Laleno Dome - Drilling Update
Released
Released
Announcement PDF
16 November 2026
Maiden Laleno Dome Drilling Intersects Hydrothermally Altered
Porphyry – Manganese Shipping Window Confirmed
Engage with this announcement on our interactive Investor Hub
HIGHLIGHTS
• First four holes (416m) completed in the 23-hole maiden drilling program at the Laleno Dome
copper-gold prospect, Timor-Leste.
• LDR001A intersected hydrothermally altered porphyritic diorite, with alteration intensity
increasing downhole and trace sulphides logged towards the end of hole at 125m – the limit of
rig capacity.
• LDR003 intersected oxidised, copper-bearing ultramafic rock from surface to 3.5m
downhole (visual observation), beneath outcrop that returned copper in previous surface
sampling (ESR006488 – ESR006491)¹.
• 19 holes still to be drilled, including the highest-priority targets – among them the copper-
bearing porphyritic diorite previously sampled at surface (ESR006494, ESR006495 and
ESR006498)¹.
• Airborne MT/magnetic survey completed across Estrella’s concessions, with processing and
modelling expected to be completed in 6–8 weeks.
• More than 17,000 tonnes of manganese material delivered to the barge facility, with the
customer confirming a shipping laycan of 25 November to 2 December 2026.
Cautionary statement – visual observations: This announcement refers to visual observations of
sulphide and copper-bearing minerals in drill samples. Visual observations and estimates of mineral
abundance should never be considered a proxy or substitute for laboratory analysis. Laboratory assays
are required to determine the widths and grade of any mineralisation and to confirm its significance.
Samples will be submitted to a recognised laboratory in Indonesia, and the Company will update the
market when assay results are received.
Estrella Resources Limited (ASX: ESR) (Estrella or the Company) is pleased to report early progress
from its maiden drilling program at the Laleno Dome copper-gold prospect in Timor-Leste, together with
an update on its airborne geophysical survey and the planned shipment of its manganese bulk market
appraisal sample.
ASX: ESR
Estrella Managing Director Robert Mencel said:
“Putting the first drill holes into Laleno Dome is a milestone for Estrella, and the early signs are
encouraging. Our first hole into the porphyry target intersected hydrothermal alteration that strengthens
with depth, with sulphides appearing towards the end of the hole. That is the geological setting we set
out to test.
“It is early days. Assays are pending and visual observations are no substitute for laboratory results.
But with 19 holes still to drill, including our highest-priority copper targets, and the airborne geophysics
now being processed, shareholders can expect regular news flow over the coming weeks.
“At the same time, our manganese team has moved more than 17,000 tonnes to the barge facility and
our customer has confirmed the shipping window. Estrella is advancing on two fronts in Timor-Leste,
and I thank our team on the ground for the effort that has brought us here.”
Laleno Dome Maiden Drilling Program
The pre-Christmas program comprises 23 planned drill holes. Most are designed to test relatively
shallow targets, with three holes planned as pre-collars for future deeper drilling.
Drilling commencement was announced on 2 November 2026. Early progress was slowed by religious
and Timorese public holidays and an initial mechanical breakdown. Four holes have now been
completed for a total of 416m, at an average of approximately 46m per day. The drilling rate is expected
to improve as the program progresses.
Hole details are set out in Appendix 1. A summary of each hole drilled to date follows.
LDR001 – Drilled to test a porphyritic intrusion. The hole was abandoned at 71m after excess
groundwater damaged the collar and was re-drilled as LDR001A.
LDR001A (Figure 1) – Re-drill of LDR001, completed to 125m at the limit of rig capacity and available
rods. The hole intersected hydrothermally altered porphyritic diorite, with the intensity of alteration
increasing downhole and trace (less than 1%) disseminated sulphides (pyrite) logged towards the end
of the hole (103m - 115m and 119m – 121m). The presence of sulphides within increasingly altered
porphyry is consistent with the Company’s exploration model and is considered encouraging; its
significance will not be known until assay results are received.
LDR002 – Drilled to test a bed of manganese oxides and secondary copper mineralisation. The hole
was completed to 119m and passed through a sequence of sedimentary rocks without intersecting
significant visible mineralisation.
