Carr Boyd Exploration Update
Released
Released
Announcement PDF
ASX:ESR
17 November 2023
Carr Boyd Geophysical Survey Update
HIGHLIGHTS
➔ Processing of the next-generation helicopter-borne Audio-Frequency-Magnetic survey continues to
identify areas prospective for nickel sulphides
➔ Resistivity Depth Imaging (RDI) data received provides greater understanding of orientation and
location of the anomalies first identified via the TargetEM survey
➔ Colreavy Komatiite and Carr Boyd host rocks successfully identified and imaged to 600m depth
(Figure 1)
➔ Data processing and drill targeting work underway with further survey data anticipated
Figure 1: RDI slice through 6672920 North showing the Colreavy Komatiite and Carr Boyd Pyroxenite as
interpreted from the AFMAG data along with bedrock conductors identified from the TargetEM system
Estrella Resources Limited (ASX: ESR) (Estrella or the Company) is pleased to announce further results
from the world-first time-domain Audio-Frequency-Magnetic (AFMAG) survey conducted at the Company’s
Carr Boyd Nickel Project, approximately 80km NNW of Kalgoorlie in Western Australia 1.
1 See ASX Announcement dated: 22 June 2023
_________________________________________________________________________________
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103
Email info@estrellaresources.com.au
Leading survey technology group Expert Geophysics continue to process the data acquired at the Carr
Boyd project in August 2023 and most recently have delivered a series of Resistivity Depth Imaging (RDI)
sections throughout the survey area.
The AFMAG survey uses highly sensitive equipment to identify differentiation in electrical resistivity,
seeking to identify anomalies which may indicate the potential for economic deposits of nickel sulphides.
The project’s highly prospective host rocks, namely the Carr Boyd pyroxenite and Colreavy komatiite,
exhibit relatively low levels of resistivity when compared to other rock-types found within the project and
the survey has successfully mapped the low-resistance areas in three dimensions.
The RDI sections are interpreted to reveal the project geology to a depth of around 600 metres below
surface and provide greater detail on the orientation of the anomalies first identified through Expert
Geophysics’ initial TargetEM survey2.
Estrella is now able to interpret that the Colreavy komatiite appears to dip towards the east, while the Carr
Boyd pyroxenite plunges vertically, see cross-sections in Figures 1 & 2.
The RDI data will be used in conjunction with the previous seismic survey and current TargetEM bedrock
anomalism to model the Carr Boyd intrusion’s internal basal contacts to prioritise drill-ready targets.
Figure 2: RDI slice through 6672920 North showing the Colreavy Komatiite and Carr Boyd Pyroxenite
2 See ASX Announcement dated: 4 October 2023
Commenting on the survey data, Estrella Managing Director Chris Daws said:
“In another fantastic result following the introduction of Expert Geophysics to the Carr Boyd project, Estrella
Resources has now gained further detailed information to develop precise drill targets to unlock further nickel
sulphide deposits.
The RDI data is a fantastic tool for exploration as the survey is capable of monitoring a greater range of
electrical resistivities than any other time-domain system currently available in the market. This means we
have industry-leading vision of our highly prospective host rocks.
We are dealing with high levels of contrast between the low-resistance host rocks and other high-resistance
rocks, such as granite, within the project. As a result, we can map the prospective rocks in three dimensions,
with a strong degree of certainty.
Further processing and refinement of the TargetEM and Audio-Frequency-Magnetic time-domain data is
anticipated, but even this first batch of data is highly useful as we continue to map out the next stage of
exploration at Carr Boyd.”
Figure 3 below shows the interpreted internal and mapped external basal contacts through the project area
and how these correlate to the recent bedrock anomalism identified by the TargetEM survey.
Updates from Expert Geophysics will continue to be received as more information is extracted from the
recent acquisition.
The Company is in discussions regarding the Carr Boyd Project area and will inform shareholders if/when
any materially binding agreements have been reached.
Figure 3: Correlation between internal and external basal contacts and the bedrock anomalies identified by the recent
TargetEM survey
The Board has authorised for this announcement to be released to the ASX.
