have been returned and the company is analysing the results. Lithium
was generally low from the surface rock samples with a peak assay of 169 ppm Li. Rubidium peaked
at 0.7%, tantalum at 178 ppm and Caesium at 169 ppm. Further analysis of the trends clearly show
fractionation away from the granites and follow-up work for areas under transported cover is being
considered.
New Nickel Targets Identified
Preliminary results from a TargetEM survey undertaken in August across Carr Boyd identified multiple
first and second order bedrock-conductor anomalies including over a 5km strike length of the Colreavy
Komatiite and a new 3km linear zone under cover to the south of the Carr Boyd Intrusion.8
Figure 9: First and second order bedrock anomalism identified by the recent TargetEM survey at Carr Boyd
The TargetEM system contains many structural, electrical, and software improvements over previous
helicopter-borne EM systems that have greatly improved the sensitivity and depth of investigation.
The resulting bedrock anomalism identified by the system correctly located known nickel-coppersulphide mineralisation at T5, Carr Boyd and Broonhill. There is no real difference between first and
second order anomalies save for second order anomalies have surface effects which partially mask
the anomaly.
The electromagnetic response from zones of known stringer sulphide such as at Tregurtha and POH
can be seen in the data, however more processing is needed to isolate those true anomalies from
other potential ground effects, enabling new but more subtle anomalies to be identified. Processing of
the data by Expert Geophysics and Southern Geoscience is ongoing.
On-ground investigation of the anomalies reveal that many of them relate to areas of interest identified
by the recent exploration review, which combined multiple data-sets with research conducted by the
CSIRO in 2022. The resulting internal and external basal contact positions (Figure 10) show some
correlation to the identified anomalism and further refinement of the exploration model and targeting
can now take place.
8 Refer to ASX announcement dated 5 October 2023
Figure 10: Recently proposed internal and external prospective contacts at the Carr Boyd Nickel Project
Further processing and refinement of the TargetEM and Audio-Frequency-Magnetic time-domain
(AFMAG) data will continue to enable more subtle anomalism to be drawn out of the data.
The Company has most of the regulatory approvals in place to commence drilling and has submitted
additional approvals to explore outlying areas such as the Eastern Pyroxenite. Additional target
ranking and budgeting has commenced so that an un-interrupted work program going forward can be
commenced.
The Carr Boyd Project will remain as key exploration asset of the Company and management are
exploring avenues for recommencement of active exploration activities at the site. In the interim we
are maintaining the site under a full-time caretaker and have reduced operating costs where possible.
The Company continues to investigate the introduction of a partner on the project and will keep
shareholders informed if any binding agreements are executed.
SPARGOVILLE NICKEL PROJECT
PFS and DFS Update
During the quarter, Estrella reported that an Interim Prefeasibility Study for the 5A deposit at its
Spargoville project demonstrates the viability of an underground nickel mine. 9
The interim PFS report reflects a step towards the completion of our Definitive Feasibility Study (DFS)
and outlines a compelling opportunity with detail on the costs associated with establishing a mining
operation. However, some commercial terms remain outstanding which prevent Estrella from providing
further detail to a DFS-level.
The report outlines a small-scale mining operation of a high-grade resource body which presents an
ideal operation for a company of Estrella’s current size. Key findings from the interim PFS include:
•
•
•
•
•
•
•
Successful trial parcel to Glencore HPAL confirms maximum recovery processing pathway
Simple decline and 2 level underground mine with long-hole stoping over 6-month time-frame
Probable Reserve of 1043t Ni metal and 24t Co metal from 28kt of mined material
Ongoing discussions with respect to devising optimal operational scenarios
Total estimated capital and operating cost AU$11.0M, or US$3.20/lb Ni for project life- costs
estimates are within +/- 25% and study assumes a USD/AUD XR of 0.67
Total project life of 10 months including crushing and haulage
Underground decline and stope design undergoing final optimisation
9 Refer to ASX announcement dated 16 October 2023.
•
•
Short-list of preferred contractors selected
Mining and Environmental approvals in progress assisted by MBS Environmental
Estrella is currently curtailing any further work on the 5A Nickel Project due to a significant
deterioration of the nickel market and projected outlook remaining unfavourable. Resources are being
directed toward other projects both locally and offshore in Timor-Leste.
Figure 12: Proposed Cutback, decline and stope design for the 5A Nickel Mine
CORPORATE
CAPITAL
The Company’s cash balance as at 31 December 2023 was $1.239m. During the quarter, Estrella
raised $1.65 million through a placement of 275,000,000 shares at an issue price of $0.006 per share
to professional and sophisticated investors. 10 Funds from the placement will be primarily used to
investigate the lithium potential of the Company’s Carr Boyd Project tenure, continuing activities at Carr
Boyd Ni/Cu Project, as well as general working capital.
The total amount paid to related parties of Estrella and their associates, as per item 6.1 of the Appendix
5B, was 82k for Directors fees, salaries and superannuation and the total amount paid to related parties
of Estrella and their associates, as per item 6.2 of the Appendix 5B, was $43k for Director’s salaries.