LDR003 – Drilled to test outcropping copper-bearing weathered ultramafic rock previously sampled at
surface (ESR006488 – ESR006491)¹. The hole was completed to 101m. Oxidised ultramafic rock with
traces (less than 1%) of copper minerals (malachite) intersected from surface to 3.5m downhole,
followed by weathered interbedded brown and grey mudstones to end-of-hole.
Figure 1: Drill rig set up on LDR001A, testing the porphyritic diorite that forms the hill.
Next Steps at Laleno Dome
Nineteen holes remain to be drilled in the current program. These include the Company’s highest-priority
targets, among them the copper-bearing porphyritic diorite previously sampled at surface as
ESR006494, ESR006495 and ESR006498¹, which the Company interprets as indicative of porphyry-
style copper mineralisation.
Samples from completed holes will be dispatched for analysis. Estrella will report assay results as they
are received, with receipt of initial results anticipated to be in the first week of December and will continue
to update shareholders as drilling advances.
Airborne Geophysical Survey Completed
The helicopter-supported airborne magnetotelluric (MT) and magnetic survey across all ground currently
held by Estrella was completed on 6 November 2026. Preliminary images show a number of anomalies
that warrant follow-up. However, the data is unprocessed, and reliable target definition depends on full
processing and modelling, which is expected to be completed in 6–8 weeks. Results will be reported
once that work is complete.
Manganese Export – Shipping Laycan Confirmed
Estrella has made strong progress towards export of its manganese bulk market appraisal sample. More
than 17,000 tonnes of manganese material have been transported to the barge facility in readiness for
loading (Figures 2 and 3). Video footage of the operation is available on Estrella’s Investor Hub.
The customer, Repusource Pty Ltd, has confirmed a shipping laycan of 25 November to 2 December
2026. The Company expects to receive the initial 10% deposit shortly and will advise the market once
loading is complete.
Figure 2: Oblique aerial view of manganese stockpiles under construction.
Figure 3: Stockpiles and the causeway under construction to assist barge loading.
¹ Refer to ASX announcement “Laleno Dome Copper-Silver-Gold Results” dated 29 September 2026.
This announcement has been authorised for release by the Board of Directors of Estrella Resources
Limited.
-ENDS-
About Estrella Resources Ltd
Estrella Resources Ltd has exploration projects and mineral rights in Western Australia but is currently
focussing its efforts on the exploration of its Timor Leste portfolio of tenements (known in Timor Leste
as “Concessions”).
Estrella concessions, Timor Leste, with currently developing prospects.
To-date, Estrella has discovered manganese mineralisation at several sites, with the Ira Miri deposit
having been excavated to extract a bulk sample to be sold as a market appraisal exercise. Exploration
for manganese continues.
In addition, Estrella has identified several occurrences of copper mineralisation and is actively pursuing
the growing copper and gold potential.
FURTHER INFORMATION CONTACT
Robert Mencel
Managing Director
Estrella Resources Limited
+61 8 9481 0389
info@estrellaresources.com.au
Media:
David Tasker
Managing Director
Chapter One Advisors
dtasker@chapteroneadvisors.com.au
+61 433 112 936
Forward Looking Statements
This document may include forward-looking statements. Forward-looking statements include, but are not limited
to, statements concerning Estrella Resources Limited’s planned exploration program and other statements that
are not historical facts. When used in this document, the words such as "could," "plan," "expect," "intend," "may”,
"potential," "should," and similar expressions are forward-looking statements. Although Estrella believes that its
expectations reflected in these forward-looking statements are reasonable, such statements involve risks and
uncertainties and no assurance can be given that further exploration will result in the estimation of a Mineral
Resource.
Compliance Statement - Exploration Results
With reference to previously reported Exploration Results, the Company confirms that it is not aware of any new
information or data that materially affects the information included in the original market announcement which
continue to apply and have not materially changed. The Company confirms that the form and context in which
the Competent Person’s findings are presented have not been materially modified from the original market
announcement.
Competent Person Statement - Exploration
The information in this announcement relating to Exploration Results is based on information compiled by Peter
Spitalny, who is the Exploration Manager, Timor Leste of Estrella Resources, and a Fellow of The Australasian
Institute of Mining and Metallurgy. Mr Spitalny has sufficient experience relevant to the style of mineralisation
and type of deposit under consideration, and to the activity they are undertaking to qualify as Competent
Persons as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral
Resource and Ore Reserves”. Mr Spitalny consents to the inclusion in the report of the matters based on their
information in the form and context in which it appears.