FURTHER INFORMATION CONTACT
Christopher J. Daws
Managing Director
Estrella Resources Limited
+61 8 9481 0389
info@estrellaresources.com.au
Media:
David Tasker
Managing Director
Chapter One Advisors
E: dtasker@chapteroneadvisors.com.au
T: +61 433 112 936
Competent Person Statement
The information in this announcement relating to Exploration Results is based on information compiled by Steve Warriner,
who is the Exploration Manager of Estrella Resources, and a member of The Australasian Institute of Geoscientists. Mr.
Warriner has sufficient experience relevant to the style of mineralisation and type of deposit under consideration, and to
the activity he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code
for Reporting of Exploration Results, Mineral Resource and Ore Reserves”. Mr Warriner consents to the inclusion in the
report of the matters based on their information in the form and context in which it appears.
Forward Looking Statements
This announcement contains certain forward looking statements which have not been based solely on historical facts
but, rather, on ESR’s current expectations about future events and on a number of assumptions which are subject to
significant uncertainties and contingencies many of which are outside the control of ESR and its directors, officers and
advisers.
APPENDIX 1 JORC TABLE 1 – CARR BOYD EXPLORATION
Section 1 - Sampling Techniques and Data
Criteria
Sampling
techniques
JORC Code explanation
• Nature and quality of sampling (e.g. cut
channels, random chips, or specific specialised
industry
standard
measurement
tools
appropriate to the minerals under investigation,
such as down hole gamma sondes, or handheld
XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of
sampling.
• Include reference to measures taken to ensure
sample representivity and the appropriate
calibration of any measurement tools or
systems used.
• Aspects of the determination of mineralisation
that are Material to the Public Report. In cases
where ‘industry standard’ work has been done
this would be relatively simple (e.g. ‘reverse
circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to
produce a 30 g charge for fire assay’). In other
cases more explanation may be required, such
as where there is coarse gold that has inherent
sampling problems. Unusual commodities or
mineralisation types (e.g. submarine nodules)
may warrant disclosure of detailed information.
Drilling
techniques
•
Drill type (e.g. core, reverse circulation, openhole hammer, rotary air blast, auger, Bangka,
sonic, etc) and details (e.g. core diameter, triple
or standard tube, depth of diamond tails, facesampling bit or other type, whether core is
oriented and if so, by what method, etc).
Drill sample
recovery
•
Method of recording and assessing core and
chip sample recoveries and results assessed.
Measures taken to maximise sample recovery
and ensure representative nature of the
samples.
Whether a relationship exists between sample
recovery and grade and whether sample bias
may have occurred due to preferential loss/gain
of fine/coarse material.
•
Whether core and chip samples have been
geologically and geotechnically logged to a
level of detail to support appropriate Mineral
Resource estimation, mining studies and
metallurgical studies.
Whether logging is qualitative or quantitative in
nature. Core (or costean, channel, etc)
photography.
The total length and percentage of the relevant
intersections logged.
•
•
•
Logging
•
•
•
Sub-sampling
techniques
•
If core, whether cut or sawn and whether
quarter, half or all core taken.
•
If non-core, whether riffled, tube sampled,
Commentary
•
ESR drilling included diamond core - half core
samples with a maximum of 2m and minimum
0.25m length. DD core samples have been
half cut with an automatic core saw.
•
Core is cut and sampled to ensure the sample
is representative and no bias is introduced.
Cutting of specific, banded or stringer
sulphide zoned core is done orthogonal to the
banding to ensure there is no bias.
•
Determination of mineralisation has been
based on geological logging, visual sulphide
estimates and confirmation using a pXRF
machine. Samples were dispatched to an
accredited laboratory for multi-element
analysis.
•
Diamond core drilling was used to obtain 6m
length samples from the core barrel which are
then marked in one metre intervals, based on
core block measurements and core recovery.
•
Samples are selected based on geological
logging boundaries or on nominal meter
marks. Collected samples weigh a nominal 23 kg (depending on sample length). Samples
have been dispatched to an accredited
commercial laboratory in Perth for analysis.
•
Samples are being analysed using a 4-acid
digest, ME- ICP for 33 elements and all
samples are also being tested for Au & PGE
elements using ICP analysis.
•
Drilling was undertaken using NQ2 sized drill
core.
•
Holes have been collared with mud rotary
from surface, HQ rough cored to top of fresh
rock then NQ2 cored to EOH.
•
•
•
•
•
•
•
•
Core recovery was recorded by the field crew
and verified by the geologist.
