Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
QUARTERLY ACTIVITIES REPORT
Quarter ending 30 September 2025
HIGHLIGHTS
• Broad manganese observed at the Ira Miri project with results
including:
o EMDD033 intersected 12.87m of 80% manganese
oxides from 5.13m
o EMDD032 intersected 11.65m including 8.3m of 60%
manganese oxides from 5.1m
o EMDD034 intersected 8.5m of 30% Primary
Manganese Oxides in Chert from 8.3m
• First assays from initial holes demonstrate the presence of
high-grade mineralisation
o EMDD001 intersected 6.45m @ 51.7% Mn
o EMDD002 intersected 8.05m @ 53.0% Mn
o EMDD003 intersected 1.5m @ 35.8% Mn
• First modern hard rock exploration campaign in Timor-Leste’s
history continues with 3,000m of diamond and 10,000m of RC
manganese-focussed drilling planned. A secondary round to
consist of a further 10,000m RC drilling to be conducted after
geological review
• All necessary approvals and community consultation works
completed permitting commencement of maiden drilling at the
Werumata limestone project
• Werumata RC drill campaign to consist of 26 holes with
follow-up diamond and infill drilling planned to test a series of
highly prospective targets
• Estrella is targeting the development of a 500 million dry
metric tonne inferred Resource, representing a key condition
of a Master Agreement with an international mining services
partner which, if executed, will deliver exclusive marketing
and offtake rights
• Track and pad building underway and the commencement of
drilling is imminent
Estrella Resources Limited (ASX: ESR) (Estrella or the Company) is
pleased to provide its quarterly activities report for the period ending 30
September 2025. During the period, the Company made substantial
progress in the virtually unexplored region of Timor-Leste, unlocking
high-grade manganese mineralisation and also finalising preparations
for a major limestone drilling campaign (Figure 1).
ASX Release: 30 October 2025
Estrella Resources Limited
ABN 39 151 155 207
ASX Code: ESR
Board and Management
Managing Director
Christopher Daws
Non-Executive Directors
Les Pereira
John Kingswood
Company Secretary
Stephen Brockhurst
Benjamin Smith
Address
Level 8, London House
216 St Georges Terrace Perth
WA 6000
PO Box 2517 Perth WA 6831
Telephone: +61 8 9481 0389
Facsimile: +61 8 9463 6103
info@estrellaresources.com.au
www.estrellaresources.com.au
TIMOR-LESTE
Commenting on activities completed during the quarter, Managing Director Chris Daws said:
“Estrella has been rapidly advancing two complementary and highly prospective exploration programs
in Timor-Leste.
At our flagship Ira Miri manganese project, Estrella reported the first-ever modern exploration drilling
results in the nation’s history, producing exceptional discoveries. High-grade mineralisation was
reported in all three holes, while our trenching operations also encountered an additional shallow
manganese bed. These initial findings demonstrate the immense (and as-yet untapped) opportunity in
Timor-Leste.
These results were followed by further and even stronger findings from step-out drilling. In particular,
hole EMDD033 has intersected 12.87m of 80% manganese oxides from a depth of roughly 5m. We
are keenly awaiting formal assay results, but these initial observations are extremely encouraging.
In parallel, all necessary approvals and community consultation works have been completed at the
Werumata limestone opportunity. We interpret the project to host a large sheet of clean calcite, which
is of immense interest to Indonesia’s nearby nickel mining operations. Lime is a key commodity used
to improve environmental impact when processing ore. We believe the project may have significant
potential to generate returns for shareholders.
With two major drilling operations located on the doorstep of Asia’s largest economies, our team is just
getting started. Go Estrella!
Figure 1: Location of Estrella Resources’ Timor-Leste concessions
Exploration activities
In August, Estrella reported trenching operations had identified in-situ primary manganese bedding
within the Noni Formation that, when exposed by weathering and erosion, underwent significant
secondary enrichment1.