APPENDIX 1: Drill-collar details
Drillhole ID Easting (mE) Northing (mN) Elev. (m asl) declination azimuth EOH (m)
LDR001 267550 9070592 31 -60 330 71
LDR001A 267562 9070595 31 -60 330 125
LDR002 268143 9069640 45 -60 60 119
LDR003 269314 9066912 80 -60 170 101
APPENDIX 2: JORC TABLE 1
Section 1 - Sampling Techniques and Data
Criteria JORC Code explanation Commentary
Sampling
techniques
• Nature and quality of sampling (e.g. cut
channels, random chips, or specific specialised
industry standard measurement tools
appropriate to the minerals under investigation,
such as down hole gamma sondes, or handheld
XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of
sampling.
• Include reference to measures taken to ensure
sample representivity and the appropriate
calibration of any measurement tools or
systems used.
• Aspects of the determination of mineralisation
that are Material to the Public Report. In cases
where ‘industry standard’ work has been done
this would be relatively simple (e.g. ‘reverse
circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to
produce a 30 g charge for fire assay’). In other
cases more explanation may be required, such
as where there is coarse gold that has inherent
sampling problems. Unusual commodities or
mineralisation types (e.g. submarine nodules)
may warrant disclosure of detailed information.
• Samples are comprised of drill-cuttings of
1m intervals produced from RC (Reverse
Circulation percussion) drilling.
• Sample representivity is ensured through
use of a cone-splitter fitted under a
dumpbox beneath the receiving cyclone.
• Samples will be submitted to PT
Geoservices in Jakarta, Indonesia where the
entirety of each sample is to be pulverised,
from which a sample for geochemical
analysis is split and then analysed, using an
Aqua Regia digest followed by Inductively
Coupled Plasma Optical Emission
Spectrometry (ICPOES) and Fire Assay for
those samples in which Au exceeds
10ppm.
Drilling
techniques
• Drill type (e.g. core, reverse circulation, open-
hole hammer, rotary air blast, auger, Bangka,
sonic, etc) and details (e.g. core diameter, triple
or standard tube, depth of diamond tails, face-
sampling bit or other type, whether core is
oriented and if so, by what method, etc).
• The drilling method is Reverse Circulation
(RC) percussion drilling, which was used
to obtain 1m-interval samples, mass
approximately 3kg, collected from the
cone splitter beneath the dump box
under the collection cyclone.
• RC drilling used a 4 ¾ inch diameter face
sampling hammer.
Drill sample
recovery
• Method of recording and assessing core and
chip sample recoveries and results assessed.
• Measures taken to maximise sample recovery
and ensure representative nature of the
samples.
• Whether a relationship exists between sample
recovery and grade and whether sample bias
may have occurred due to preferential loss/gain
of fine/coarse material.
• RC sample recovery was qualitatively
assessed by comparing drill chip volumes
(sample bags) for individual meters.
Sample depths were routinely crossed
checked every rod (6m).
• The RC sample recovery was generally
satisfactory, only being reduced at the
commencement of the drill-hole and during
rod-change in intervals where significant
groundwater was encountered.
• This announcement does not discuss assay
results so no grades are known or if there is
any sample bias.
Logging • Whether core and chip samples have been
geologically and geotechnically logged to a
level of detail to support appropriate Mineral
Resource estimation, mining studies and
metallurgical studies.
• Whether logging is qualitative or quantitative in
nature. Core (or costean, channel, etc)
photography.
• The total length and percentage of the relevant
intersections logged.
• RC holes were logged in one-metre
intervals at the rig by the geologist,
through inspection of drill chips.
• Logging was recorded either on standard
logging descriptive sheets or directly into
Excel tables. Drill logs will be compiled into
an Access database.
• 100% of all 1-meter sample intervals were
geologically logged.
Criteria JORC Code explanation Commentary
Sub-sampling
techniques
and sample
preparation
• If core, whether cut or sawn and whether
quarter, half or all core taken.
• If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet or dry.
• For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
• Quality control procedures adopted for all sub-
sampling stages to maximise representivity of
samples.
• Measures taken to ensure that the sampling is
representative of the in-situ material collected,
including for instance results for field
duplicate/second-half sampling.
• Whether sample sizes are appropriate to the
grain size of the material being sampled.
• Single 1 metre splits were automatically
taken at the time of drilling through a cone
splitter attached beneath the dump box
under the cyclone.
