12 November 2026
Werumata Limestone Scoping Study Confirms Robust Large-
Scale Development Opportunity
Engage with this announcement on our interactive Investor Hub
HIGHLIGHTS
• Scoping Study for the Werumata Limestone project in Timor-Leste outlines a compelling
development opportunity via open cut mine, mechanical crushing and port facility
• Low life-of-mine OPEX of US$7.89/t FOB (Free On Board, a sale price excluding shipping and
insurance)
• Low CAPEX for start-up (Stage 1, operation of ~8 Mtpa) of US$117 million (Including contingency)
• Base Case after-tax and pre-financing NPV10 of US$1,453 million representing an IRR of 46%
and payback period of 3.5 years
• Staged, capital-light development designed to reach cashflow quickly and then grow largely from
a self-funding base with:
o Stage 1: a start-up operation of ~8 Mtpa, constructible in approximately six-months;
o Stage 2 (Base Case of this study): expansion to 25 Mtpa through additional berths for large
bulk carriers, with construction following Stage 1 through 2029 and ramp-up to full capacity
by early 2030.
o Stage 3: a future expansion to 50 Mtpa (or more), treated as upside and subject to market
demand
• Base Case 20-year mine life determined based on Updated JORC (2012) Mineral Resource of
533 Mt, comprising 274 Mt Indicated and 259 Mt Inferred, with approximately 51% classified as
Indicated.1
• Total CAPEX of US$476 million for Base Case developments, with peak funding requirement of
US$363 million.
• Sales price of US$20/t FOB reflects strong economics under conservative assumptions with
sensitivity analysis determining even Stage 1 development at a reduced US$15/t FOB clears
Estrella's minimum 20% IRR threshold.
• Development anchored by a signed Master Agreement with PT Raka Energi Mandiri (REM) for
Indonesian offtake, with the scoping-study conditions precedent now satisfied.
• Study identifies no fatal flaws and will assist in the advancement of the Project. Commencement
of a Feasibility Study will be subject to Board approval.
1 Refer to ASX announcement dated 15th
October 2026
ASX: ESR
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
Cautionary Statement – Scoping Study
This announcement contains the results of a Scoping Study on the Werumata Limestone Project ("Project").
The Scoping Study referred to in this announcement is a preliminary technical and economic study of the
potential viability of the Project. It is based on low-level technical and economic assessments, including AACE
International Class 5 (conceptual) capital and operating cost estimates with an expected accuracy range of
the order of -20% to -50% on the low side and +30% to +100% on the high side, and is not sufficient to
support the estimation of Ore Reserves or to provide assurance of an economic development case at this
stage. There is no certainty that the conclusions of the Scoping Study will be realised.
The Mineral Resource underpinning the Scoping Study is classified 51% Indicated Resource and 49% and
Inferred Mineral Resources under the JORC Code (2012) over the life of mine. There is a low level of
geological confidence associated with Inferred Mineral Resources, and there is no certainty that further
exploration work will result in the determination of Indicated or Measured Mineral Resources, or that the
production target itself will be realised. It is also uncertain whether further exploration, evaluation and studies
will result in the estimation of an Ore Reserve, or that the economic development case set out in this
announcement will ultimately be realised.
The Mineral Resource estimate of 533 Mt referred to in this announcement was reported by the Company in
its ASX announcement dated 15 October 2026, titled "MRE Update - Werumata Limestone Project," which
is available on the ASX Market Announcements Platform. The Company confirms that it is not aware of any
new information or data that materially affects the information contained in that announcement, and that all
material assumptions and technical parameters underpinning the Mineral Resource estimate continue to
apply and have not materially changed.