The enriched primary beds can be seen in Figure 2, where up to three parallel primary (hypogene) beds
have been mapped. Significant detrital material can be seen composed of remobilised boulders of
secondary-enriched Noni Formation along with re-cementation of the recent soils and detrital
manganese.
Figure 2: In-situ secondary enrichment manganese mineralisation identified during trenching1
Additional trenching is being planned to follow the sub-cropping primary zones along strike to the north
and to the south so as to enable accurate drill targeting of the mineralisation.
Following the identification of manganese in drilling and trenching, the Company announced the
commencement of a large-scale survey program consisting of LiDAR (Light Detection and Ranging),
drone-based magnetics and MobileMTd surveying to enhance geological modelling2.
Initial LiDAR surveying commenced at Werumata covering 1,700ha, flown on 100m-spaced lines at
~80m altitude. The program was overseen by TimorRai Exploration Services Lda in collaboration with
Enmintech (Figure 3).
LiDAR is a laser-based mapping technology capable of precisely measuring differences in surface
height and is required in order for the intended drilling to meet JORC compliance along with vital
planning information.
Estrella currently interprets the Werumata prospect to consist of a large sheet of high-purity limestone
and the LiDAR technology was used to identify subtle surface features like ridges, valleys or outcrops
to further refine the interpreted model and subsequent tonnage.
1
Refer to ASX Announcement dated: 15 August 2025
2
Refer to ASX Announcement dated: 28 August 2025
Following the completion of the survey, the geophysics team relocated to the Ira Miri manganese project
for a further 1,500ha of surveying.
The concessions at Ira Miri contain a series of manganese occurrences at surface with the Company
interpreting historical manganese bands within the Noni Formation that have become eroded over time.
These secondary supergene manganese occurrences are believed to have been relocated, moving
down-slope into local creeks where they can accumulate in thick layers.
The ability for LiDAR to detect not only current topographical lows but also signs of historical structures
is anticipated to enhance the Company’s predictive modelling for the locations of these secondary
manganese occurrences.
Figure 3: Done testing prior to the start of surveying at Werumata2
Subsequent to the completion of LiDAR surveying at Ira Miri, TimorRai Exploration Services oversaw a
drone-based electromagnetics campaign.
The magnetics survey saw the installation of sensitive magnetometer equipment to a drone which then
executed further flight lines across the project.
The magnetometer took a series of electromagnetic readings to identify anomalous variations in the
Earth’s magnetic field. Results are being analysed and the Company will seek to identify geological
contacts and potential structures (e.g. faults, folds) which control potential subsurface manganese
deposits.
These subsurface controls are anticipated to exhibit a distinct magnetic signature occurring from the
interaction between the magnetic nature of the Noni Formation manganese with the overlying
limestones, which are typically non-magnetic. Highly prospective targets will be mapped and compared
with the Company’s existing data sets, which include Induced Polarisation (IP) surveying, surface
prospecting and drilling/trenching results.
The Company also intends to supplement this geological data with results from the final stage of the
surveying program, which will consist of a magnetotellurics campaign (MobileMTd). The MobileMTd
campaign will see Expert Geophysics deploy specialty drone-mounted equipment, with the aim of
measuring electromagnetic resistivity fields across Ira Miri.
Unlike the drone magnetics, MobileMTd is specifically engineered to assess how well particular rock
formations conduct electricity and the technology can assess the depth and extent of conductive
manganese zones below surface.
Low resistive responses can be returned from a number of different geological features such as perched
water tables or clay zones. However, the Company and its consultants will be focused on identifying
distinct low-resistivity signatures returned from manganese-rich zones.
While each of the LiDAR, magnetics and MobileMTd surveys are anticipated to be beneficial to the
Company’s geological model, the combination of each of these methods is expected to provide a
detailed assessment of the most prospective locations, substantially improving drill targeting activities.
In September, Estrella announced the receipt of assays from the first three holes at the Company’s Ira
Miri prospect as well as further visual results from drilling3.
