QUARTERLY ACTIVITIES REPORT
Quarter ending 31 March 2026
HIGHLIGHTS
• Estrella commences Timor-Leste’s first ever hard rock
minerals extraction under its modern Mining Code
• Excavation work underway using majority local contractors
with zero LTIs and strong community support
• Approval received for 30,000-tonne manganese market
sample extraction, with material to be exported to potential
offtake partners
• Estrella is reviewing logistics and preparing the Ira Miri port
stockpile in readiness of sale and export
• Further compelling highly chargeable IP anomaly targets
remain underexplored beneath existing pit
• Estrella to progress Category A Mining Licence which will
enable full-scale development at Ira Miri
• Assays received from maiden Werumata limestone drilling
campaign comprising 33 RC drill holes (for 2,804m) and 9
diamond holes (for 913.10m)
• Baucau Limestone intersections up to 87m*, averaging 30m,
and Batu Putih Chalk intersections up to 59m*, also averaging
30m.
o *The stated intersections are down-hole lengths but
likely to be very close to true thickness
• Baucau Limestone average grade 83% CaCO3) and Batu Putih
Chalk average grade 77.5% CaCO3)
• Results strongly position the Company towards its target of a
JORC compliant Inferred Mineral Resource Estimate (MRE) of
500M
• Bulk density determinations are currently underway with
results to support the delivery of the MRE
• Company in strong financial position following underwriting
of listed option agreements, which provide capital to rapidly
progress manganese and limestone projects
Estrella Resources Limited (ASX: ESR) (Estrella or the Company) is
pleased to provide its quarterly activities report for the period ending 31
March 2026.
During the period, the company made significant progress in its
transition from explorer to producer following its development activities
at the Ira Miri manganese pit and the Werumata limestone project
(Figure 1).
ASX Release: 30 April 2026
Estrella Resources Limited
ABN 39 151 155 207
ASX Code: ESR
Board and Management
Managing Director
Christopher Daws
Chief Executive Officer
Robert Mencel
Non-Executive Directors
Les Pereira
John Kingswood
Company Secretary
Stephen Brockhurst
Benjamin Smith
Address
Level 8, London House
216 St Georges Terrace Perth
WA 6000
PO Box 2517 Perth WA 6831
Telephone: +61 8 9481 0389
Facsimile: +61 8 9463 6103
info@estrellaresources.com.au
www.estrellaresources.com.au
Commenting on activities completed during the quarter, Managing Director Chris Daws said:
“It’s been a hugely significant period for Estrella in which the Company has commenced early-stage
mining operations in Timor-Leste, representing the nation’s first ever minerals extraction event
following the introduction of a modern mining code.
Emphasising the speed and scale of this opportunity, Estrella only made initial discoveries at Ira Miri
in February 2025 with the receipt of some excellent rock chip assays. In just over 12 months we have
accelerated from very early exploration to development of the Ira Miri pit.
Further emphasising the speed and scale of our work, during the quarter Estrella received approvals
for extraction of a market sample, constructed the pit using predominantly local labour (with zero LTIs)
and we now sit on the precipice of exporting this market sample to potential customers.
With plenty of exploration and development news in the pipeline, there’s never been a more exciting
time to be a shareholder. Go Estrella!
Figure 1: Location of Estrella Resources’ Timor-Leste concessions
IRA MIRI MANGANESE PROJECT
In January, Estrella advised that the Company had successfully executed an agreement with the
Autoridade Nacional dos Minerais, I.P. (ANM) of Timor-Leste authorising the extraction of up to 30,000
tonnes (30kT) of high-grade manganese oxide from the Ira Miri Manganese Project for market appraisal
purposes1.
The agreement provides a clear regulatory framework under which the Company may conduct sample
extraction, prepare material for sale, and remit applicable government fees equivalent to standard
mining royalties.