RQD measurements were digitally recorded to
ensure recovery details were captured.
Sample recovery in all mineralised zones is
high with negligible core loss observed.
Diamond core drilling is the highest standard
and no relationship has been established
between sample recovery and reported grade
as the core is in very good condition.
Detailed industry standard of collecting core
in core trays, marking metre intervals and
drawing core orientation lines were
undertaken.
Core trays were photographed wet and dry
prior to sampling.
Prior to 2021 drill hole logs were recorded in
Excel spread sheets and validated in
Micromine
Software
as the
drilling
progressed.
In 2021 a digital logging system, Logchief,
was implemented which validates data as it is
recorded and uploads that data remotely to a
centralised database.
The entire length of all holes are logged.
Core is half cut using an automatic core saw
to achieve a half-core sample for laboratory
submission.
The
sample
preparation
_________________________________________________________________________________
Criteria
and sample
preparation
Quality of
assay data
and
laboratory
tests
Verification of
sampling and
assaying
JORC Code explanation
rotary split, etc and whether sampled wet or dry.
• For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
• Quality control procedures adopted for all subsampling stages to maximise representivity of
samples.
• Measures taken to ensure that the sampling is
representative of the in situ material collected,
including for instance results for field
duplicate/second-half sampling.
• Whether sample sizes are appropriate to the
grain size of the material being sampled.
• The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or
total.
• For geophysical tools, spectrometers, handheld
XRF instruments, etc, the parameters used in
determining the analysis including instrument
make and model, reading times, calibrations
factors applied and their derivation, etc.
• Nature of quality control procedures adopted
(e.g. standards, blanks, duplicates, external
laboratory checks) and whether acceptable
levels of accuracy (i.e. lack of bias) and
precision have been established.
Commentary
technique is considered industry best
standard practice.
•
No field duplicates have been collected for
DD holes. Field duplicates will be collected
once initial results are returned and
resampling of the mineralised zones is
warranted.
•
Sample sizes are appropriate to the grain size
of the mineralisation.
•
•
•
•
•
Location of
data points
•
•
•
Data spacing
and
distribution
•
•
•
The verification of significant intersections by
either independent or alternative company
personnel.
The use of twinned holes.
Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
Discuss any adjustment to assay data.
•
•
•
•
•
•
•
Prior to 2021 drill hole logs were recorded in
Excel spread sheets and validated in
Micromine
Software
as
the
drilling
progressed.
In 2021 a digital logging system, Logchief,
was implemented which validates data as it is
recorded and uploads that data remotely to a
centralised database hosted by Maxgeo.
Hole CBDD028 is twinning hole CBP042. No
other twinning is warranted at this stage.
•
No adjustments
undertaken.
Accuracy and quality of surveys used to locate
drill holes (collar and down-hole surveys),
trenches, mine workings and other locations
used in Mineral Resource estimation.
Specification of the grid system used.
Quality and adequacy of topographic control.
•
Data spacing for reporting of Exploration
Results.
Whether the data spacing and distribution is
sufficient to establish the degree of geological
and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation
procedure(s) and classifications applied.
Whether sample compositing has been applied.
•
For drill collars, RC and DD holes were
surveyed with DGPS equipment using the
MGA94, Zone 51 coordinate system. Mineral
Resource estimation was carried out on this
grid.
Topography is relatively flat and control is
more than adequate given the early stage of
the project. A 3D drone ortho-photographic
survey has been used to create a DTM of the
project area.
Drill data spacing of all drill data is sufficient
to establish the degree of geological and
grade continuity appropriate for estimating a
Mineral Resource.
Drill hole spacing ranges from 10m by 10m in
the most well-drilled portion of the deposit and
broadens to approximately 40m by 80m over
the remaining areas. Spacing is adequate to
establish the degree of geological and grade
continuity for estimating a Mineral Resource.
Samples were composited to 1m lengths prior
to Mineral Resource estimation.
The geometry of drill holes relative to the
mineralised zones achieves unbiased
sampling of this deposit type.
No orientation-based sampling bias has been
identified.
•
•
•
Orientation of
data in
relation to
geological
structure
Samples are selected based on geological
logging boundaries or on nominal meter
marks. Collected samples weigh a nominal 23 kg (depending on sample length). Samples
have been dispatched to an accredited
commercial laboratory in Perth for analysis.
