Quarterly Activities Report and 5B
Released
Released
Announcement PDF
QUARTERLY ACTIVITIES REPORT
Quarter ending 31 March 2015
ASX RELEASE 24 April 2015
HIGHLIGHTS
Strategic review of project areas and prioritisation of targets underway.
Estrella in discussions with several key parties for potential investment into Antucoya
West Project.
Tenement option fees paid up during the Quarter.
$700,000 capital raising underway; placement for $125,000 completed, rights issue
to raise approximately $576,000 underway.
Quarterly Activities Report – 31 March 2015
Estrella Resources Limited (ASX: ESR) (Estrella or Company) is pleased to provide its Exploration
Activities and Cashflow Report for the quarter ending 31 March 2015.
1. INTRODUCTION
Estrella’s exploration activity for the Quarter was focussed on consolidating the most prospective
exploration ground and promoting the projects to third party investors (see Figure 1 and Figure 2)
Figure 1: Estrella’s Altair Project is ideally located close to ports, power, major mining infrastructure
and mining projects in Region II northern Chile (Map Datum WGS84).
2
Quarterly Activities Report – 31 March 2015
Figure 2: Estrella’s tenement holdings in Chile- Antucoya West, Colupo, Dania and Ivannia projects
(Altair project) (Map Datum WGS84).
3
Quarterly Activities Report – 31 March 2015
Table 1: Mines and project developments nearby to Project Altair (None owned by Estrella)
Nearby Deposits *
Ore Reserve
( All not owned by
Mineral Resource
Mineralisation
Proximity to
style
Altair
Estrella)
Measured: 26.7Mt @ 1.61%
Michilla
N/A
Indicated: 24.7Mt @ 1.45%
Manto & Breccias
17 km west of
Saturno
Inferred: 15.8Mt @ 1.67%
Proven: 215Mt @ 0.38%
Antucoya
Measured:278 Mt @ 0.34%
Indicated:737 Mt @ 0.30%
Surrounded
Porphyry
Probable: 427Mt @ 0.34%
8.3 Mt @ 0.54%, 2.1Mt @
0.18%
Mantos Blancos
borders
West
Measured:47.8 Mt @ 0.75%, 14.1Mt
@ 0.47%
Indicated: 68.1 Mt @ 0.56%, 10.5 Mt
Probable: 19.7 Mt @ 0.80%,
Antucoya
Project
Inferred:91 Mt @ 0.28%
Proven: 26.3 Mt @ 0.83%,
Altair;
by
@ 0.43%, 8.3 Mt @ 0.20%
Rhyolite dome
40 km south of
Altair
16.3 Mt @ 0.33%, 49.6Mt @
0.23%
Inferred: 30.5 Mt @ 0.55%, 5.2Mt @
0.49%
Disclaimer: This table and information contained therein relates to nearby deposits of Project Altair, none of which are owned by Estrella. The
information is obtained from publicly available information. All deposits have been published in compliance with the 2004 JORC Code. Estrella
makes no comparison between its projects and these named deposits other than to demonstrate their locality. There is no guarantee that
Estrella’s projects will realise similar results.
4
Quarterly Activities Report – 31 March 2015
2. THE ALTAIR PROJECT
2.1.
Antucoya West
Estrella's Antucoya West Project is now subject to a legally binding Option Agreement contract that
removed the 49% clawback condition that was part of the Altair Project Option Agreement (see ASX
Announcement 14 October 2014). Upon signing the new Antucoya West Option Agreement, Estrella
has extracted 5,270 ha from the existing Altair Option Agreement area. The new Antucoya West Option
Agreement is for 4 years and ensures Estrella the metallic rights to 100% of all discoveries within the
Antucoya West Project. Estrella considers this a significant advancement in the ‘commerciality’ of the
Antucoya West Project as it increases the range of investment opportunities for any potential Third Party
investors. Since signing the Option Agreement Estrella has entered into Confidentiality Agreements with
three interested parties and discussions are on-going with two other parties.
The Estrella’s exploration has been focussed on the Buey Muerto Fault Zone (BMZ) as it hosts the
Antucoya porphyry mine development (owned by Antofagasta Minerals PLC) and the Antucoya West,
Ivannia, Dania, Colupo and Colupo Norte prospects.