The sample is Timor-Leste’s first-ever economic mineral bulk extraction under its modern Mining Code
and will provide material for sale, export and testing with potential future long-term customers.
Following the agreement, the Company quickly commenced extraction activities undertaken by a local
contractor operating a sizable fleet which initially included three production excavators and bulldozers,
a loader, backhoe and ancillary excavator, supported by twelve local community dump trucks fitted with
mud chains for wet-season operations2.
Project management tasks were closely supervised by Estrella’s geological and engineering teams
which are maintaining detailed metallurgical, quality and commercial assessments of the Ira Miri
manganese ore.
The well-defined pit was designed to excavate intersected mineralisation reported previously, which
includes very high grades (e.g., EMDD002; 8.05m @ 53% Mn) and impressive thicknesses (e.g.,
EMDD033; 11.97m @ 28.9% Mn3).
The pit conception is depicted below (Figure 2) and had a maximum depth of approximately 15m with
total excavation of approximately 85,000 cubic metres. The topsoil will be stored separately for
rehabilitation, and the overburden will be stored in benched external stockpile (See Figure 2).
Figure 2: Ira Miri manganese bulk sample extraction location and pit design overlayed with drill assay results
The export program will see Estrella use local contractors to move the stockpiled manganese
approximately 17 km from the Stage 1 government approved head port stockpile to the existing barge
landing site: the LCT port site.
Material will be loaded onto a barge and shipped offshore to be on-loaded into a bulk carrier, avoiding
lengthy road transport. Transporting bulk material by barge to offshore bulk carriers is a well-established
and commonly used practice across the archipelago region.
1 Refer to ASX Announcement dated 8 January 2026
2 Refer to ASX Announcement dated 22 January 2026
3 See ASX Announcements dated: 12 & 18 December 2025 and, 4 September 2025
The approved sampling extraction will enable Estrella to undertake detailed metallurgical, quality and
commercial assessments of the Ira Miri manganese ore with a range of prospective buyers in the
international seaborne manganese market.
By February, Estrella reported the manganese-bearing mineralised horizon had been successfully
intercepted as part of pit excavation activities, validating the Company’s exploration model and providing
further confidence in project development (Figure 3)4.
Figure 3: typical geological horizons at the Ira Miri manganese pit excavation
Following the encounter of mineralisation, production was ramped up with further heavy equipment
arriving plus lighting towers to facilitate night shifts. Additionally, the Stage 1 port stockpile area
commenced receiving initial manganese ore.
Towards the end of February, Estrella reported ~22,600 tonnes of the permitted 30,000-tonne
manganese market sample had been successfully extracted5.
Mineralisation extracted from the Ira Miri pit is currently located at the designated port stockpile for
logistical preparation and shipment planning (Figure 4).
4 Refer to ASX Announcement dated 6 February 2026
5 Refer to ASX Announcement dated 26 February 2026
Figure 4: Stockpiled ore encountered from various depths, stratified by interpreted grades
Intersected mineralisation is supported by Induced Polarisation (IP) data which highlights large, highly
chargeable anomalies beneath the current pit design—consistent with potential supergene manganese
accumulations. These SE and NW deep anomalies remain untested, representing compelling targets
for future drilling and potential project growth.
The anomalies have significant potential to expand current manganese extractions and represent high-
priority follow-up drill targets.
In addition to the excavation activities, Estrella also advised the Autoridade Nacional dos Minerais, I.P.
(ANM) of Timor-Leste had approved the port stockpile location, enabling the site for use. Estrella will
arrange the DSO to be on-loaded into a bulk carrier, avoiding lengthy road transport.
Estrella is reviewing logistics and preparing the Ira Miri port stockpile to meet customer specifications.
Barging and trans-shipment into an offshore bulk carrier is a standard practice throughout the region
that Estrella will be utilise to optimise efficiency.
Following strong early-stage operational success, Estrella intends to apply for a Category A Mining
Licence with the ANM. This licence will enable full-scale development of the Ira Miri Manganese Project.