Samples are being analysed at Intertek and
ALS Laboratories in Perth using a 4-acid
digest, ME- ICP for 33 elements and all
samples are also being tested for Au & PGE
elements using ICP analysis.
For ESR drilling, QAQC included Certified
Reference Material (CRM’s) and blank
(Blanks) samples inserted at the laboratory.
Whether the orientation of sampling achieves
unbiased sampling of possible structures and
the extent to which this is known, considering
the deposit type.
If the relationship between the drilling
orientation and the orientation of key
•
•
to
assay
data
were
Criteria
Sample
security
Audits or
reviews
JORC Code explanation
mineralised structures is considered to have
introduced a sampling bias, this should be
assessed and reported if material.
• The measures taken to ensure sample security.
Commentary
•
•
The results of any audits or reviews of sampling
techniques and data.
•
Samples are in the possession of ESR
personnel from field collection to laboratory
submission in Kalgoorlie.
No independent audit or review has been
undertaken.
Section 2 - Reporting of Exploration Results
Criteria
Mineral
tenement and
land tenure
status
Exploration
done by other
parties
JORC Code explanation
• Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint ventures,
partnerships, overriding royalties, native title
interests, historical sites, wilderness or national
park and environmental settings.
• The security of the tenure held at the time of
reporting along with any known impediments to
obtaining a license to operate in the area.
• Acknowledgment and appraisal of exploration
by other parties.
Commentary
•
Carr Boyd Nickel Pty Ltd (a wholly owned
subsidiary of ESR) holds a 100% interest in
the nickel and base metal rights to the project.
•
All of the tenements are current and in good
standing.
•
•
•
•
•
•
•
•
•
•
The Carr Boyd Rocks deposit was discovered
by Great Boulder Mines, in a joint venture with
North Kalgurli Ltd in 1968. The deposit was
mined between 1972 and 1975, during which
time they explored for additional breccia pipe
occurrences near the mine.
WMC acquired Great Boulder Mines Ltd in
1975, briefly reopening the mine in 1977
before closing it permanently shortly
thereafter due to a collapse in the nickel price.
The mine had produced 210,000t at 1.44% Ni
and 0.46% Cu before its closure.
From 1968 Pacminex Pty Ltd held most of the
ground over the CBLC outside of the
immediate mine area.
Between 1968 and 1971 they conducted
extensive exploration programs searching for
large basal contact
and/or stratabound Ni-Cu deposits. It was
during this time that most of the disseminated
and cloud sulphide occurrences such as
those at Tregurtha, West Tregurtha and
Gossan Hill were discovered.
Defiance Mining acquired the regional
tenements from Pacminex in 1987 and
focused on exploration for PGE deposits
between 1987 and 1990. In 1990 Defiance
purchased the Carr Boyd Rocks mine from
WMC and switched focus to the mine area
between 1990 and 2001, leaving many PGE
targets untested.
From 1990 Defiance dewatered the mine to
conduct testwork and feasibility studies on
the remnant mineralisation. Metallurgical
testwork, Mineral Resource estimations, and
scoping studies were completed. Around
1996 the focus shifted again to regional
exploration for large tonnage basal contact
deposits.
In 2001 Titan Resources Ltd (Titan) acquired
the project and recommenced economic
evaluations of the remnant material at Carr
Boyd Rocks before embarking on another
regional exploration program focusing on the
basal contact.
An aeromagnetic survey,
airborne EM reprocessing, and several
programs of RAB and RC drilling were
completed.
From 2005 Yilgarn Mining entered a JV with
Titan and continued with some regional
exploration but focused most attention in and
around the Carr Boyd Rocks mine.
In 2007 Titan was acquired by Consolidated
Minerals Ltd (Consmin). Consmin conducted
IP surveys and detailed gravity surveys but
did not drill any targets before selling the
project to Salt Lake Mining (SLM) in 2013.
SLM completed limited drilling to meet
expenditure commitments, before selling the
project to Apollo Phoenix Resources in 2016.
Criteria
JORC Code explanation
Geology
•
Drill hole
information
• A summary of all information material to the
under-standing of the exploration results
including a tabulation of the following
information for all Material drill holes:
• easting and northing of the drill hole collar
• elevation or RL (Reduced Level – elevation
above sea level in metres) of the drill hole
collar
• dip and azimuth of the hole
• down hole length and interception depth
• hole length
• If the exclusion of this information is justified on
the basis that the information is not Material and
this exclusion does not detract from the
understanding of the report, the Competent
Person should clearly explain why this is the
case.