The Company’s maiden hole EMDD001 was drilled vertically into outcropping manganese and
successfully encountered thick mineralisation, however the hole ended in mineralisation due to technical
difficulties. The hole was subsequently twinned by EMDD002 to improve recovery of the friable
manganese oxides. Both holes intersected primary manganese with a thick zone of secondary
enrichment >50% Mn.
EMDD003 was drilled vertically approximately 15m to the north of EMDD001 and EMDD002 anticipating
a flatter supergene horizon between these two locations.
Table 1 below shows the significant assay intercepts.
Table 1: Significant results for EMDD001, EMDD002 and EMDD0033
Hole_ID mFrom mTo Interval Mn % Al2O3 % Fe2O3 % P % Si %
EMDD001 1.35 7.8 6.45 51.7 0.6 0.1 0.1 7.1
EMDD002 0.25 8.30 8.05 53.0 1.0 0.3 0.0 3.8
EMDD003 8.3 9.80 1.5 35.8 4.2 1.7 0.0 14.7
Subsequent trenching revealed several primary manganese horizons within the Noni Formation dipping
between 40 and 70 degrees to the north which are the source of the manganese. This mineralisation
has later been redistributed in the much flatter weathering profile and upgraded by secondary
processes.
EMDD022 and EMDD023 were the first in a series of angled holes which specifically targeted the
primary horizons and allowed the Company to project them up into the tertiary weathering zone where
the supergene enrichment first started. These zones were subsequently covered by more limestones
(the Coralline Limestone and Batu Putih Chalk) before being re-exposed in more recent times (Figure
4).
3
Refer to ASX Announcement dated: 4 September 2025
Figure 4: Stylised cross section looking Northwest representing the current target within the exploration model.3
Both EMDD022 and EMDD023 intersected secondary enrichment, and the visual estimates are shown
in Table 2.
Table 2: Visual estimates of EMDD022 and EMDD0233
Hole ID m From m To Description
EMDD022
0 1.7 Baucau Limestone
1.7 4.8 Noni Formation Muds
4.8 5 90% Manganese oxides
5 7.7 50% Manganese oxide, 50% clay
7.7 10 Noni Formation Chert
10 12.1 50% Manganese oxide, 50% clay
12.1 29.3 Noni Formation Chert
EMDD023
0 3.5 Baucau Limestone
3.5 5.15 Old alluvial cover
5.15 8.25 Noni Formation Muds
8.25 10.4 70% Manganese oxide, 30% clay
10.4 20.6 Noni Formation Chert
Cautionary Statement: The Company draws attention to uncertainty in reporting visual results. Visual estimates
of mineral abundance should never be considered a proxy or substitute for laboratory analyses where
concentrations or grades are the factor of principal economic interest. Visual estimates also potentially provide no
information regarding impurities or deleterious physical properties relevant to valuations.
The secondary enrichment interpretation of these intersections is shown in Figure 5.
Figure 5: Cross-Section 270115 East showing drilling at the first Ira Miri outcrop site and the interpreted outline of
intersected secondary manganese mineralisation
Drilling continued to yield further manganese discoveries, with the Company reporting further exciting
results throughout September4.
Drillholes EMDD024 to EMDD027 intersected primary manganese with secondary enrichment to the
west of the initial discovery zone (Figure 6) and the visual estimates are shown in Table 3 below.
4
Refer to ASX Announcement dated: 15 September 2025
Figure 6: Secondary and detrital manganese in EMDD026.
The secondary enrichment follows the trend of primary manganese deposited within the Noni Formation.
Although folded on the small scale, the primary mineralisation broadly follows a northwest trend.