Table 1: Estrella Capital structure as at 31 December 2023
Fully Paid Ordinary Shares
1,759,371,869
Listed options exercisable
325,300,000
Unlisted options exercisable
70,750,000
Performance Rights
36,000,000
EXPLORATION
ASX Listing Rule 5.3.1: Exploration and Evaluation Expenditure during the Quarter was $247k.
ASX Listing Rule 5.3.2: There were no mining production and development activities during the Quarter.
ASX Listing Rule 5.3.3: Refer to Appendix 1 for Estrella Tenement Information.
10 Refer to ASX announcement dated 20th October 2023.
ENDS
The Board of Directors of Estrella Resources Limited authorised this announcement to be given to ASX.
FURTHER INFORMATION CONTACT
Christopher J. Daws
Managing Director
Estrella Resources Limited
info@estrellaresources.com.au
P: +61 (08) 9481 0389
Media Contact:
David Tasker
Chapter One Advisors
Email: dtasker@chapteroneadvisors.com.au
Tel: 0433 112 936
Compliance Statement
With reference to previously reported Exploration Results and Mineral Resources, the Company confirms that it is
not aware of any new information or data that materially affects the information included in the original market
announcement and, in the case of estimates of Mineral Resources, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not
materially changed. The Company confirms that the form and context in which the Competent Person’s findings
are presented have not been materially modified from the original market announcement.
Forward Looking Statements
Forward-looking statements are statements that are not historical facts. Words such as "expect(s)", "feel(s)",
"believe(s)", "will", "may", "anticipate(s)" and similar expressions are intended to identify forward-looking
statements. These statements include, but are not limited to statements regarding future production, resources or
reserves and exploration results. All of such statements are subject to certain risks and uncertainties, many of which
are difficult to predict and generally beyond the control of the Company, that could cause actual results to differ
materially from those expressed in, or implied or projected by, the forward-looking information and statements. Our
audience is cautioned not to place undue reliance on these forward-looking statements that speak only as of the
date hereof, and we do not undertake any obligation to revise and disseminate forward-looking statements to reflect
events or circumstances after the date hereof, or to reflect the occurrence of or non-occurrence of any events.
Appendix 1 – Tenement Information as Required by Listing Rule 5.3.3
Change in
Holding (%)
Current
Interest (%)
Country
Location Project
Tenement
Australia
WA
Carr Boyd Nickel Project
E29/1012
-
100
Australia
WA
Carr Boyd Nickel Project
E29/0982
-
100
Australia
WA
Carr Boyd Nickel Project
L24/0186
-
100
Australia
WA
Carr Boyd Nickel Project
E31/0726
-
100
Australia
WA
Carr Boyd Nickel Project
E31/1124
-
100
Australia
WA
Carr Boyd Nickel Project
M31/0012
-
100
Australia
WA
Carr Boyd Nickel Project
M31/0109
-
100
Australia
WA
Carr Boyd Nickel Project
M31/0159
-
100
Australia
WA
Carr Boyd Nickel Project
E31/1215
-
100
Australia
WA
Carr Boyd Nickel Project
E31/1162
-
100
Australia
WA
Spargoville Nickel Project
M15/395
Australia
WA
Spargoville Nickel Project
M15/703
Australia
WA
Spargoville Nickel Project
M15/1828
Australia
WA
Spargoville Nickel Project
L15/128
Australia
WA
Spargoville Nickel Project
L15/255
*Nickel rights only
-
100*
100*
100*
100*
100*
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Estrella Resources Limited
ABN
Quarter ended (“current quarter”)
39 151 155 207
31 December 2023
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
Year to date (6
months)
$A’000
-
-
(a) exploration & evaluation
-
-
(b) development
-
-
(c) production
-
-
(d) staff costs
(107)
(199)
(e) administration and corporate costs
(196)
(323)
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
3
5
1.5
Interest and other costs of finance paid
(102)
(102)
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
-
-
1.9
Net cash from / (used in) operating
activities
(402)
(619)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
(10)
(10)
(d) exploration & evaluation
(247)
(970)
(e) investments
-
-
(f)
-
-
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date (6
months)
$A’000
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
R&D expenditure refund
1,327
1,327
1,070
347
1,652
1,652
2.6
Net cash from / (used in) investing
activities
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
(145)
(145)
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
(1,044)
(1,044)
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
-
-
3.10
Net cash from / (used in) financing
activities
463
463
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
108
1,048
Net cash from / (used in) operating
activities (item 1.9 above)
(402)
(619)
Net cash from / (used in) investing activities
(item 2.6 above)
1,070
347
4.2
4.3
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Current quarter
$A’000
Year to date (6
months)
$A’000
Net cash from / (used in) financing activities
(item 3.10 above)
463
463
Effect of movement in exchange rates on
cash held
-
-
1,239
1,239
Consolidated statement of cash flows
4.4
4.5
4.6
5.
Cash and cash equivalents at end of
period
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
1,239
108
5.2
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
1,239
108
6.
Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
82
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
43
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding
Share your feedback