• Typical sample mass is approximately 3kg,
which is considered adequate and
appropriate.
• Sample preparation will utilise industry
standard oven drying, crushing, and
pulverisation to 90% passing 75 um, from
which a sample for geochemical analysis
is split and then analysed.
Quality of
assay data
and
laboratory
tests
• The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or
total.
• For geophysical tools, spectrometers, handheld
XRF instruments, etc, the parameters used in
determining the analysis including instrument
make and model, reading times, calibrations
factors applied and their derivation, etc.
• Nature of quality control procedures adopted
(e.g. standards, blanks, duplicates, external
laboratory checks) and whether acceptable
levels of accuracy (i.e. lack of bias) and
precision have been established.
• Samples are analysed through method
ARA40_DG (Aqua Regia digest of 40g split
from pulp) followed by method
ARA40_AUSX determining concentration
of Au and a suite of 40 elements through
(Inductively Coupled Plasma Optical
Emission Spectrometry (ICPOES). For
those samples in which Au exceeds
10ppm, FAA40 (Fire Assay of a 40g
charge) is completed to provide greater
accuracy.
• Duplicates and Certified Reference Materials
(Blanks and “Standards”) have been inserted
into the sample stream, with a ratio of
approximately 10% of samples being QA/QC
samples.
• As assay results are not yet known, the
accuracy of results or presence of biases
are not known.
Verification of
sampling and
assaying
• The verification of significant intersections by
either independent or alternative company
personnel.
• The use of twinned holes.
• Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
• Discuss any adjustment to assay data.
• No prior modern exploration has been
conducted in the area, so there is no pre-
existing data to compare.
• Assay results are not discussed but it is
not intended that adjustments to assay
data received from the laboratory will
be undertaken.
Location of
data points
• Accuracy and quality of surveys used to locate
drill holes (collar and down-hole surveys),
trenches, mine workings and other locations
used in Mineral Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
• All sample locations have been
determined using a hand-held Garmin
GPS, accurate to +/- 1.8m in open ground.
• The grid system used is WGS-84,Zone
52S.
Data spacing
and
distribution
• Data spacing for reporting of Exploration
Results.
• Whether the data spacing and distribution is
sufficient to establish the degree of geological
and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation
• This announcement does not discuss
drilling results and cannot be used to
complete a Mineral Resource estimate.
Criteria JORC Code explanation Commentary
procedure(s) and classifications applied.
• Whether sample compositing has been applied.
Orientation of
data in
relation to
geological
structure
• Whether the orientation of sampling achieves
unbiased sampling of possible structures and
the extent to which this is known, considering
the deposit type.
• If the relationship between the drilling
orientation and the orientation of key
mineralised structures is considered to have
introduced a sampling bias, this should be
assessed and reported if material.
• The drilling is an early-stage initial
testing of targets and drill-hole spacing
and orientation are variable.
• The possibility of sampling bias due to
the orientation of drill-holes with
respect to bedding is unknown.
Sample
security
• The measures taken to ensure sample security. • Exported samples are kept in the
possession of ESR personnel from field
collection, through transport to Dili and
through completion of governmental
inspections (IGTL, ANM, Customs and
Quarantine) in Dili. Possession then
passes to Ceva Logistics, an
international courier that delivers the
samples to PT Geoservices in Jakarta,
Indonesia.
Audits or
reviews
• The results of any audits or reviews of sampling
techniques and data.
• No independent audit or review has
been undertaken at this stage.
Section 2 - Reporting of Exploration Results
Criteria JORC Code explanation Commentary
Mineral
tenement and
land tenure
status
• Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint ventures,
partnerships, overriding royalties, native title
interests, historical sites, wilderness or national
park and environmental settings.
• The security of the tenure held at the time of
reporting along with any known impediments to
obtaining a license to operate in the area.
• Exploration and Evaluation Licences
MEL2023-CA-ZA001, MEL2023-CA-ZA002 and
MEL2023-CA-ZA003 are awarded for four
years (26/03/2024 – 25/03/2028) to Estrella
Resources Representação Permanente, who
are exploring the concessions as a Joint
Venture (JV) project through the JV company
Estrella Murak Rai, comprised of Estrella
Resources Representação Permanente (70%)
and Murak Rai Timor (30%).