2.2.
Colupo and Colupo Norte
Colupo is 20 km north of Antucoya West (see Figure 3).
Estrella announced an Exploration Target for Colupo of 4.5 to 6.0 million tonnes with a grade range of
0.7 to 1.0% copper (see ASX release 26 November 2014).
The Exploration Target is based upon 19 drill holes from drilling campaigns by Estrella and SQM. Estrella
drilled two campaigns at Colupo in the last 12 months, consisting of RC and Diamond core drilling. The
best results are summarised below (refer ASX announcements of 11 November and 3 December 2013):
20m @ 2.4% Cu from 12 m (hole RCC04) including;
o 6m @ 6.6% Cu, 0.5 g/t Au & 27.1 g/t Ag
16m @ 1.5% Cu from 131m (hole RCC04) including;
o 6m @ 1.6% Cu, 0.2 g/t Au & 7.5 g/t Ag
o 6m @ 2.2%Cu, 0.2 g/t Au & 11.8 g/t Ag
20m @0.9% Cu from 144m (hole RCC02) including;
o 3m @ 3.4% Cu
8 m @ 1.1% Cu from 126 m (hole RCC06) including:
o 3 m @ 2.5% Cu, 0.15 g/t Au & 20.3 g/t Ag
6 m @ 0.8% Cu from 102m (hole RCC06) including:
o 3 m @ 1.2% Cu
5 m @ 0.7% Cu from 55m (hole RCC07)
All previously reported drilling results from Estrella’s RC campaign are shown in Table 2 and results from
the diamond drilling campaign in Table 3.
5
Quarterly Activities Report – 31 March 2015
Figure 3: Colupo drill plan layout for all historical Estrella’s and SQM’s drill holes. The red arrows
indicate the mineralisation trends and the yellow ellipses highlight the areas drilled in the shallow RC
program (Map Datum PSAD56 Zn19).
6
Quarterly Activities Report – 31 March 2015
Table 2: Colupo, summary of the assay results from holes RCC01 to RCC09 set out below (using a cutoff of 0.3% copper) as previously announced to the ASX on 11 November and 3 December 2013.
Hole_ID
RCC01
Coordinates (PSAD56)
East
North
402081
7514511
RL
EOH
Dip
Azimuth
1910
210
-60
180
Incl
Incl
RCC02
402089
7514579
1910
200
-70
180
RCC03
402096
7514638
1910
200
-60
130
RCC04
402033
7514550
1910
230
-60
180
Incl
Incl
Incl
Incl
Incl
RCC05
402008
7514595
1910
250
-60
180
RCC06
402067
7514616
1910
200
-60
146
Incl
Incl
RCC07
402140
7514653
1910
199
-60
130
RCC09
402050
7514600
1910
257
-60
180
From
(m)
10
12
34
43
47
53
7
118
144
150
41
52
87
12
23
56
102
115
116
131
131
141
91
197
102
104
125
127
50
194
83
101
184
195
To
(m)
16
15
37
56
51
55
10
122
158
153
44
54
94
31
26
62
108
122
119
147
137
147
96
199
108
107
133
130
55
196
89
103
186
199
Interval
(m)
6
3
3
13
4
2
3
4
20
3
3
2
7
20
6
6
6
7
3
16
6
6
5
2
6
3
8
3
5
2
6
2
2
5
Copper
%Cu
0.7
1.1
0.5
0.4
0.6
0.5
0.5
0.4
0.9
3.4
0.3
0.5
1
2.4
6.6
0.4
0.4
0.5
0.7
1.5
1.6
2.2
0.3
0.4
0.8
1.2
1.1
2.5
0.7
0.3
0.4
0.5
0.3
0.5
Gold
g/t Au
Silver
g/t Ag
0.5
27.1
0.2
0.2
7.5
11.8
0.15
20.3
0.2
7
Quarterly Activities Report – 31 March 2015
Table 3: Colupo diamond hole Assay results reported to the ASX on 18 March 2014.
Colupo Norte
Estrella reported (see ASX Announcement 28 August 2014) high grade copper intercepts from its shallow
RC drill hole program at Colupo Norte.