WERUMATA LIMESTONE PROJECT
Estrella significantly progressed its Werumata limestone project during the quarter, with the Company
targeting the development of a 500Mt Inferred Mineral Resource.
Figure 5: Diamond drillhole WLD001 at the Werumata Limestone Project
During the period, Estrella announced assay results from its maiden drill programme, which encountered
broad intersections of low impurity mineralisation6.
Drill activities targeted two large limestone plateaus located near the coastal town of Uero-Mata and
potential port area (Figure 6) with 33 RC drill holes (for 2,804m) and 9 diamond holes (for 913.10m)
completed for a total of 3,717m drilled.
Initial assays for holes WLR001 – WLR011 were received following sample inspection by Timor-Leste
government agencies and dispatch to PT Geoservices in Jakarta Indonesia and all assays were
received following the same protocol in March7.
6 Refer to ASX Announcement dated 11 February 2026
7 Refer to ASX Announcement dated 16 March 2026
Figure 6: Location of All drill-holes, Werumata Limestone Project.
The assay results were highly encouraging with Baucau Limestone intersections up to 87m*, averaging
30m, and Batu Putih Chalk intersections up to 59m*, also averaging 30m.
*The stated intersections are down-hole lengths but likely to be very close to true thickness.
The Baucau Limestone is a young (less than 2 million years old) formation comprised of former coral
reefs and other carbonate rocks typical of modern coral reefs and, like modern reefs is comprised of
different facies, e.g., fore-reef, reef flats and shoreline, but all are carbonate-rich. It is exposed along
the present-day coastline and as a dissected plateau and generally thickens northwards. The limestone
includes distinct facies but has an average grade of 83% CaCO3.
The silica (SiO2) content of the Baucau Limestone varies according to the facies (with former beaches
being sandier) and is also influenced by weathering, with leaching of Ca resulting in a relative increased
proportion of insoluble silica. Overall, the Baucau Limestone averages 8.34% SiO2.
Unlike many marine limestones, the magnesium content is very low, averaging only 2.05% MgO. The
average alumina (Al2O3) content is also low (1.83%), as is the average ferric oxide content (0.96%).
The overall composition of the Baucau Limestone suggests that the limestone has strong potential to
be used for acid-neutralisation in large scale industrial applications.
In many, but not all locations, underlying the Baucau Limestone there is chalk of the Batu Putih
Formation. The variable presence and thickness of the chalk is a result of the contact between the
younger Baucau Limestone and the Batu Putih Formation (approximately 5 million years old) being an
erosional surface. In some locations much if not all the Batu Putih Formation had eroded before
deposition of the Baucau Formation, such that in places, the Baucau Formation lays directly on much
older rocks.
The most distinctive unit of the Batu Putih Formation is chalk. The chalk varies in texture and
composition, chiefly through variations in silica content, which is higher (average 12.68% SiO2) than the
Baucau Limestone. The chalk has a very low magnesium content (1.11% MgO) but average alumina
(Al2O3) content (3.82%) and average ferric oxide content (1.74%) are greater than the Baucau
Limestone.
Beneath both the Baucau Limestone and the Batu Putih Chalk there is a variable thickness of a gritty,
clayey calcareous rock interpreted as a Marl. Estrella’s discovery of these marl units is a significant
contribution to the understanding of the geology of Timor Leste
Completion of a Mineral Resource Estimate for the Werumata Limestone deposit requires determination
of the bulk density values. Work has commenced, with Estrella collaborating with the Universidade
Nacional Timor Lorosa'e (UNTL) to complete bulk density assessments. Estrella already possesses a
strong collaborative relationship with UNTL, which provided the sample preparation laboratory site,
which is currently being established and will be the first facility of its kind to cater for the mineral industry
in Timor Leste. When this laboratory becomes operational, it will assist delivery of assay results in a
more cost effective, predictable and rapid manner.
