Quarterly Activities and Cashflow Report (March 2014)
Released
Released
Announcement PDF
QUARTERLY ACTIVITIES REPORT
Quarter ending 31 March 2014
ASX RELEASE 30 April 2014
HIGHLIGHTS
Assay results from initial Diamond Drilling Program at Dania identifies near surface
copper oxide to compliment Colupo.
Diamond Drilling at Colupo completed and assay results received.
Secured 100% owned tenement areas adjacent to Project Altair.
Successful Capital Raising of A$1.25M in April 2014.
SPP announced to raise up to A$2M during May 2014.
Quarterly Report - 31 March 2014
Estrella Resources Limited (ASX: ESR) (Estrella or Company) is pleased to provide its Exploration
Activities and Cashflow Reports for the quarter ending 31 March 2014.
1. INTRODUCTION
Estrella’s exploration activity for the Quarter was focussed solely on the Altair Project (Estrella’s flagship
project) with Diamond Drilling programs completed at both the Colupo Prospect and the Dania Prospect.
Estrella’s Board proceeded to consolidate the tenement holding in compliance with the Option
Agreements held with SQM at Project Altair and in addition, the company relinquished all other projects
deterring from the core focus of the Company.
Figure 1: Estrella’s tenement holdings in Chile- Project Altair, Mercurio and Saturno.
2
Quarterly Report - 31 March 2014
Table 1: Mines and project developments nearby to Project Altair (All not owned by Estrella)
Nearby Deposits *
( All not owned by
Ore Reserve
Mineral Resource
Mineralisation
Proximity to
style
Altair
Estrella)
Measured: 26.7Mt @ 1.61%
Michilla
N/A
Indicated: 24.7Mt @ 1.45%
Manto & Breccias
17 km west of
Saturno
Inferred: 15.8Mt @ 1.67%
Proven: 215Mt @ 0.38%
Antucoya
Measured:278 Mt @ 0.34%
Indicated:737 Mt @ 0.30%
Porphyry
Probable: 427Mt @ 0.34%
Surrounded
by
Altair
Inferred:91 Mt @ 0.28%
Proven: 26.3 Mt @ 0.83%,
8.3 Mt @ 0.54%, 2.1Mt @
0.18%
Los Mantos Blancos
Measured:47.8 Mt @ 0.75%, 14.1Mt
@ 0.47%
Indicated: 68.1 Mt @ 0.56%, 10.5 Mt
Probable: 19.7 Mt @ 0.80%,
@ 0.43%, 8.3 Mt @ 0.20%
Rhyolite dome
40 km south of
Altair
16.3 Mt @ 0.33%, 49.6Mt @
0.23%
Inferred: 30.5 Mt @ 0.55%, 5.2Mt @
0.49%
Disclaimer: This table and information contained therein relates to nearby deposits of Project Altair, none of which are owned by Estrella. The
information is obtained from publicly available information. All deposits have been published in compliance with the 2004 JORC Code. Estrella
makes no comparison between its projects and these named deposits other than to demonstrate their locality. There is no guarantee that
Estrella’s projects will realise similar results.
3
Quarterly Report - 31 March 2014
2. THE ALTAIR PROJECT
2.1.
Colupo Prospect Drilling
Prior to the March 2014 Quarter, on 23 December 2013 Estrella announced to the ASX the
commencement of Diamond Drilling at the Colupo Prospect within the Altair Project. A total of four
diamond holes were drilled from December 2013 through to February 2014 to follow up on the successful
intercepts from the RC campaign during September/October 2013.
Diamond holes DHC-01 and DHC-02B compare closely with Estrella’s historical RC drill holes that lie
within the same section line (Figure 2). The observed mineralisation widths are greater in DHC-02 and
DHC-02B and are up to 21 meters in true width and the copper grades are similar, except higher gold
and silver values are present in DHC-02.