Table 3: Visual estimates of EMDD024 to EMDD0274
Hole ID m From m To Interval Description
EMDD024
0 6 Baucau Limestone
6 7.8 Noni Formation Muds
7.8 8.6 0.8 15% Manganese oxide, 85% clay
8.6 35.4 Noni Formation Chert
EMDD025
0 1 Colluvium / Soil
1 3.5 2.5 70% Manganese oxides
3.5 10.5 Noni Formation Chert
EMDD026
0 1.4 Colluvium / Soil
1.4 4.5 3.1 60% Manganese oxides
4.5 35 Noni Formation Chert
EMDD027
0 1.4 Colluvium / Soil
1.4 3 1.6 30% Manganese oxides
3 8.2 Noni Formation Chert
Cautionary Statement: The Company draws attention to uncertainty in reporting visual results. Visual estimates
of mineral abundance should never be considered a proxy or substitute for laboratory analyses where
concentrations or grades are the factor of principal economic interest. Visual estimates also potentially provide no
information regarding impurities or deleterious physical properties relevant to valuations.
These results were followed by the Company’s broadest intersections to date with Estrella reporting the
success of seven diamond drillholes targeting the Ira Miri mineralisation (Figure 7)5.
Figure 7: Secondary manganese in core from EMDD033, looking from the bottom of the hole.
In particular, EMDD032 and EMDD033 both intersected greater than 11m and 12m of manganese
oxides respectively as is presented in Table 4 below.
Table 4: Visual estimates of EMDD028 to EMDD0335
Hole ID m From m To Interval Description
EMDD028
0 2.9 Colluvium / Soil / Limestone Cover
2.9 4.2 1.3 10% Manganese oxides, 90% clay
4.2 26.4 Noni Formation Chert
EMDD029
0 8.37 Colluvium / Soil / Limestone Cover
8.37 8.7 0.33 10% Manganese oxides, 90% clay
8.7 13.8 Noni Formation Chert
13.8 15.9 2.1 50% Manganese oxide, 50% clay
15.9 33.7 Noni Formation Chert
EMDD030 0 12.5 Colluvium / Soil / Limestone Cover
5
Refer to ASX Announcement dated: 22 September 2025
12.5 17.3 4.8 15% Manganese oxide, 85% clay
17.3 18.4 1.1 80% Manganese oxides, 20% clay
18.4 21.7 Noni Formation Chert
EMDD031
0 7.86 Colluvium / Soil / Limestone Cover
7.86 11.1 3.24 70% Manganese oxides, 30% clay
11.1 13.6 2.5 20% Manganese oxide, 80% Clay
13.6 15.9 Noni Formation Chert
15.9 17 1.1 15% Manganese oxide, 85% clay
17 21.7 Noni Formation Chert
EMDD032
0 5.1 Colluvium / Soil / Limestone Cover
5.1 11 5.9 50% Manganese oxide, 50% clay
11 13.4 2.4 90% Manganese oxides, 10% Clay
13.4 16.75 3.35 15% Manganese oxide, 85% clay
16.75 27.9 Noni Formation Chert
EMDD033
0 5.13 Colluvium / Soil / Limestone Cover
5.13 18 12.87 80% Manganese oxides, 20% clay
18 28.3 Noni Formation Chert
Cautionary Statement: The Company draws attention to uncertainty in reporting visual results. Visual estimates
of mineral abundance should never be considered a proxy or substitute for laboratory analyses where
concentrations or grades are the factor of principal economic interest. Visual estimates also potentially provide no
information regarding impurities or deleterious physical properties relevant to valuations.
These intersections are a continuation of the secondary enrichment following the trend of primary
manganese deposited within the Noni Formation. The weathering process has enriched the primary
manganese, increasing the manganese grade and widening the mineralised zone (Figure 8).
Figure 8: Cross section through EMDD004, EMDD032 to EMDD034 showing the location of primary and secondary
mineralisation which is open to the West.
Drilling will continue to chase the extents of mineralisation along strike within the supergene horizon just
below surface between two main areas of outcropping manganese located 450 metres apart. This line
is represented below in yellow in Figure 9.
Figure 9: Location of the mapped detrital and subcropping secondary manganese at Ira Miri along with the geological
boundary between the Noni Formation (manganese potential) and the underlying Triassic sediments. Drilling will be
following this outcropping trend to the northwest.
Limestone Drilling
At the end of September, Estrella announced the Timor-Leste Minerals Authority, Autoridade Nacional
dos Minerais (ANM) approved the Company’s Environmental Impact Statement and Environmental
Management Plan for drilling at the Werumata limestone project6.