The complete set of data required to complete the MRE has been delivered to consultants with results
anticipated to assist in the production of a maiden MRE..
CORPORATE
During the period, Estrella announced Robert Mencel has agreed to join Estrella as Chief Executive
Officer with a structured transition to Managing Director by 30 June 2026. Current Managing Director
Mr Chris Daws is expected to remain within the Estrella Group as Business Development Officer8.
On 13 March 2026, The Company provided an update regarding its legal rights and interests in the Mt
Edwards Lithium Royalty. The Board continues to protect these important assets of the Company and
advised of the commencement of proceedings in the Supreme Court of Western Australia against WIN
Metals Limited (ASX:WIN) (and its wholly owned subsidiaries), Auric Mining Limited (ASX: AWJ) (and
its wholly-owned subsidiaries), and Neometals Limited (ASX: NMT) concerning its royalty rights in
respect to lithium bearing ore. The Company advised that pleadings have been filed in the proceedings
and the matter has been listed for mediation on 29 April 2026. The Board will continue to provide further
updates to shareholders if and as material developments occur, in accordance with the ASX Listing
Rules and the Company’s continuous disclosure obligations.
The Company reiterates that it does not expect this litigation to impact its current operations.
CAPITAL
The Company’s cash balance as at 31 March 2026 was $336k.
During the period, Estrella significantly improved its cash position following the underwriting of its Listed
Options (ASX: ESROB), in two separate agreements.
In February, the Company announced it had entered into an option underwriting agreement with
Lightview Asset Pty Ltd to partially underwrite the exercise of existing quoted options issued by the
Company9. The listed options are exercisable at $0.018 each and expire at 5:00pm (AWST) on 13
December 2026 (“Expiry Date”) (ASX:ESROB) (“Options”). A total of 111,111,111 Options, were
8 Refer to ASX announcement dated 5 January 2026
9 Refer to ASX announcement dated 2 February 2026
underwritten totalling $2,000,000 before costs. This involves the Underwriters subscribing or procuring
subscriptions for such number of shares as is equal to the number of Underwritten Options which are
not exercised by the Expiry Date (such number of shares being the “Shortfall Shares”). Listed options
were underwritten for a total fee of 6%.
At the end of the period, Estrella also entered into an option underwriting agreement with Million Link
(China) Investment Ltd (Million Link) to underwrite the majority balance of existing quoted (ESROB)
options issued by the Company10. A total of 445,000,000 Listed Options were underwritten representing
$8,010,000 before costs. Underwritten funds with Million Link were receivable via two tranche payments
of $4,005,000 with the first tranche received by the Company within 5 days of executing the Underwriting
Agreement, and the second tranche of $4,005,000 receivable within 40 days. The Options were
underwritten for a fee of 8%, as well as 10,000,000 new unlisted 3-year $0.045 exercise options per
$1,000,000 of underwriting funds received by the Company, subject to a 25% penalty if the full amount
of $8,010,000 is not received within 40 days. The total of 80,000,000 new unlisted options exercisable
at $0.045, expiring 3-years from the date of issue will be issued under the Company’s current ASX
Listing Rule 7.1 placement capacity on the receipt of funds in full after 40 days.
Any Shortfall Shares to be issued to the Underwriters (and any sub-underwriters, if appointed) under
the Underwriting Agreement are expected to be issued in accordance with ASX Listing Rule 7.2
(Exception 10) and will not require shareholder approval nor count toward the Company’s placement
capacity under ASX Listing Rule 7.1.
With Tranche 1 funds received, the Company expects the Tranche 2 funds of $4,005,000 to be received
within the timeframe specified under the agreement of 40 days.
Total amount paid to related parties of Estrella and their associates, as per item 6.1 of the Appendix 5B,
was $56k for Directors fees, salaries and superannuation and the total amount paid to related parties of
Estrella and their associates, as per item 6.2 of the Appendix 5B, was $33k for Director’s salaries.