The production target and forecast financial information referred to in this announcement, including the
estimated capital cost, revenue, EBITDA, NPV and IRR for the base case (Stage 2, 25 Mtpa), are based on
the Scoping Study and, as such, are subject to ASX Listing Rules 5.16 and 5.17. All material assumptions
underpinning the production target and the forecast financial information derived from it are set out elsewhere
in this announcement. While the Company considers all the material assumptions to be based on reasonable
grounds, there is no certainty that they will prove to be correct, or that the range of outcomes indicated by
the Scoping Study will be achieved.
The Company confirms that it has a reasonable basis for providing the forward-looking statements included
in this announcement, and will update the market in accordance with its continuous disclosure obligations
under ASX Listing Rules if that basis ceases to apply.
To achieve the range of outcomes indicated in the base case of the Scoping Study, total capital of
approximately US$476 million (including contingency) is estimated, with a peak funding requirement of
approximately US$363 million. No debt or equity funding has been secured for the Project, and investors
should note that there is no certainty the Company will be able to raise the required funding when needed,
or on terms that are not dilutive to, or otherwise adverse to the value of, the Company's existing shares.
The marketing strategy referred to in this announcement is underpinned by a Master Agreement with PT
Raka Energi Mandiri, which operates as a framework only. No binding, bankable sales contract has been
executed, and realised price is the variable to which the Project's economics are most sensitive. The Project
also requires a mining licence, environmental licensing, and maritime and port approvals, none of which have
yet been obtained.
Further exploration and evaluation work, and appropriate studies, are required before the Company will be
in a position to estimate any Ore Reserves, secure binding offtake, obtain the necessary approvals, or provide
any assurance of an economic development case, or certainty that the conclusions of the Scoping Study will
be realised.
Given the uncertainties involved, and in particular that the Scoping Study is based on 51% Indicated Mineral
Resources and 49% Inferred Mineral Resources, investors should not make any investment decisions based
solely on the results of the Scoping Study.
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
Commenting on the completion of the Study, Managing Director Robert Mencel said:
"This Scoping Study confirms Werumata as a genuinely significant development opportunity for Estrella
Resources and more broadly for the nation of Timor-Leste.
“The key takeaway for all parties is that this project is valued at close to US$1.5 billion in net present
value from a series of conservative assumptions with a resource we've only just begun to define.
“Importantly, our recently upgraded Mineral Resource now stands at 533 million tonnes, including 274
million tonnes in the Indicated category. With approximately 70% of our higher-value acid-neutralisation
product now classified as Indicated, we have a strong geological foundation for the proposed
development, particularly in the areas targeted for initial mining.
“Estrella has established a staged development program to best take advantage of our highest grade and
purity mineralisation, funding subsequent increases in scale.
“This proposed development plan at Werumata is assisted by some excellent tailwinds. Limestone is a
fundamental industrial commodity and our resource is particularly well suited to some of its highest-value
applications, principally acid neutralisation for the mining and metals sector, and as a metallurgical flux in
blast furnaces or copper/nickel smelting. High-purity material from Werumata is well suited to these
applications and allows us to target premium pricing for our early production rather than simply competing
on volume.
"We're also supported by our strategic location. Werumata and its associated port are located in the heart
of South-East Asia which is one of the fastest-growing limestone markets in the world, driven by rapid
industrialisation and urbanisation across the region. Our largest identified customer base, which is
Indonesia's nickel processing industry, sits right on our doorstep, enhancing margins and accelerating
return on capital.
"Following this initial Study, we're now in a position to move into much more substantive discussions with
the Government of Timor-Leste on approvals, as well as advance prospective offtakers beyond our
existing Master Agreement.
“Moreover, additional drilling at Werumata is planned as part of our forward work programme as well as
further detailed study work to meet our ambitious target of reaching FID by Q4 2027.
"It’s also worth adding that Werumata is highly complementary to our existing portfolio of other
development assets. As a long-life, low-technical-risk production opportunity, it lets us deploy capital
strategically to not only develop this asset but also continue targeting immediate areas of value creation.
For example, by backing our current drill-out plans for our high-growth targets like the Laleno Dome,
where our copper porphyry exploration is showing considerable promise.