DHC-02 was a failed hole as the rig became stuck at 128 metres of drilling down hole due to fractured
ground conditions. The hole was abandoned and DHC02B was drilled 5 metres away to reach the target
depth of 190 metres.
DHC-03 was drilled to the southeast (145o) to test structural continuity in the east and northeast sector
of the currently known extents of mineralisation. DHC-03 demonstrated significant width of
mineralisation and continuity of copper grade, along with significant gold and silver values.
Table 2: Colupo Diamond hole Assay results reported to the ASX on 18 March 2014:
4
Quarterly Report - 31 March 2014
402085E
Figure 2: Drill plan layout for all Estrella’s and SQM’s drill holes at Colupo Prospect. The
yellow section line is shown in profile in Figure 3.
5
Quarterly Report - 31 March 2014
DHC02 & DHC02B
Mineralised zone intercepted in
DHC-02 and DHC-02B
Figure 3: Colupo - Section 402085E displays DHC-02 and DHC-02B drill hole traces (blue)
and mineralised intercepts from historical drill holes. The light grey shells represent breccias
and the light green shells represent the 0.2% Cu cut-off mineralisation shells.
The results from the Colupo Diamond Drilling program confirm:
Structural continuity and true widths up to 21 metres.
Visual confirmation of mineralisation host within matrix of quartz-tourmaline breccia system and
volcanic clasts.
Technical complications due to challenging ground conditions resulted in poor core recovery and
assay results considered not representative of mineralisation intersections for DHC-01.
The known extents of mineralisation at Colupo remain open and will be tested with further with a Rotary
Air Blast (RAB) drilling program scheduled to commence in May 2014. The purpose of the RAB program
is to drill 50-100 shallow holes to 10-15 metres depth stepping out from the current known mineralisation
extents. This will enable sufficient penetration of the shallow caliche cover unit (up to 5 metres thick) to
trace the near-surface extents of the mineralised breccia system. This is a relatively inexpensive way to
identify further mineralisation before commencing a Reverse Circulation (RC) drilling program.
6
Quarterly Report - 31 March 2014
2.2.
Dania Prospect Drilling
On the 20th February 2014 Estrella announced to the ASX that a Diamond Drilling program was
commencing at the Dania Prospect. Estrella drilled two diamond core holes at Dania between February
and March 2014.
The combination of Estrella’s current drilling and historical RC drilling by SQM at the Dania Prospect has
identified near surface oxide copper within several repeated intrusive stocks in a northwest trend over
500 metres in length across a width of 450 metres steeply dipping to beyond 200 metres depth. The
system remains open in all directions except to the east where the contact with the unmineralised
andesite unit has been established at surface and 298.4 metres down hole in DHD-01.
Figure 4: Surface drill plan layout for Dania including SQM’s historical RC collars and
Estrella’s diamond core collars. The green polygons indicate the known mineralisation
trends.
7
Quarterly Report - 31 March 2014
The assay results for DHD-01 and DHD-02 are presented in Table 3 and Table 4. Both drill holes had long
mineralisation intercepts grading 0.2% to 0.4% Cu. Geological observations of the drill core confirm
mineralisation is due to:
i.
ii.
Multiple porphyritic stock emplacement along the Buey Muerto Fault zone (BMZ);
Oxidation, leaching, and secondary enrichment of copper.
The upper mineralised intercepts in holes DHD-01 and DHD-02 (Figure 5 and Figure 6) are likely to link,
however the lower intercept in DHD-01 was not intercepted by DHD-02. The northerly extent of the
lower mineralised intercept in DHD-01 remains open as DHD-02 did not intercept the Jurassic aged
andesite unit to the east.