• In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (e.g. cutting of high
grades) and cut-off grades are usually Material
and should be stated.
Data
aggregation
methods
Deposit type, geological setting and style of
mineralisation.
Commentary
•
Apollo sold the project to ESR in 2018.
•
The Project lies within the Achaean Yilgarn
Craton in a 700km belt of elongate deformed
and folded mafic, ultramafic rocks and
volcanic sediments intruded by granitoids
which is referred to as the Norseman-Wiluna
Belt. The belt has been divided into several
geological distinct terranes, with the project
area lying at the northern end of the Gindalbie
terrane (Swager, 1996). The geology of the
Carr Boyd area is dominated by the Carr
Boyd mafic-ultramafic intrusive complex
(“CBIC”).
•
Several distinctive styles of Ni and Ni-Cu
mineralisation have been identified within the
CBIC. At the Carr Boyd Rocks Nickel Mine NiCu mineralisation is hosted within several 20
to 60m diameter brecciated pipe-like bodies
that appear to be discordant to the magmatic
stratigraphy. Mineralisation is hosted by a
matrix of sulphides (pyrrhotite, pentlandite,
pyrite and chalcopyrite) within brecciated
bronzite and altered country rock clasts.
•
Stratiform Ni-Cu-PGE mineralisation has
been identified at several different locations
within the layered magmatic complex.
•
ESR is in the process of re-mapping and
reclassifying the Carr Boyd Igneous
Complex. Previous “Layered Intrusive”
models are misleading as the complex is
made up of many overprinted and
juxtaposed, smaller layered and non-layered
intrusives that have progressed from
ultramafic to mafic over time. The complex is
better described as a magma feeder zone,
where the earliest melts passing through the
Morelands Formation have assimilated
graphitic sulphidic shales, reached sulphur
saturation and deposited nickel sulphides
along basal contacts.
•
These basal contacts are not restricted to the
base of the complex, but can form within the
complex, wherever access was gained by
these earlier flows.
•
The complex has then been intruded and
inflated over time by progressively more
mafic, barren magmas to produce what we
see today.
• Exploration results with all relevant drillhole
information are reported in the body of the
text.
• All drill hole information relevant to this
resource report/statement has been included
in the appendices. No relevant drill hole
information has been excluded.
•
•
Exploration results with all relevant drillhole
information are reported in the body of the
text.
Significant Grade Intersections are reported on
a 0.5% Ni cut-off
Criteria
Relationship
between
mineralisation
widths and
intercept
lengths
Diagrams
Balanced
Reporting
Other
substantive
exploration
data
Further work
JORC Code explanation
• Where aggregate intercepts incorporate short
lengths of high grade results and longer lengths
of low grade results, the procedure used for
such aggregation should be stated and some
typical examples of such aggregations should
be shown in detail.
• The assumptions used for any reporting of
metal equivalent values should be clearly
stated.
• These relationships are particularly important in
the reporting of Exploration Results.
• If the geometry of the mineralisation with respect
to the drill hole angle is known, its nature should
be reported.
• If it is not known and only the down hole lengths
are reported, there should be a clear statement
to this effect (e.g. ‘down hole length, true width
not known’).
Commentary
• Composite assay grades are determined by
geology and nickel-copper-sulphur content.
• Assays are length and SG weighted when
calculating
average
grades
over
an
intersection.
• Metal equivalent values have not been used.
• Appropriate maps and sections (with scales)
and tabulations of intercepts should be included
for any significant discovery being reported.
These should include, but not be limited to a
plan view of drill hole collar locations and
appropriate sectional views.
• Accuracy and quality of surveys used to locate
drill holes (collar and down-hole surveys),
trenches, mine workings and other locations
used in Mineral Resource estimation.
• Where comprehensive reporting of all
Exploration Results is not practicable,
representative reporting of both low and high
grades and/or widths should be practiced to
avoid misleading reporting of Exploration
Results.
• Other exploration data, if meaningful and
material, should be reported including (but not
limited to): geological observations; geophysical
survey results; geochemical survey results; bulk
samples - size and method of treatment;
metallurgical test results; bulk density,
groundwater,
geotechnical
and
rock
characteristics;
potential
deleterious
or
contaminating substances.