Two mineralised tourmaline breccias intersected near surface; and
125 m strike length identified and remains open along strike and depth.
Shallow RC drilling program intercepts at Colupo Norte include:
o
o
4 m @ 1.1% Cu from 1m (RCCN-02), including;
1m at 2.6% Cu from 3m; and
2 m @ 1.1% Cu from 8m (RCCN-02), including;
1m at 1.5% Cu from 9m.
8
Quarterly Activities Report – 31 March 2015
Table 4: Colupo Norte assay summary using 0.2% Cu cut-off. Note, all mineralisation is host within
Tourmaline Breccias.
Hole ID
Easting
Northing
RL
EOH
Azimuth
Dip
RCCN-01
400,988 7,517,317
2075
24
230
-70
RCCN-02
400,981 7,517,410
2075
26
230
-70
incl
RCCN-03
400,983 7,517,383
2075
20
230
incl
-70
From
(m)
2
9
1
3
8
9
1
To
(m)
8
10
5
4
10
10
4
Interval
Cu%
6
1
4
1
2
1
3
0.4
0.4
1.1
2.6
1.1
1.5
0.4
(Coordinates in PSAD56, zone19s)
Estrella is greatly encouraged by the results from the shallow RC drill holes because holes RCCN-01, 02
and 03 each intersected two mineralised tourmaline breccias (where previously only one was thought to
occur) along a 125 metre strike length. The system remains open along strike and at depth.
2.3.
Dania Prospect
No exploration activity was undertaken at Dania during the March 2015 Quarter.
Estrella is currently assessing the next steps to advance exploration activities at Dania.
2.4.
Ivannia Prospect
No exploration activity was undertaken at Ivannia during the March 2015 Quarter.
9
Quarterly Activities Report – 31 March 2015
3. TENEMENT HOLDINGS
Pursuant to ASX Listing Rule 5.3.3, the Company provides the following information:
3.1
Estrella’s Tenement holdings in Chile
Tenement Size
(hectares)
Option Agreements held with SQM
Tenement Size
(km2)
Option Agreement One
1,700
17.00
Option Agreement Two (Ivannia and Dania)
2,476
24.76
Option Agreement Three (Antucoya West)
5,270
52.70
Description
100% Owned by Estrella Resources Limited
Mercurio (100% owned by Estrella)
2,700
27.00
Saturno (100% owned by Estrella)
3,450
34.5
Total tenement holdings in Chile
15,596
155.96
4. CORPORATE
4.1
March 2015 Capital Raising
On 31 March 2015 the Company announced a $700,000 capital raising, comprising a placement (which
was completed that day) to raise $125,000 and a non-renounceable, 3:5 rights issue at a price of $0.007
(0.7 cents) per share to raise approximately $576,000. The Prosepctus for the offer will be released
shortly.
4.2
Board Changes
On 31 March 2015 Mr Rob Thomson resigned as a non-executive Director (and Chairman) of Estrella and
Mr Guy Robertson was appointed as a non-Executive Director. The Board thanks Mr Thomson for his
contribution and welcomes Mr Robertson.
5. FINANCIAL POSITION
The Company’s Appendix 5B Cashflow Report is attached.
Disclaimer: References are made in this quarterly report to historical drilling results by SQM and to
drilling results from Estrella’s own drilling, all of which have previously been released to the ASX. The
Company is not aware of any new information or data that materially affects either of the drilling results
from SQM or Estrella.
Competent Person’s Statement:
Exploration information in this announcement is based upon and fairly represents, information,
supporting documentation and work undertaken by Dr. Jason Berton, the Managing Director and a full-
10
Quarterly Activities Report – 31 March 2015
time employee of Estrella Resources Limited whom is a Member of the Australasian Institute of
Metallurgy and Mining (AusIMM). Dr Berton has sufficient experience that is relevant to the style of
mineralisation and type of deposit under consideration and to the activity which he is undertaking to
qualify as a ‘Competent Person’ as defined in the 2012 Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code). Dr Berton consents to the
inclusion in this presentation of the statements based on his information and context in which they
appear.