• Reconnaissance Permits ESR-RP-01, ESR-RP-
02, ESR-RP-03, ESR-RP-04, ESR-RP-05, ESR-
RP-06, ESR-RP-07 and ESR-RP-08 were
awarded to Estrella Resources Limited
Representação Permanente (100%).
Subsequently, ESR-RP-01 to ESR-RP-04 were
converted to Exploration and Evaluation
Licences MEL2024-DA-CA-ZA001 to
MEL2024-DA-CA-ZA004 respectively,
awarded for four years (14/05/2025 –
13/05/2025). ESR-RP-06 has been
relinquished but applications to convert ESR-
RP-05, ESR-RP07 and ESR-RP-08 into
Exploration and Evaluation Concessions have
been submitted; approval is pending.
• Exploration and Evaluation Licences
MEL2024-DA-CA-ZB001 to MEL2024-DA-CA-
Criteria JORC Code explanation Commentary
ZB004, awarded for four years (26/09/2024 –
25/09/2029) to Estrella Resources
Representação Permanente, who are
exploring the concessions as a Joint Venture
(JV) project through the JV company Estrella
Murak Rai, comprised of Estrella Resources
Representação Permanente (70%) and
Murak Rai Timor (30%).
• Estrella Resources Limited Representação
Permanente is registered in Timor-Leste and
is a wholly-owned subsidiary of Estrella
Resources Limited (Australia).
• All the Concessions (Exploration and
Evaluation Licences and Reconnaissance
Permits) are current and in good standing
Exploration
done by other
parties
• Acknowledgment and appraisal of exploration
by other parties.
• The first exploration was conducted by
Allied Mining Corporation in 1937 during
which mineral potential was discovered.
Very small-scale mining of manganese, gold
and construction material was conducted.
The exploration was not systematic and
hampered by difficult access.
• Other work in the early 2000’s has been
conducted by the Pacific Economic
Cooperation Council -PECC Minerals
Network to assist Timor-Leste to
understand and develop its minerals
potential.
• Local geologists and companies have
sporadically explored the area however
there has been no documentation collected
nor systematic exploration to quantify
mineral occurrences.
• Prior to Estrella, no minerals drilling had
taken place.
• Prior to Estrella, no close-spaced geophysics
had taken place.
• Prior to Estrella, no systematic, modern
exploration had taken place.
• The Geological Institute of Timor-Leste
(IGTL) has recently (and still is) conducting
stratigraphic analysis and fossil dating to
reconstruct the geological history of Timor-
Leste.
Geology • Deposit type, geological setting and style of
mineralisation.
• The current Concessions (EEL’s and RP’s)
host a range of types of mineralisation,
including manganese and copper and
associated elements.
• Within Estrella’s broad concession area,
copper mineralisation is recognised within
sedimentary, metamorphic and igneous
host rocks and presents in 3 styles.
• Sedimentary rock hosted copper
mineralisation is noted to occur at several
locations within the Noni Formation and
Criteria JORC Code explanation Commentary
appears to be stratiform. The origin of this
mineralisation is not yet certain and
classification is uncertain, as known
occurrences are highly weathered.
• Copper mineralisation has been identified in
porphyritic hydrothermally altered dioritic
rocks, likely representing high-level sub-
volcanic intrusions. This style of
mineralisation has the characteristics of
“porphyry copper” mineralisation.
• In addition, vein or vein-zone copper
mineralisation is present in a range of rocks,
commonly metamorphic rocks, and may
represent epithermal mineralisation
associated with the intrusions responsible
for the porphyry style mineralisation.
• Alluvial gold mineralisation has historically
been reported in the region but not verified.
• There are three main forms of manganese
mineralisation; primary mineralisation
formed in a marine environment from direct
precipitation of Manganese oxides onto the
sea floor. The mineralisation occurs as
layers of manganese oxide interbedded with
mudstone, thin lenses of sandstone, and
chert. Secondary mineralisation exists as a
supergene blanket above the interbedded
chert-manganese oxide unit where they
have been exposed to chemical weathering.
Tertiary mineralisation exists where high
rainfall and erosion has sorted and
concentrated detrital manganese into river
paleo-channels or scree deposits.
• Estrella will use and expand upon the
current known stratigraphy to evaluate and
document mineralisation styles and relate
them back to the tectono-stratigraphic
genesis of the area.