Table 3: Significant Assay Results from diamond core hole DHD-02
Hole ID
Coordinates (PSAD56)
East
North
RL
EOH
Dip
Azimuth
1580
289
-65
80
including
From
To
Interval
Copper
(m)
(m)
(m)
%Cu
10
36
70
65
60
29
0.3
0.4
87
89
2
0.4
97
99
2
0.1
118
122
4
0.2
127
130
3
0.2
177
178
1
0.7
211
212
1
0.1
Diamond core
DHD-02
402600
7508430
Table 4: Significant Assay Results from diamond core hole DHD-01
Hole_ID
DHD01
Coordinates (PSAD56)
East
North
402692
7508346
RL
EOH
Dip
Azimuth
1580
316.2
-75
From
To
Interval
Copper
(m)
(m)
(m)
%Cu
Comments
55
2
298
271
0.14
excludes 27.5 metres of dyke
including
2
56
54
0.3
CuOx from 2 m below surface
including
10
27
17
0.4
72
75
4
0.2
118
122
4
0.1
161
171
10
0.13
180
183
4
0.13
192
194
3
0.2
200
212
13
0.2
Unmineralised dyke
220
233
14
0.2
Unmineralised dyke
256
271
16
0.3
274
298
25
0.14
exit rhyolite at 299 m into
eastern andesitic contact
8
Quarterly Report - 31 March 2014
Figure 5: Dania cross-section 7,508,075N for DHD-02 intersects a mineralised intrusive
stock near-surface. CuOx mineralisation was intersected for 60 metres at 0.3% (yellow
zone) including 29 metres at 0.4% (red zone).
Figure 6: Dania cross section 7,508,000N for DHD-01, shows two mineralised porphyritic
stocks intruded along faults of the BMZ. The western stock likely links to the stock
intersected by DHD-02. Each stock has the potential for higher grade hypogene zones at
depth, also there is potential for mineralised repetitions to the west.
9
Quarterly Report - 31 March 2014
2.3.
Antucoya West Prospect
Estrella’s exploration team has been mapping the surface geology at the Antucoya West prospect during
the March 2014 Quarter. The focus of the mapping has been the surface area across the dipole anomaly
in the Vector Induced Polarisation (VIP) image (see Figure 7) and the eastern border next to the
Antucoya project (owned by Antofagasta Minerals PLC).
Figure 7: Vector IP surface results for Antucoya West. The blue circle indicates the dipole
area of interest.
Estrella’s exploration mapping at Antucoya West has identified numerous outcrops with clear copper
oxide mineralisation, sericitic and silicic alteration, hydrothermal breccias and ‘crackle’ zones, which are
all encouraging signs of porphyry style mineralisation beneath.
Estrella is currently planning its maiden exploration drilling program at Antucoya West, which is to
commence in May 2014.
10
Quarterly Report - 31 March 2014
2. TENEMENT HOLDINGS
Pursuant to ASX Listing Rule 5.3.3, the Company provides the following information:
2.1
The Altair Project-100% ESR Owned- subject to Option Agreements with SQM
(providing SQM with either a 49% clawback right or royalty payments per discovery)
Estrella announced to the ASX on the 25th March 2014, the consolidation of the tenements within Project
Altair on the as part of Estrella’s strategy to focus and prioritise exploration and development on the
most prospective and advanced areas within the Altair Project and in compliance with the Option
Agreements held with SQM, Estrella relinquished certain parts of Project Altair back to SQM.
The Altair Project located in Region II of northern Chile, 90 km north northeast of Antofagasta now
covers an area of 1,232.33 km2 (inclusive of both “Mercurio and Saturno” Prospects a total of 108 km2 of
100% Estrella owned tenement) at the end of the March 2014 Quarter.
2.2
Mercurio Prospect (100% ESR Owned)
Estrella announced to the ASX on the 25th March 2014 that it has become the prime applicant for an
additional 74.17 km2 (7,417 hectares) situated immediately to the north of the Colupo Prospect. This
additional tenement titled “Mercurio” is of strategic benefit to Estrella given its location in proximity to
the Colupo Prospect coupled with recent announcements regarding the prospectivity and mineralisation
trends observed at the Colupo Prospect. (See Figure 1)
2.3
Estrella’s Tenement holdings in Chile
Description
Tenement Size
(hectares)
Option Agreements held with SQM
Tenement Size
(km2)
109,890
1,098.90
2,476
24.76
Option Agreement One
Option Agreement Two (Ivannia and Dania)
100% Owned by Estrella Resources Limited
Mercurio (100% owned by Estrella)
Saturno (100% owned by Estrella)
Total tenement holdings in Chile
2.4
7,417
74.17
3,450
34.5
123,233
1,232.33
Other Projects- All now relinquished
The Venus Project, Jupiter Project, Luna/Inca Project
There was no exploration activity on the Venus, Jupiter or Luna/Inca projects during the quarter.