•
Relevant diagrams have been included within
the Mineral Resource report main body of
text.
•
All new drillhole information within this
announcement is reported
•
•
•
•
No other substantive data exists.
Everything meaningful and material is
disclosed in the body of the report.
Geological observations are included in the
report.
No bulk samples, metallurgical, bulk density,
groundwater, geotechnical and/or rock
characteristics test were carried out.
There are no known potential deleterious or
contaminating substances.
Further work by ESR may include a Scoping
Study for the T5 Mineral Resource estimate.
Refer to diagrams in the body of text within
the Mineral Resource report.
Diamond drilling and DHTEM geophysical
testing is continuing.
•
The nature and scale of planned further work
(e.g. tests for lateral extensions or depth
extensions or large- scale step-out drilling).
Diagrams clearly highlighting the areas of
possible extensions, including the main
geological interpretations and future drilling
areas, provided this information is not
commercially sensitive.
•
•
•
•
•
•
•
Most drill holes were angled to 060° or 270°
so that intersections were orthogonal to the
orientation of mineralisation.
True widths have been stated where possible
however, the variable orientation of
mineralisation
within magma
feeders
combined with a structural overprint and
steep drill angles make true width
calculations highly misleading.
Section 3 Estimation and Reporting of Mineral Resources
Criteria
Database
integrity
JORC Code explanation
• Measures taken to ensure that data has not
been corrupted by, for example, transcription or
keying errors, between its initial collection and
its use for Mineral Resource estimation
purposes.
• Data validation procedures used.
Site visits
•
•
Geological
interpretation
•
•
•
•
•
Comment on any site visits undertaken by the
Competent Person and the outcome of those
visits.
If no site visits have been undertaken indicate
why this is the case.
Confidence in (or conversely, the uncertainty
of) the geological interpretation of the mineral
deposit.
Nature of the data used and of any
assumptions made.
The effect, if any, of alternative interpretations
on Mineral Resource estimation.
The use of geology in guiding and controlling
Mineral Resource estimation.
The factors affecting continuity both of grade
and geology.
Commentary
•
The data for this Mineral Resource estimate
was collected and logged using Excel
spreadsheets and validated using Micromine
Software. The data will be loaded into an
externally hosted and managed database.
•
It is assumed that due care was taken
historically with the process of transcribing
data from field notes into digital format for
statutory annual reporting.
•
All assays were reported by laboratories in
digital format reducing the likelihood of
transcription errors.
•
No site visit has been conducted by the
Competent Person, due to the level of study
so far conducted at the Project.
•
•
•
•
•
Dimensions
•
Estimation
and modelling
techniques
•
•
•
•
•
•
•
•
•
The extent and variability of the Mineral
Resource expressed as length (along strike or
otherwise), plan width, and depth below
surface to the upper and lower limits of the
Mineral Resource.
The nature and appropriateness of the
estimation technique(s) applied and key
assumptions, including treatment of extreme
grade
values,
domaining,
interpolation
parameters and maximum distance of
extrapolation from data points. If a computer
assisted estimation method was chosen
include a description of computer software and
parameters used.
The availability of check estimates, previous
estimates and/or mine production records and
whether the Mineral Resource estimate takes
appropriate account of such data.
The assumptions made regarding recovery of
by-products.
Estimation of deleterious elements or other
non-grade variables of economic significance
(e.g. sulphur for acid mine drainage
characterisation).
In the case of block model interpolation, the
block size in relation to the average sample
spacing and the search employed.
Any assumptions behind modelling of selective
mining units.
Any assumptions about correlation between
variables.
Description of how the geological interpretation
was used to control the resource estimates.
Discussion of basis for using or not using grade
cutting or capping.
•
•
•
•
•
•
The
confidence
in
the
geological
interpretation is considered to be good and is
based predominantly on ESR diamond
drilling.
Geochemistry and geological logging has
been used to assist identification of lithology
and mineralisation.
The Project consists of steep east dipping
lodes, striking approximately north-south.
The current interpretation is considered
robust.
Structural observations on diamond core
confirm the geometry of the mineralisation.
Recent drilling by ESR has confirmed the
geological and
Share your feedback
Discover