• The limestone potential is still being
investigated however the stratigraphy and
unit thicknesses are well known in the
literature. The units under assessment are
coralline in nature or large chalk beds with
very low silica and other impurities. They are
mostly fresh and devoid of alteration.
Drill hole
information
• A summary of all information material to the
under-standing of the exploration results
including a tabulation of the following
information for all Material drill holes:
• easting and northing of the drill hole collar
• elevation or RL (Reduced Level – elevation
above sea level in metres) of the drill hole
collar
• dip and azimuth of the hole
• down hole length and interception depth
• hole length
• Drill hole locations and descriptors are
included as Appendix 1.
Criteria JORC Code explanation Commentary
• If the exclusion of this information is justified on
the basis that the information is not Material and
this exclusion does not detract from the
understanding of the report, the Competent
Person should clearly explain why this is the
case.
Data
aggregation
methods
• In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (e.g. cutting of high
grades) and cut-off grades are usually Material
and should be stated.
• Where aggregate intercepts incorporate short
lengths of high grade results and longer
lengths of low grade results, the procedure
used for such aggregation should be stated
and some typical examples of such
aggregations should be shown in detail.
• The assumptions used for any reporting of
metal equivalent values should be clearly
stated.
• Assay results from drilling are not discussed
in this announcement.
• No aggregation methods have been used.
• Metal equivalent values have not been used.
Relationship
between
mineralisation
widths and
intercept
lengths
• These relationships are particularly important in
the reporting of Exploration Results.
• If the geometry of the mineralisation with
respect to the drill hole angle is known, its
nature should be reported.
• If it is not known and only the down hole lengths
are reported, there should be a clear statement
to this effect (e.g. ‘down hole length, true width
not known’).
• Drilling results are not discussed in this
announcement.
Diagrams • Appropriate maps and sections (with scales)
and tabulations of intercepts should be included
for any significant discovery being reported.
These should include but not be limited to a plan
view of drill hole collar locations and appropriate
sectional views.
• Drilling results are not discussed in this
announcement. When results are available
and announced maps and cross-sections will
be included to provide context to the
results.
Balanced
Reporting
• Accuracy and quality of surveys used to locate
drill holes (collar and down-hole surveys),
trenches, mine workings and other locations
used in Mineral Resource estimation.
• Where comprehensive reporting of all
Exploration Results is not practicable,
representative reporting of both low and high
grades and/or widths should be practiced to
avoid misleading reporting of Exploration
Results.
• No new information has been withheld.
Other
substantive
exploration
data
• Other exploration data, if meaningful and
material, should be reported including (but not
limited to): geological observations; geophysical
survey results; geochemical survey results; bulk
samples - size and method of treatment;
metallurgical test results; bulk density,
groundwater, geotechnical and rock
characteristics; potential deleterious or
contaminating substances.
• In 2025, Estrella completed a Resistivity/IP
survey, comprised of a single survey line at
the Ira Miri manganese prospect.
• The survey was completed using the IRIS
Syscal Pro multi-electrode imaging system.
The following configuration and acquisition
parameters were applied during the survey:
Instrument: IRIS Syscal Pro (Res-IP
configuration)
Number of electrodes: 48
Array: Dipole-Dipole
Electrode spacing: 5 meters
Total survey line length: Approximately
222.23 meters
Measurement mode used: n76
• Data was acquired successfully using the
Arithmetic Mode, which produced stable and
high-quality data.
Criteria JORC Code explanation Commentary
• Data Processing: All datasets were
processed using the standard IRIS software
workflow followed by inversion and modelling
in Res2DInv, applying noise filtering, error
analysis, and smooth-model inversion to
generate reliable subsurface resistivity and
chargeability sections.
• In 2026, Estrella has completed several
additional ground Resistivity/IP surveys,
utilizing the same equipment and methods
outlined above.
• In 2026 Estrella completed an airborne UAV
(drone) geophysical survey using the
proprietary (Expert Geophysics, patent
pending) Mobile MTd system.
• The MTd survey was conducted using an
airborne electromagnetic system comprising
three orthogonal Induction coils operating
over a frequency 25 Hz to 21,000Hz, with a
digitizing rate of 73,728 Hz. The survey was
supported by a ground base station
consisting of four pairs of electrodes with 50
m electrode spacing, installed along 490
and
2750
orientations to record complementary
electric field data.
• The data from the Mobile MTd survey was
processed initially w