“Werumata is shaping up as a highly exciting development option and I encourage shareholders to review
this report in detail to understand the scale of the opportunity which sits before them."
Scoping Study – Executive Summary
Project Overview
The Scoping Study (the "Study") for the Werumata Limestone Project (the "Project") was prepared by
Valleyspring Pty Ltd, drawing on specialist input from AGP Mining Associates (mine planning, cost estimation
and economic analysis), PT Rexline Engineering Indonesia (materials handling, port and infrastructure
design), and ASEAMCO Pty Ltd (JORC Mineral Resource estimation, mine design and scheduling). The
Study is prepared to an AACE International Class 5 (conceptual) standard.
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
The Project lies near the villages of Binagua and Werumata on the north coast of Timor-Leste, 33 km by road
from Baucau and about 150 km from the capital, Dili. Estrella holds eleven Exploration and Evaluation
concessions over approximately 512 km², granted by the Autoridade Nacional dos Minerais ("ANM"), the
mining regulatory authority of Timor-Leste.
Figure 1: Werumata Limestone Project location, north coast of Timor-Leste
The project area sits on a narrow coastal strip, with the limestone hills hosting the Mineral Resource rising
immediately inland (Figure 2). The updated JORC (2012) Mineral Resource, reported as at 15 October 2026,
totals 533 Mt, comprising 274 Mt Indicated and 259 Mt Inferred, at an average acid-neutralising capacity of
66.0%. Approximately 51% of the Resource is classified as Indicated, including 70% of the higher-value acid-
neutralisation product.
The Scoping Study mine plan, production schedule and financial evaluation have been prepared using the
updated Mineral Resource Estimate. The updated Resource supports the proposed start-up and Base Case
development scenarios, with the mine plan and financial evaluation to be updated during the Feasibility
Study.
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
The Project comprises of a conventional open-pit mine using hydraulic
excavators and haul trucks, extracting the Resource in a series of
terraces advancing from the coastal plain southward into the hills.
Mined limestone is crushed and screened by mechanical means only,
with no chemicals or reagents are used in processing. The materials
handling system comprises ROM stockpiles, up to five crushing and
screening plants, crushed product stockpiles, reclaim conveyors, and
multiple rail-mounted shiploaders rated at 3,000tph each, providing a
combined Stage 2 loading capacity of 12,000tph.
A purpose-built, staged export port will also be constructed
immediately adjacent to the mine, taking advantage of a naturally deep
nearshore profile. The port develops in four stages: Early Works
(mobile equipment for trial/sample shipments), Stage 1 (~8Mtpa,
single berth to 30,000 Deadweight Tonnage (DWT)), Stage 2
(~25Mtpa, multiple berths up to 100,000 DWT plus provision for larger
vessels), and Stage 3 (blue-sky expansion to 50Mtpa+).
Figure 2: Visible Limestone Sheeting at Werumata
Figure 3: Modelled Port General Arrangement, Stage 2 (~25 Mtpa)
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
Key Development and Financial Metrics
Mine development is staged to match market growth and to minimise up-front capital at risk:
• Stage 1 — an ~8Mtpa start-up operation, constructible in approximately six months, enabling early
sales and cashflow;
• Stage 2 (Base Case) — expansion to 25Mtpa (the Study's base case), via additional deep-water
berths; and
• Stage 3 — a blue-sky expansion to 50Mtpa or more, subject to market demand, and not included in
the base case economics.
The updated 533 Mt Mineral Resource supports the proposed development scenarios and the Scoping Study
mine plan provides for 465 Mt of saleable limestone over a 20-year period.
No Ore Reserve has been declared, and the Project's economic estimates remain at scoping-study level.
Further infill and extension drilling is planned to improve resource confidence and assess additional resource
potential.