About Estrella Resources
Directors and Management
Estrella Resources Limited is an ASX listed, Chilean focused
copper-gold exploration company. Estrella has a number of
exploration projects in Chile. With a highly experienced board, a
strong operational and management team and a sole focus on
Chilean copper and gold projects, the Company is well positioned
to develop its projects and add value for shareholders.
Managing Director:
-Dr Jason Berton
Independent Non-Executive
Director:
-Julian Bavin
Non Executive Director
-Guy Robertson
Company Secretary
-Heath Roberts
ESTRELLA RESOURCES LIMITED
ACN 151 155 207
ASX CODE: ESR
ORDINARY FULLY PAID SHARES:
137,291,527
UNLISTED OPTIONS:
17,151,427
SHARE RIGHTS:
1,866,667 (maximum number that may
convert to fully paid ordinary shares on
1 July 2015)
11
APPENDIX 5B
Mining exploration entity quarterly report
Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10,
01/05/2013
Name of entity
Estrella Resources Limited
Quarter Ended (''Current Quarter'')
ABN
39 151 155 207
31 March 2015
Consolidated statement of cash flows
Current
Year to date
quarter
$A’000
(12 months)
$A’000
Cash flows related to operating activities
1.1
Receipts from product sales and related debtors
1.2
Payments for
-
-
(47)
(394)
(b) development
-
-
(c) production
-
-
(191)
(784)
(a) exploration and evaluation
(d) administration
1.3
Dividends received
-
-
1.4
Interest and other items of a similar nature received
-
-
1.5
Interest and other costs of finance paid
1
6
1.6
Income taxes paid
-
-
1.7
Other (provide details if material)
-
-
(237)
(1,172)
-
-
(b) equity investments
-
-
(c) other fixed assets
-
-
(a) prospects
-
-
(b) equity investments
-
-
(c) other fixed assets
-
-
Net operating cash flows
Cash flows related to investing activities
(a) prospects
1.8 Payment for purchases of:
1.9
Proceeds from sale of:
1.1
Loans to other entities
-
-
1.11
Loans repaid by other entities
-
-
1.12
Other- Project Option Fees
-
-
Net investing cash flows
-
-
(237)
(1,172)
1.15
Total operating and investing cash flows (carried forward)
ESTRELLA RESOURCES LIMITED- APPENDIX 5B 31 March 2015
Page 12 of 16
Cash flows related to financing activities
1.16
Proceeds from issues of shares, options, etc.
140
329
1.17
Proceeds from sale of forfeited shares
-
-
1.18
Proceeds from borrowings
-
-
1.19
Repayment of borrowings
-
-
1.20
Dividends paid
-
-
1.21
Other – Capital raising costs
-
(9)
Net financing cash flows
140
320
Net increase (decrease) in cash held
(97)
(852)
1.22
Cash at beginning of quarter/year to date
342
1,128
1.23
Exchange rate adjustments to item 1.2
2
(29)
1.24
Cash at end of quarter
247
247
Payments to directors of the entity and associates of the directors
Payments to related entities of the entity and associates of the related entities
Current quarter $A'000
1.25
Aggregate amount of payments to the parties included in item 1.2
101
1.26
Aggregate amount of loans to the parties included in item 1.10
-
1.27
Explanation necessary for an understanding of the transactions
Directors including Managing Directors fees/salary for the period: $100,967
Non-cash financing and investing activities
2.1
Details of financing and investing transactions which have had a material effect on consolidated
assets and liabilities but did not involve cash flows
Nil
2.2
Details of outlays made by other entities to establish or increase their share in projects in which
the reporting entity has an interest
Nil
Financing facilities available
Add notes as necessary for an understanding of the position.
Amount
Available
$A,000
Amount
used
$A,000
3.1
Loan facilities
-
-
3.2
Credit standby arrangements
-
-
ESTRELLA RESOURCES LIMITED- APPENDIX 5B 31 March 2015
Page 13 of 16
Estimated cash outflows for next quarter
$A’000
4.1
Exploration and evaluation
250
4.2
Development
-
4.3
Production
-
4.4
Administration
100
Total
350
Reconciliation of cash
Reconciliation of cash at the end of the quarter (as shown in the consolidated statement of
cash flows) to the related items in the accounts is as follows.