The initial drill campaign will consist of 26 RC holes targeting a series of highly prospective limestone
targets with further follow-up stratigraphic diamond drilling and infill drilling to be completed, as required.
Estrella is targeting a JORC compliant resource of at least 500 million tonnes of limestone from an
interpreted calcite deposit located near the coast just south of the Uero-Mata Township (Figure 10).
Figure 10: Location of drilling at the Werumata Limestone Project
The Werumata project is located in proximity to the coast where a deep-water port development option
is available.
The Batu Putih (White Rock) and Baucau Limestones that outcrop over MEL2025-DA-ZA002 and
MEL2025-DA-ZA003 are stratigraphically above the Noni Formation. Any future drill testing of the
manganese potential of the Noni Formation will necessitate the drilling of the limestones, and vice versa.
This is a win-win for optimising exploration expenditure.
The stratigraphy responsible for this clean lime includes the Baucau Formation, which in places is
several hundred metres thick (source: Institute of Geology, Timor-Leste and Estrella’s stratigraphic
mapping). Ten samples from fresh sources of Baucau limestone within MEL2025-DA-ZA003 were
6
Refer to ASX Announcement dated: 29 September 2025
imported to Australia and assayed for their chemical and acid neutralisation content. The rock type is
known for its pure coral content which is reflected in the assays received in Table 57.
Table 5: Results from limestone sampling in MEL2025-DA-ZA003
Al2O3 CaO Fe2O3 K2O MgO P2O5 SO3 SiO2 CaCO3 Net Neutralisation
Potential
Sample ID % % % % % % % % % tCaCO3/1Kt
CBR114697 0.28 51.51 0.33 0.08 0.41 0.02 0.37 1.73 91.9 914
CBR114698 0.45 49.83 0.36 0.11 0.79 0.02 0.48 2.23 88.9 872
CBR114699 0.48 49.75 0.43 0.12 0.91 0.04 0.54 2.39 88.8 902
CBR114700 0.81 47.42 0.52 0.21 0.91 0.03 0.72 4.4 84.6 856
CBR114703 0.79 48.35 0.55 0.2 0.8 0.03 0.66 4.49 86.3 865
CBR114704 1.09 45.52 0.77 0.24 1.07 0.03 0.45 5.21 81.2 814
CBR114705 1.92 41.76 1.05 0.45 1.82 0.06 0.36 11.12 74.5 783
CBR114706 0.59 49.44 0.86 0.15 1.06 0.03 0.34 2.81 88.2 904
CBR114707 0.3 52.34 0.23 0.07 0.72 0.03 0.34 1.32 93.4 944
The Baucau limestone is predominantly calcite with a small but varying silica content and minor traces
of dolomite (calcium magnesium carbonate) and siderite (iron carbonate). The Neutralisation Value is a
calculation derived from acid-testing the samples and expressing the result as percent calcite (calcium
carbonate). In addition, the Batu Putih Limestone is mostly comprised of pure white chalk, which is
typically at least 95% fine-grained foraminiferal calcite, and thus highly effective for neutralizing acid, as
well as being useful for many industrial purposes.
The very high lime content, lack of impurities and excellent neutralisation potential of either the Baucau
or Batu Putih formations makes these rocks amenable to many industrial and environmental processes
where limestone is necessary, and Estrella will explore these opportunities across various Asian
markets.
Estrella has already established a Master Agreement with a leading Indonesian mining services
company PT Raka Energi Mandiri (“REM”), which following the satisfaction of a number of conditions
and timeframes will facilitate entry into a definitive Offtake Agreement8.
During the quarter, the Company announced an extension to a number of Milestone timelines9.
Under the variation to the Master Agreement, both parties have agreed to extend the milestone timelines
pursuant to the following:
• Estrella obtaining all material licenses, permits and approvals in respect of the mining and
export of limestone on Estrella’s mining concessions by 31 March 2026.