The Company continues to take steps to protect its legal rights and interests in the Mt Edwards Lithium
Royalty. The Board will protect these important assets of the Company and will be providing further
updates as material developments occur in accordance with the ASX Listing Rules and the Company’s
continuous disclosure obligations. Refer to Companies latest update in ASX Announcement dated 13
March 2026.
EXPLORATION
ASX Listing Rule 5.3.1: Exploration and Evaluation Expenditure during the Quarter was $0.106M.
ASX Listing Rule 5.3.2: The Company $1.948m on mining production activities during the quarter for its
sample extraction in Timor-Leste.
ASX Listing Rule 5.3.3: Refer to Appendix 1 for Estrella Tenement Information. No changes to
tenements throughout the period.
Table 1: Estrella Capital structure as at 31 March 2026
Fully Paid Ordinary Shares 2,210,536,962
Listed options exercisable 559,843,386
Unlisted options exercisable 515,000,000
Share Performance Rights 150,500,000
10 Refer to ASX announcement dated 31 March 2026
ENDS
The Board of Directors of Estrella Resources Limited authorised this announcement to be given to ASX.
FURTHER INFORMATION CONTACT
Christopher J. Daws
Managing Director
Estrella Resources Limited
info@estrellaresources.com.au
P: +61 (08) 9481 0389
Media Contact:
David Tasker
Chapter One Advisors
Email: dtasker@chapteroneadvisors.com.au
Tel: 0433 112 936
Compliance Statement
With reference to previously reported Exploration Results and Mineral Resources, the Company confirms that it is
not aware of any new information or data that materially affects the information included in the original market
announcement and, in the case of estimates of Mineral Resources, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not
materially changed. The Company confirms that the form and context in which the Competent Person’s findings
are presented have not been materially modified from the original market announcement.
Forward Looking Statements
This announcement contains certain forward-looking statements which have not been based solely on historical
facts but, rather, on ESR’s current expectations about future events and on a number of assumptions which are
subject to significant uncertainties and contingencies many of which are outside the control of ESR and its directors,
officers and advisers.
Competent Person Statement
The information in this announcement relating to Exploration Results is based on information compiled by Peter
Spitalny, who is the Exploration Manager, Timor Leste of Estrella Resources, and a Fellow of The Australasian
Institute of Mining and Metallurgy. Mr Spitalny has sufficient experience relevant to the style of mineralisation and
type of deposit under consideration, and to the activity they are undertaking to qualify as Competent Persons as
defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resource and
Ore Reserves”. Mr Spitalny consents to the inclusion in the report of the matters based on their information in the
form and context in which it appears.
Cautionary Statement
The Company draws attention to uncertainty in reporting visual results. Visual estimates of mineral abundance
should never be considered a proxy or substitute for laboratory analyses where concentrations or grades are the
factor of principal economic interest. Visual estimates also potentially provide no information regarding impurities
or deleterious physical properties relevant to valuations.