Current
quarter
$A’000
Previous
quarter
$A’000
5.1
Cash on hand and at bank
148
89
5.2
Deposits at call
99
254
5.3
Commercial Bills
5.4
Other: Term Deposit
-
Total: cash at end of quarter (item 1.22)
247
343
Interest
at beginning
of quarter
Interest
at end of
quarter
Changes in interests in mining tenements
Tenement
reference
6.1
Interests in mining tenements relinquished,
reduced or lapsed
6.2
Interests in mining tenements acquired or
increased
ESTRELLA RESOURCES LIMITED- APPENDIX 5B 31 March 2015
Nature of
interest
Refer
Activities
Report
Nil
Page 14 of 16
Issued and quoted securities at end of current quarter
Description includes rate of interest and any redemption or conversion rights together with prices and dates.
7.1
Preference +securities(description)
7.2
Changes during quarter
Total Number
Number
quoted
137,291,527
137,291,527
5,305,658
5,305,658
17,900,000
17,900,000
Issue price
per security
(see note 3)
Amount paid
up per
security
(see note 3)
(a) Increases through issues
7.3
(b) Decreases through returns of capital,
buy-backs, redemptions
+Ordinary securities
Changes during quarter
7.4
(a) Increases through issues
7.5
7.6
n/a –
tenent
acqn
$0.007
n/a
Fully paid
(b) Decreases through returns of capital,
buy-backs
Convertible
debt
securities
(description)
Changes during quarter
(a) Increases through issues
(b)
Decreases
through
matured, converted
7.7
securities
Exercise
price
Expiry date
-
20 cents
19-Dec-16
600,000
-
20 cents
25-Oct-16
1,500,000
-
20 cents
9-May-17
Unlisted
475,000
-
20 cents
3-Oct-18
Unlisted
450,000
-
35 cents
18-Apr-16
Unlisted
3,000,000
-
35 cents
21-Nov-18
Unlisted
500,000
-
35 cents
18-Dec-16
Unlisted
750,000
-
35 cents
7-Mar-17
Unlisted
5,500,000
-
10 cents
13-Nov-19
Unlisted
3,871,427
-
5 cents
31-Dec-15
Options
Unlisted
505,000
Unlisted
Unlisted
7.8
Issued during quarter
7.9
Exercised during quarter
7.1
Expired during quarter
7.11
Debentures (totals only)
7.12
Performance Rights (totals only)
7.13
Unsecured notes (totals only)
ESTRELLA RESOURCES LIMITED- APPENDIX 5B 31 March 2015
1,866,667
n/a
Page 15 of 16
Compliance statement
1. This statement has been prepared under accounting policies which comply with accounting
standards as defined in the Corporations Act or other standards acceptable to ASX (see note
5).
2. This statement does give a true and fair view of the matters disclosed.
Sign here:
Print name:
Date: 24 April 2015
Heath Roberts - Company Secretary
Notes:
1. The quarterly report provides a basis for informing the market how the entity’s activities have
been financed for the past quarter and the effect on its cash position. An entity wanting to
disclose additional information is encouraged to do so, in a note or notes attached to this
report.
2. The “Nature of interest” (items 6.1 and 6.2) includes options in respect of interests in mining
tenements and petroleum tenements acquired, exercised or lapsed during the reporting
period. If the entity is involved in a joint venture agreement and there are conditions
precedent which will change its percentage interest in a mining tenement or petroleum
tenement, it should disclose the change of percentage interest and conditions precedent in
the list required for items 6.1 and 6.2.
3. Issued and quoted securities The issue price and amount paid up is not required in items
7.1 and 7.3 for fully paid securities.
4. The definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral
Resources and AASB 107: Statement of Cash Flows apply to this report.
5. Accounting Standards ASX will accept, for example, the use of International Financial
Reporting Standards for foreign entities. If the standards used do not address a topic, the
Australian standard on that topic (if any) must be complied with.
ESTRELLA RESOURCES LIMITED- APPENDIX 5B 31 March 2015
Page 16 of 16
Share your feedback