• Estrella announcing a JORC Code compliant resource of at least 500 million dry metric tons of
contained limestone on the Estrella Mining Concessions by 30 November 2025.
7
Refer to ASX Announcement dated 14 May 2025
8
Refer to ASX Announcement dated: 21 May 2025
9
Refer to ASX Announcement dated: 26 August 2025
• Estrella announcing the completion of a positive Scoping Study in relation to the Mining
Concessions by 30 January 2026; and
• Obtaining all permits, approvals for infrastructure required to export product extracted from the
mining concessions from a port facility in Timor-Leste, by 30 June 2026.
Under the variation to the Master Agreement both parties agree that all terms have the same meanings,
and that the variation does not affect any other terms as agreed to in the Master Agreement.
CORPORATE
CAPITAL
The Company’s cash balance as at 30 September 2025 was $4.4m
Throughout the Quarter, the Company issued 136,761,488 full-paid ordinary shares at $0.037 to raise
$5m (before costs), following shareholder approval on August 15 in line with the subscription agreement
between the Company and strategic investors announced 2 September 2024. The Company notes, the
amount was held on trust at June 2025, prior to shareholder approval. Company option holders also
converted 522,222 ESROB listed options at $0.018 to raise $10k throughout the quarter.
Total amount paid to related parties of Estrella and their associates, as per item 6.1 of the Appendix 5B,
was $76k for Directors fees, salaries and superannuation and the total amount paid to related parties of
Estrella and their associates, as per item 6.2 of the Appendix 5B, was $48k for Director’s salaries.
The Company continues to take steps to protect its legal rights and interests in the Mt Edwards Lithium
Royalty. The Board will protect these important assets of the Company and will be providing further
updates as material developments occur in accordance with the ASX Listing Rules and the Company’s
continuous disclosure obligations. Refer to ASX announcement dated 6 September 2024.
Table 6: Estrella Capital structure as at 30 September 2025
Fully Paid Ordinary Shares 2,198,251,574
Listed options exercisable 564,378,774
Unlisted options exercisable 30,250,000
Share Performance Rights 154,250,000
EXPLORATION
ASX Listing Rule 5.3.1: Exploration and Evaluation Expenditure during the Quarter was $1.644M.
ASX Listing Rule 5.3.2: There were no mining production and development activities during the Quarter.
ASX Listing Rule 5.3.3: Refer to Appendix 1 for Estrella Tenement Information. No changes to
tenements throughout the period.
ENDS
The Board of Directors of Estrella Resources Limited authorised this announcement to be given to ASX.
FURTHER INFORMATION CONTACT
Christopher J. Daws
Managing Director
Estrella Resources Limited
info@estrellaresources.com.au
P: +61 (08) 9481 0389
Media Contact:
David Tasker
Chapter One Advisors
Email: dtasker@chapteroneadvisors.com.au
Tel: 0433 112 936
Compliance Statement
With reference to previously reported Exploration Results and Mineral Resources, the Company confirms that it is
not aware of any new information or data that materially affects the information included in the original market
announcement and, in the case of estimates of Mineral Resources, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not
materially changed. The Company confirms that the form and context in which the Competent Person’s findings
are presented have not been materially modified from the original market announcement.
Forward Looking Statements
This announcement contains certain forward-looking statements which have not been based solely on historical
facts but, rather, on ESR’s current expectations about future events and on a number of assumptions which are
subject to significant uncertainties and contingencies many of which are outside the control of ESR and its directors,
officers and advisers.
Competent Person Statement
The information in this announcement relating to Exploration Results is based on information compiled by Steve
Warriner, who is the Group Exploration Manager of Estrella Resources, and a member of The Australasian Institute
of Geoscientists. Mr Warriner has sufficient experience relevant to the style of mineralisation and type of deposit
under consideration, and to the activity they are undertaking to qualify as Competent Persons as defined in the
2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resource and Ore Reserves”.
Mr Warriner consents to the inclusion in the report of the matters based on their information in the form and context
in which it appears.