As announced to the ASX on the 25th March 2014 the each of Venus, Jupiter and Luna/Inca Projects have
been relinquished from Estrella’s portfolio of tenements in Chile. The Company is committed to focus
solely on the Altair Project and these areas were not considered prospective enough to deter focus away
from the Company’s core priorities. There were nil costs incurred by the Company in respect of the
relinquished tenements.
11
Quarterly Report - 31 March 2014
3. CORPORATE
3.1
Board Succession Planning
During the March 2014 quarter, Mr Robert Thomson was appointed to the Board as an independent nonexecutive director. Mr Thomson is a Sydney based mining engineer with extensive onsite mining
experience as well as significant corporate and board experience.
Subsequent to the March 2014 Quarter the Board continued its succession planning program with Mr
Simon Kidston announcing his resignation as a Director in order to pursue other business interests. Mr
Kidston was instrumental in the establishment of Estrella and worked tirelessly since inception to position
the Company where it is today. The Company’s Chairman, Mr Gavin Solomon has also announced his
intention to stand down as a Director from 30 June 2014 to pursue other business interests. Gavin has
also worked tirelessly for the betterment of the Company and was instrumental in delivering the option
agreements for Project Altair with SQM. The Board is now in the process of identifying a successor as
Chairman of the Company.
3.2
Half Year Review
On 12 March 2014 the Company released its statutory accounts for the 6 month period to 31 December
2013. This was the second Half Year Review completed by the Company since its listing on the ASX in
May 2012.
3.3
Capital Raising
Subsequent to the end of the March 2014 Quarter, Estrella undertook its second capital raising since
listing on the ASX. The capital raising consists of a placement to new and existing institutional and
sophisticated investors to raise a total of A$1.25M at A$0.11 per share through the issue of 11,132,271
new ordinary shares in the Company together with the announcement of a Share Purchase Plan to raise
up to a maximum of A$2,000,000 during May 2014.
4. FINANCIAL POSITION
The Company had A$1.061 million in cash at 31 March 2014.
12
Quarterly Report - 31 March 2014
Disclaimer: References are made in this quarterly report to historical drilling results by SQM and to
drilling results from Estrella’s own drilling, all of which have previously been released to the ASX. The
Company is not aware of any new information or data that materially affects either of the drilling results
from SQM or Estrella.
Competent Person’s Statement:
Exploration information in this announcement is based upon and fairly represents, information,
supporting documentation and work undertaken by Dr. Jason Berton, the Managing Director and a fulltime employee of Estrella Resources Limited whom is a Member of the Australasian Institute of
Metallurgy and Mining (AusIMM). Dr Berton has sufficient experience that is relevant to the style of
mineralisation and type of deposit under consideration and to the activity which he is undertaking to
qualify as a ‘Competent Person’ as defined in the 2012 Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code). Dr Berton consents to the
inclusion in this presentation of the statements based on his information and context in which they
appear.
About Estrella Resources
Directors and Management
Estrella Resources Limited is an ASX listed, Chilean
focused copper-gold exploration company. Estrella
has a number of exploration projects in Chile. With
a highly experienced board, a strong operational
and management team and a sole focus on Chilean
copper and gold projects, the Company is well
positioned to develop its projects and add value for
shareholders.