Total capital for Stage 1 and Stage 2 is estimated at approximately US$476 million including contingency,
spent progressively across the staged build. The maximum cash investment, being the peak the Project must
fund before it becomes self-funding, is lower at approximately US$363 million, because part of the Stage 2
capital is met from Stage 1 cashflow. Life-of-mine average operating cost is approximately US$7.89 per
tonne of product FOB, against an assumed US$20 per tonne FOB sales price.
The estimates are AACE International Class 5 (conceptual), with an expected accuracy range of the order of
-20% to -50% on the low side and +30% to +100% on the high side.
Table 1: Investment and Returns
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
The Project's three distinct saleable products are differentiated by acid-neutralising capacity (ANC) and grade
with the initial sales focus on the higher-quality end of the product suite. Estrella intends to sell the highest-
grade material first in order to support start-up revenues and early cash flows, and discussions with
customers to date support that strategy.
The updated Mineral Resource totals 533 Mt, with approximately 73% comprising higher-quality Product 1
limestone suitable for acid-neutralisation applications. Of the 391 Mt Product 1 Resource, 274 Mt
(approximately 70%) is now classified as Indicated.
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
Table 2: Updated JORC Mineral Resource by Product
Note: Resources are reported on a dry basis with the report’s 97% recovery factor to account for voids. Totals may differ due to
rounding. No Measured Resource or Ore Reserve is reported.
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
Limestone is a high-volume, low-unit-value commodity used in acid neutralisation, cement manufacture,
construction aggregates and fills, lime production, agriculture and a range of industrial applications. The
Project's principal volume market is Indonesia, where crushed limestone is used for the neutralisation of
waste acids and acid-containing tailings produced by the mining and metallurgical industries, in particular the
nickel processing industry.
Indonesia's nickel industry is the largest in the world and consumes very large and rapidly growing quantities
of limestone for this purpose. Regional demand for this single application is estimated at 25 Mtpa or more,
and it has emerged only recently as nickel processing capacity in Indonesia has expanded.
Table 3: Sensitivity to Sales Price
Project economics are most sensitive to realised price. At US$15/t FOB the base case remains viable (NPV
US$622 million, IRR 26%), while at US$25/t the NPV rises to approximately US$2.3 billion.
The 8 Mtpa start-up case is tighter than the base case but still clears Estrella's minimum 20% IRR threshold.
At the assumed US$20/t price it is expected to return an IRR of approximately 48%, and it remains above
the threshold at a reduced price of US$15/t FOB, returning approximately 21% with an NPV at 10% of
approximately US$120 million.
Actual prices collected in Indonesia, by application, are shown in Table 4. The wide range of prices is clearly
driven by product specification. A detailed study of the regional limestone market is recommended as part of
the next phase of study.
A product price of US$20/t FOB (real 2026 terms) is adopted for the base case evaluation, representing an
average across the product suite.
Higher-grade material, including the Sagadati area to be drilled, is expected to achieve of the order of
US$25/t, while lower-grade product is expected to realise of the order of US$17/t. Because the initial 8 Mtpa
is expected to comprise a higher proportion of high-grade product, the US$20/t average is considered
reasonable for the early years.
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
Table 4: Recent Export Sales Prices, Indonesia
Project Sales Strategy and Approvals
Estrella’s staged development strategy is anchored by a Master Agreement with PT Raka Energi Mandiri
("REM"), signed 9 May 2025. REM is a Jakarta-based Indonesian resources and energy investment group
with demonstrated capacity to originate and complete transactions.
Under the agreement:
• REM agrees to assist Estrella in the marketing and/or sale of limestone from the Estrella tenements;
and
• Estrella appoints REM, or its appointees, as offtaker and/or marketing agent with exclusive rights for
Indonesian customers, subject to the parties entering into an Offtake Agreement and to REM
achieving an annual sales target. Pricing will be agreed under that Offtake Agreement.
REM's incentive under the agreement is a grant of up to 500 million unlisted options in Estrella Resources
Limited, exercisable at A$0.05 and vesting at one option for each dry metric tonne sold, which ties REM's
return to tonnes actually shipped.