Cautionary Statement:
The Company draws attention to uncertainty in reporting visual results. Visual estimates of mineral abundance
should never be considered a proxy or substitute for laboratory analyses where concentrations or grades are the
factor of principal economic interest. Visual estimates also potentially provide no information regarding impurities
or deleterious physical properties relevant to valuations.
Appendix 1 – Tenement Information as Required by Listing Rule 5.3.3
Country Location Project Tenement
Change
in
Holding
(%)
Current
Interest (%)
Australia
WA Carr Boyd Nickel Project E29/1012 - 100
Australia
WA Carr Boyd Nickel Project E29/0982 - 100
Australia
WA Carr Boyd Nickel Project L24/0186 - 100
Australia
WA Carr Boyd Nickel Project E31/0726 - 100
Australia
WA Carr Boyd Nickel Project E31/1124 - 100
Australia
WA Carr Boyd Nickel Project M31/0012 - 100
Australia
WA Carr Boyd Nickel Project M31/0109 - 100
Australia
WA Carr Boyd Nickel Project M31/0159 - 100
Australia
WA Carr Boyd Nickel Project E31/1215 - 100
Australia
WA Carr Boyd Nickel Project E31/1162 - 100
Australia
WA Carr Boyd Nickel Project E31/1381 - 100
Australia
WA Spargoville Nickel Project M15/395 - 100*
Australia
WA Spargoville Nickel Project M15/703 - 100*
Australia
WA Spargoville Nickel Project M15/1828 - 100*
Australia
WA Spargoville Nickel Project L15/128 - 100*
Australia
WA Spargoville Nickel Project L15/255 - 100*
Timor-Leste
Lautem Lautem Exploration Project MEL2023-CA-ZA001 - 100**
Timor-Leste
Lautem Lautem Exploration Project MEL2023-CA-ZA002 - 100**
Timor-Leste
Lautem Lautem Exploration Project MEL2023-CA-ZA003 - 100**
Timor-Leste Lautem Lautem Exploration Project MEL2025-DA-ZA001
(ex ESR-RP-01)
- 100
Timor-Leste Lautem Lautem Exploration Project MEL2025-DA-ZA002
(ex ESR-RP-02)
- 100
Timor-Leste Lautem Lautem Exploration Project
MEL2025-DA-ZA003
(ex ESR-RP-03)
- 100
Timor-Leste Lautem Lautem Exploration Project
MEL2025-DA-ZA004
(ex ESR-RP-04)
- 100
Timor-Leste
Lautem Lautem Exploration Project ESR-RP-05 - 100
Timor-Leste
Lautem Lautem Exploration Project ESR-RP-07 - 100
Timor-Leste
Lautem Lautem Exploration Project ESR-RP-08 - 100
Timor-Leste
Baucau Baucau Exploration Project MEL2024-DA-ZB001 - 100**
Timor-Leste
Baucau Baucau Exploration Project MEL2024-DA-ZB002 - 100**
Timor-Leste
Baucau Baucau Exploration Project MEL2024-DA-ZB003 - 100**
Timor-Leste
Baucau Baucau Exploration Project MEL2024-DA-ZB004 - 100**
* Nickel rights only
** Free carry Murak Rai Timor 30% up to publication of DFS or similar
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Estrella Resources Limited
ABN Quarter ended (“current quarter”)
39 151 155 207 30 September 2025
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (76) (76)
(e) administration and corporate costs (469) (469)
1.3 Dividends received (see note 3) - -
1.4 Interest received 11 11
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(534) (534)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment * - -
(d) exploration & evaluation (1,644) (1,644)
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material)
R&D expenditure refund - -
2.6 Net cash from / (used in) investing
activities
(1,644) (1,644)
*During the Dec quarter, March 2025 quarter and current quarter, the Company made down payments on
drilling/exploration equipment to be used in Timor Leste. This resulted in a loan/prepayment agreement in lieu
of exploration services with CoreSearch Minerals and Mining LDA as announced to ASX on 4 April 2025 (refer
for further detai