Appendix 1 – Tenement Information as Required by Listing Rule 5.3.3
Country Location Project Tenement
Change
in
Holding
(%)
Current
Interest (%)
Australia
WA Carr Boyd Nickel Project E29/1012 - 100
Australia
WA Carr Boyd Nickel Project E29/0982 - 100
Australia
WA Carr Boyd Nickel Project L24/0186 - 100
Australia
WA Carr Boyd Nickel Project E31/0726 - 100
Australia
WA Carr Boyd Nickel Project E31/1124 - 100
Australia
WA Carr Boyd Nickel Project M31/0012 - 100
Australia
WA Carr Boyd Nickel Project M31/0109 - 100
Australia
WA Carr Boyd Nickel Project M31/0159 - 100
Australia
WA Carr Boyd Nickel Project E31/1215 - 100
Australia
WA Carr Boyd Nickel Project E31/1162 - 100
Australia
WA Carr Boyd Nickel Project E31/1381 - 100
Australia
WA Spargoville Nickel Project M15/395 - 100*
Australia
WA Spargoville Nickel Project M15/703 - 100*
Australia
WA Spargoville Nickel Project M15/1828 - 100*
Australia
WA Spargoville Nickel Project L15/128 - 100*
Australia
WA Spargoville Nickel Project L15/255 - 100*
Timor-Leste
Lautem Lautem Exploration Project MEL2023-CA-ZA001 - 100**
Timor-Leste
Lautem Lautem Exploration Project MEL2023-CA-ZA002 - 100**
Timor-Leste
Lautem Lautem Exploration Project MEL2023-CA-ZA003 - 100**
Timor-Leste Lautem Lautem Exploration Project MEL2025-DA-ZA001
(ex ESR-RP-01)
- 100
Timor-Leste Lautem Lautem Exploration Project MEL2025-DA-ZA002
(ex ESR-RP-02)
- 100
Timor-Leste Lautem Lautem Exploration Project
MEL2025-DA-ZA003
(ex ESR-RP-03)
- 100
Timor-Leste Lautem Lautem Exploration Project
MEL2025-DA-ZA004
(ex ESR-RP-04)
- 100
Timor-Leste
Lautem Lautem Exploration Project ESR-RP-05 - 100
Timor-Leste
Lautem Lautem Exploration Project ESR-RP-07 - 100
Timor-Leste
Lautem Lautem Exploration Project ESR-RP-08 - 100
Timor-Leste
Baucau Baucau Exploration Project MEL2024-DA-ZB001 - 100**
Timor-Leste
Baucau Baucau Exploration Project MEL2024-DA-ZB002 - 100**
Timor-Leste
Baucau Baucau Exploration Project MEL2024-DA-ZB003 - 100**
Timor-Leste
Baucau Baucau Exploration Project MEL2024-DA-ZB004 - 100**
* Nickel rights only
** Free carry Murak Rai Timor 30% up to publication of DFS or similar
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Estrella Resources Limited
ABN Quarter ended (“current quarter”)
39 151 155 207 31 March 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date (9
months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (56) (210)
(e) administration and corporate costs (397) (1,303)
1.3 Dividends received (see note 3) - -
1.4 Interest received 1 31
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(452) (1,482)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment * (2) (2)
(d) exploration & evaluation (2,054) (6,796)
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (9
months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material)
R&D expenditure refund - -
2.6 Net cash from / (used in) investing
activities
(2,056) (6,798)
3. Cash flows from financing activities
2,000 2,000
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options 46 199
3.4 Transaction costs related to issues of equity
securities or convertible debt securities (120) (141)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (provide details if material)
Proceeds received in advance for Option
exercise
- -
3.10 Net cash from / (used in) financing
activities
1,926 2,058
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period 918 6,558
4.2 Net cash from / (used in) operating
activities (item 1.9 above) (452) (1,482)
4.3 Net cash from / (used in) investing activities
(item 2.6 above) (2,056) (6,798)
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (9
months)
$A’000
4.4 Net cash from / (used in) financing activities
(item 3.10 above) 1,926 2,058
4.5 Effect of movement in exchange rates on
cash held - -
4.6 Cash and cash equivalents at end of
period 336 336
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 336 918
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other (cash held on trust subject to
shareholder approval at 15 August 2025
meeting)
- -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above) 336 918
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
(56)
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
(33)
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (please specify)
R & D financing facility - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (452)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(2,054)
8.3 Total relevant outgoings (item 8.1 + item 8.2) (2,506)
8.4 Cash and cash equivalents at quarter end (item 4.6) 336
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 336
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
0.13
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: The Company will continue to spend funds on its Timor-Leste project, with a
continued focus on exploration at its Werumata Limestone project, and development
of its Manganese project including its sample extraction.
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: Yes, the Company will be required to raise further cash to fund its operations. The
Company has executed a listed option underwri