All resource, licensing and scoping-study conditions precedent are now satisfied in relation to the agreement
and the final condition requires the Company to obtain all permits, approvals and infrastructure required for
the export of product from a port in Timor-Leste.
Given its scale, the combined mine, materials-handling and port development is expected to be classified as
a Category A project, requiring a full Environmental Impact Assessment and public consultation process.
Estrella's current tenure provides the foundation from which a mining title application will be progressed
alongside environmental licensing, land access and maritime/port approvals, sequenced in parallel with the
Project's development schedule.
In addition to the agreement with REM, Estrella is in discussion with other potential offtakers seeking bulk
limestone supply. These include a major Japanese industrial and trading company operating globally, with
interests including steel and non-ferrous metals production, raw materials and metals trading, industrial
equipment and energy, whose interest is in limestone for acid neutralisation and metals production. These
discussions are preliminary and no binding commitment has been given by any party.
Key Milestones and Development Schedule
With the release of the full Scoping Study Report and the updated Mineral Resource incorporating 274 Mt of
Indicated material, the commencement of a Feasibility Study will be subject to board approval and
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
appropriate financing being available. The Board remains focused on its Copper and Manganese drilling and
exploration programs, and monetising its Manganese trial sample.
The Feasibility Study include updating the mine plan, production schedule and financial evaluation based on
further infill and extensional drilling, detailed engineering, environmental studies and progression of key
project approvals. Completion of the Feasibility Study and a Final Investment Decision remain targeted for
Q4 2027.
Early works are planned as part of Stage 1 that will be brought forward where practicable, comprising
construction of a coffer dam at the port site and the use of mobile shiploaders to despatch bulk market
samples to customers in Indonesia who have requested trial shipments.
The timing and scope of these works will be settled during the Feasibility Study. Stage 1 construction is
estimated at approximately six months from FID, placing first production and first revenue at approximately
8 Mtpa in Q3 2028, with Stage 2 construction starting no earlier than Q1 2029 and taking at least 12 months,
and ramp-up to the full 25 Mtpa capacity from 2030.
For further details please see the appended Werumata Limestone Project Scoping Study Full Report.
The Board has authorised this announcement for release to the ASX.
ENDS
FURTHER INFORMATION CONTACT
Robert Mencel
Managing Director
Estrella Resources Limited
+61 8 9481 0389
info@estrellaresources.com.au
Media:
David Tasker
Managing Director
Chapter One Advisors
dtasker@chapteroneadvisors.com.au
+61 433 112 936
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103 Email info@estrellaresources.com.au
Forward Looking Statements
This document may include forward-looking statements. Forward-looking statements include, but are not limited
to, statements concerning Estrella Resources Limited’s planned exploration program and other statements that
are not historical facts. When used in this document, the words such as "could," "plan," "expect," "intend," "may”,
"potential," "should," and similar expressions are forward-looking statements. Although Estrella believes that its
expectations reflected in these forward-looking statements are reasonable, such statements involve risks and
uncertainties and no assurance can be given that further exploration will result in the estimation of a Mineral
Resource.
Compliance Statement - Exploration Results and Mineral Resource Estimates
With reference to previously reported Exploration Results and Mineral Resources, the Company confirms that it
is not aware of any new information or data that materially affects the information included in the original market
announcement and, in the case of estimates of Mineral Resources that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not
materially changed. The company confirms that the form and context in which the Competent Person’s findings
are presented have not been materially modified from the original market announcement.
Estrella Confirms that Mineral Resource estimate referred to in this announcement was first reported by the
Company in its ASX announcement dated 14 May 2026, titled "Maiden Resource – Werumata Limestone
Project," and subsequently updated on 15 October 2026 “MRE Update – Werumata Limestone Project” which is
available on the ASX Market Announcements Platform. The Company confirms that it is not aware of any new
information or data that materially affects the information contained in that announcement, and that all material
assumptions and technical parameters underpinning the Mineral Resource estimate continue to apply and have
not materially changed.