Non-Executive Chairman:
-Gavin Solomon
Managing Director
-Dr. Jason Berton
Non-Executive Directors:
-Julian Bavin
-Robert Thomson
ESTRELLA RESOURCES LIMITED
ACN 151 155 207
ASX CODE: ESR
ORDINARY FULLY PAID SHARES:
107,733,271
UNLISTED OPTIONS:
12,380,000
Company Secretary
-Justin Clyne
13
APPENDIX 5B
Mining exploration entity quarterly report
Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 1/05/2013
Name of entity
Estrella Resources Limited
Quarter Ended (''Current Quarter'')
ABN
39 151 155 207
31 March 2014
Consolidated statement of cash flows
Current
Year to date
quarter
$A’000
(12 months)
$A’000
-
-
(618)
(1,480)
(b) development
-
-
(c) production
-
-
(259)
(841)
Cash flows related to operating activities
1.1
Receipts from product sales and related debtors
1.2
Payments for
(a) exploration and evaluation
(d) administration
1.3
Dividends received
-
-
1.4
Interest and other items of a similar nature received
9
39
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Other (provide details if material)
-
-
(868)
(2,282)
-
-
(b) equity investments
-
-
(c) other fixed assets
-
-
(a) prospects
-
-
(b) equity investments
-
-
(c) other fixed assets
-
-
Net operating cash flows
Cash flows related to investing activities
(a) prospects
1.8 Payment for purchases of:
1.9
Proceeds from sale of:
1.10
Loans to other entities
-
-
1.11
Loans repaid by other entities
-
-
1.12
Other- Project Option Fees
-
-
Net investing cash flows
-
-
(868)
(2,282)
1.13
Total operating and investing cash flows (carried forward)
ESTRELLA RESOURCES LIMITED- APPENDIX 5B 31 MARCH 2014
Page 14 of 18
1.13
Total operating and investing cash flows (brought forward)
(868)
(2,282)
Cash flows related to financing activities
1.14
Proceeds from issues of shares, options, etc.
-
950
1.15
Proceeds from sale of forfeited shares
-
-
1.16
Proceeds from borrowings
-
-
1.17
Repayment of borrowings
-
-
1.18
Dividends paid
-
-
1.19
Other – Capital raising costs
-
(81)
Net financing cash flows
-
869
Net increase (decrease) in cash held
(868)
(1413)
1.20
Cash at beginning of quarter/year to date
1,966
2,487
1.21
Exchange rate adjustments to item 1.2
(37)
(13)
1.22
Cash at end of quarter
1,061
1,061
Payments to directors of the entity and associates of the directors
Payments to related entities of the entity and associates of the related entities
Current quarter $A'000
1.23
Aggregate amount of payments to the parties included in item 1.2
122
1.24
Aggregate amount of loans to the parties included in item 1.10
-
1.25
Explanation necessary for an understanding of the transactions
Directors including Managing Directors fees/salary for the quarter: $122.441
Non-cash financing and investing activities
2.1
Details of financing and investing transactions which have had a material effect on consolidated
assets and liabilities but did not involve cash flows
Nil
2.2
Details of outlays made by other entities to establish or increase their share in projects in which
the reporting entity has an interest
Nil
Financing facilities available
Add notes as necessary for an understanding of the position
Amount
Available
$A,000
Amount
used
$A,000
3.1
Loan facilities
-
-
3.2
Credit standby arrangements
-
-
ESTRELLA RESOURCES LIMITED- APPENDIX 5B 31 MARCH 2014
Page 15 of 18
Estimated cash outflows for next quarter
$A’000
4.1
Exploration and evaluation
450
4.2
Development
-
4.3
Production
-
4.4
Administration
250
Total
700
Reconciliation of cash
Reconciliation of cash at the end of the quarter (as shown in the consolidated statement of
cash flows) to the related items in the accounts is as follows.