Competent Persons Statement – Mineral Resource Estimates
The information in this report to which this statement is attached relates to the Mineral Resources for the
Werumata Limestone Project, and is based on information compiled by Mr Robert de Jongh BE Mining (Hons)
FAusIMM, Managing Director of ASEAMCO Pty Ltd. Mr de Jongh is a Fellow of The Australasian Institute of
Mining and Metallurgy and has sufficient experience that is relevant to the style of mineralisation and type of
deposit under consideration to qualify as a Competent Person as defined in the 2012 Edition of the JORC Code.
Mr Robert de Jongh consents to the inclusion in this announcement of statements based on this information in
the form and context in which it appears.
Werumata Limestone Project Scoping Study
CONFIDENTIAL: This Scoping Study contains confidential information of Estrella Resources Limited and may not be disclosed to third parties without
Estrella's prior written consent.
Page 1
Werumata Limestone Project
Scoping Study
Estrella Resources Limited (ASX: ESR)
November 2026
ISSUED FOR USE
Prepared by Valleyspring Pty Ltd
Werumata Limestone Project Scoping Study
CONFIDENTIAL: This Scoping Study contains confidential information of Estrella Resources Limited and may not be disclosed to third parties without
Estrella's prior written consent.
Page 2
DOCUMENT CONTROL
Revision Date Description Prepared Reviewed Approved
Rev 3 11
November
2026
Updated for the
ASEAMCO mining
schedule as at 23
October 2026. Draft
for Estrella review.
R. van Niekerk R. Mencel
ASEAMCO
AGP
R. Mencel
Werumata Limestone Project Scoping Study
CONFIDENTIAL: This Scoping Study contains confidential information of Estrella Resources Limited and may not be disclosed to third parties without
Estrella's prior written consent.
Page 3
IMPORTANT NOTICE AND DISCLAIMER
This Scoping Study has been prepared for Estrella Resources Limited (“Estrella”) for the
purposes of internal decision-making, the preparation of a summary for release to the ASX, and
use as a supporting document for the Business Plan to be submitted to the Government of
Timor-Leste.
The Study is a preliminary technical and economic assessment of the Werumata Limestone
Project. The capital and operating cost estimates presented herein are prepared to an AACE
International Class 5 (conceptual) standard as defined by Recommended Practice No. 47R-11,
with an expected accuracy range of the order of -20% to -50% on the low side and +30% to
+100% on the high side. The results are not a guarantee of project outcomes.
ASEAMCO’s Mineral Resource estimate as at 14 October 2026 comprises 274 Mt Indicated and
259 Mt Inferred. ASEAMCO’s mining schedule as at 23 October 2026 reports 317 Mt of
classified material within the scheduled mining sequence, comprising 158 Mt Indicated and
159 Mt Inferred, or approximately 50% in each category. The schedule comprises mining
increments rather than calendar years and does not define an annual production target. There
is a low level of geological confidence associated with Inferred Mineral Resources and there is
no certainty that further exploration work will result in the determination of Indicated Mineral
Resources or that the production target itself will be realised. No Ore Reserve has been
declared. Estrella, the relevant Competent Persons and its legal advisers must review the
production target, financial information and associated disclosures before public release.
Werumata Limestone Project Scoping Study
CONFIDENTIAL: This Scoping Study contains confidential information of Estrella Resources Limited and may not be disclosed to third parties without
Estrella's prior written consent.
Page 4
CONTENTS
Document Control................................................................................................................. 2
Important Notice and Disclaimer............................................................................................ 3
Definitions and Abbreviations............................................................................................... 12
1. Executive Summary...................................................................................................... 17
1.1. The Opportunity.................................................................................................... 18
1.2. The Project........................................................................................................... 19
1.3. T
Share your feedback
Discover