Current
quarter
$A’000
Previous
quarter
$A’000
5.1
Cash on hand and at bank
218
753
5.2
Deposits at call
843
1,213
5.3
Commercial Bills
5.4
Other: Term Deposit
-
Total: cash at end of quarter (item 1.22)
1,061
1,966
Interest
at beginning
of quarter
Interest
at end of
quarter
100%
0%
100%
0%
100%
0%
0%
100%
Changes in interests in mining tenements
Tenement
reference
6.1
Interests in mining tenements relinquished,
reduced or lapsed
Luna/Inca
Venus
Jupiter
6.2
Interests in mining tenements acquired or
increased
ESTRELLA RESOURCES LIMITED- APPENDIX 5B 31 MARCH 2014
Mercurio
Nature of
interest
The
tenement
was
relinquished
The
tenement
was
relinquished
The
tenement
was
relinquished
Primary
Applicant
Page 16 of 18
Issued and quoted securities at end of current quarter
Description includes rate of interest and any redemption or conversion rights together with prices and dates.
7.1
Preference +securities(description)
7.2
Changes during quarter
Total
Number
Number
quoted
96,601,000
60,662,500
Issue price
per security
(see note 3)
Amount paid
up per
security
(see note 3)
Exercise
price
Expiry date
(a) Increases through issues
7.3
(b) Decreases through returns of capital,
buy-backs, redemptions
+Ordinary securities
7.4
Changes during quarter
(a) Increases through issues
7.5
7.6
(b) Decreases through returns of capital,
buy-backs
Convertible
debt
securities
(description)
Changes during quarter
(a) Increases through issues
(b)
Decreases
through
matured, converted
7.7
7.8
securities
Options
Unlisted
3,600,000
-
25 cents
12-Sep-14
Unlisted
1,000,000
-
25 cents
25-Oct-14
Unlisted
505,000
-
20 cents
19-Dec-16
Unlisted
600,000
-
20 cents
25-Oct-16
Unlisted
1,500,000
-
20 cents
9-May-17
Unlisted
475,000
-
20 cents
3-Oct-18
Unlisted
450,000
-
35 cents
18-Apr-16
Unlisted
3,000,000
-
35 cents
21-Nov-18
Unlisted
500,000
-
35 cents
18-Dec-16
Unlisted
750,000
-
35 cents
7-Mar-17
Issued during quarter
500,000
-
35 cents
18-Dec-16
750,000
-
35 cents
7-Mar-17
7.9
Exercised during quarter
7.10
Expired during quarter
7.11
Debentures (totals only)
7.12
Unsecured notes (totals only)
ESTRELLA RESOURCES LIMITED- APPENDIX 5B 31 MARCH 2014
Page 17 of 18
Compliance statement
1. This statement has been prepared under accounting policies which comply with accounting
standards as defined in the Corporations Act or other standards acceptable to ASX (see note
5).
2. This statement does give a true and fair view of the matters disclosed.
Sign here:
Print name:
Date: 30 April 2014
Justin Clyne - Company Secretary
Notes:
1. The quarterly report provides a basis for informing the market how the entity’s activities have
been financed for the past quarter and the effect on its cash position. An entity wanting to
disclose additional information is encouraged to do so, in a note or notes attached to this
report.
2. The “Nature of interest” (items 6.1 and 6.2) includes options in respect of interests in mining
tenements and petroleum tenements acquired, exercised or lapsed during the reporting
period. If the entity is involved in a joint venture agreement and there are conditions
precedent which will change its percentage interest in a mining tenement or petroleum
tenement, it should disclose the change of percentage interest and conditions precedent in
the list required for items 6.1 and 6.2.
3. Issued and quoted securities The issue price and amount paid up is not required in items
7.1 and 7.3 for fully paid securities.
4. The definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral
Resources and AASB 107: Statement of Cash Flows apply to this report.
5. Accounting Standards ASX will accept, for example, the use of International Financial
Reporting Standards for foreign entities. If the standards used do not address a topic, the
Australian standard on that topic (if any) must be complied with.
ESTRELLA RESOURCES LIMITED- APPENDIX 5B 31 MARCH 2014
Page 18 of 18