5A Resource Confirmation Drilling Commenced
HIGHLIGHTS
Nickel sulphide resource confirmation and metallurgical drilling underway Spargoville 5A
DFS to be updated utilising this additional drilling
Mine planning underway for SMP pit cut-back at 5A nickel mine
Picture 1. Picture of TDA Diamond rig located at the 5A nickel mine.
Estrella Resources Limited (ASX: ESR) (Estrella or the Company) is pleased to announce that Top Drive Australia
(TDA) have mobilised to the Spargoville Nickel Rights Project to undertake resource confirmation drilling at the
Company’s 5A nickel mine to aid in completion of a Definative Feasibility Study for the mining of the 5A nickel
resource. Recent strength and the robust outlook for the nickel market have caused the Company to re-evaluate its
strategy for the Spargoville Nickel Rights Project located only 20km’s from Western Australia preeminent nickel
sulphide district at Kambalda. The Company withdrew the project for sale after the receipt of serval offers were
made and a formal sale process was being undertaken as the price of nickel has appreciated to levels not seen for
more than 15 years.
Estrella Managing Director Chris Daws commented:
“5A represents an early nickel producing opportunity for Estrella via an extremely simple SMP open pit cutback operation accessing valuable nickel tonnes. With the re-start of the Kambalda Nickel Concentrator at
Kambalda by BHP-Billiton to treat third-party ores the location and timing of developing 5A is obvious. Our
relationships with drilling and mine service groups are aiding in our efforts to make the most of what we
have in the backdrop of an incredible nickel market.”
_________________________________________________________________________________
At current nickel prices the 5A nickel mine cut-back represents an early cash-flow generating opportunity for the
Company which could then be utilised for the development of the Carr Boyd nickel mine (Carr Boyd Ni/Cu Project),
T5 resource expansion/definition drilling and to progress the 5B nickel mine, 1A nickel mine and Andrews nickel
mine development opportunities (Spargoville Nickel Rights Project).
The 5A Nickel Mine is envisaged as an 80m deep cutback of the existing 5A open pit which is currently 30m deep
(see Figure 3). Further pit wall geotechnical studies will be undertaken to refine optimal pit designs to access the
5A mineralisation. The mine optimisation and pit designs will be completed by independent third parties upon the
completion of drilling and resource estimation with additional metallurgical studies. Mining professionals specialising
in open pit mine project development have been engaged and will be assisting the Company in preparing, reviewing
and submitting its mining development plans with relevant authorities.
An important feature of the nickel right assets at Spargoville is that they are free of third-party royalty’s (other than
W.A. State Government royalty on nickel) that impact most of the nickel sulphide assets in the Widgiemooltha and
Kambalda district. Thus, timing of profitable development comes much earlier than assets which are impeded by
such onerous and heavy royalty’s applied to many of those deposits. Although not all the 5A resource will be able
to be mined and recovered within the open pit cutback, the Company believes that a substantial portion will fall into
the economic category of the DFS to be mined, processed and sold.
The Company will be completing approximately 17 diamond holes into the 5A mine resource area which will aid
in final ore reserve calculations, metallurgical characteristics and final mine design parameters. Drilling is expected
to take 4-6 weeks to complete as the hole lengths will be relatively short to reach the anticipated maximum new
5A pit design depth. Assays for nickel intersections will be fast-tracked through the laboratory to aid in the speed
of the completion of the DFS, mine planning and permitting.
The Company has been fortunate that recent upgrades to water supplies in the area will assist the drilling efforts,
keeping costs to a minimum. Heavy earth moving fleet in the immediate 5A mine area has also aided the Company
in keeping costs down to establish drilling pads, sumps and to undertake some minor earth works around the 5A
pit in a very short timeframe.
Figure 1: Regional location of the Spargoville Nickel Rights Project
Figure 2: Location of Spargoville Nickel Rights Project and 5A Nickel Mine.
Figure 3. Illustration of the 5A pit and possible pit cut-back to 80m depth to access fresh high grade nickel sulphide ore.
Table1 – 5A October 2019 Mineral Resource Estimate (0.5% Nickel Cut-off)1
Type
Saprolite
Saprock
Fresh
Total
Type
Saprolite
Saprock
Fresh
Total
Type
Saprolite
Saprock
Fresh
Total
Tonnage
kt
12
38
19
69
Ni
%
1.0
2.2
3.7
2.4
Indicated Mineral Resource
Cu
Ni
%
t
0.10
120
0.19
830
0.24
680
0.19
1,630
Cu
t
10
70
40
130
Tonnage
kt
11
17
29
58
Ni
%
0.9
1.0
1.6
1.3
Inferred Mineral Resource
Cu
Ni
%
t
0.10
100
0.14
170
0.10
470
0.11
730
Cu
t
10
20
30
70
Tonnage
kt
24
55
48
127
Ni
%
0.9
1.8
2.4
1.9
Total Mineral Resource
Cu
Ni
%
t
0.10
220
0.17
1,000
0.15
1,140
0.15
2,370
Cu
t
20
100
70
190
1
Refer to ASX release dated 18 October 2019 (ASX: ESR)
The Board has authorised for this announcement to be released to the ASX.
FURTHER INFORMATION CONTACT
Christopher J. Daws
Managing Director
Estrella Resources Limited
+61 8 9481 0389
info@estrellaresources.com.au
Media:
David Tasker
Managing Director
Chapter One Advisors
E: dtasker@chapteroneadvisors.com.au
T: +61 433 112 936
Compliance Statement
With reference to previously reported Exploration results and mineral resources, the company confirms that it is not aware
of any new information or data that materially affects the information included in the original market announcement and, in
the case of estimates of Mineral Resources or Ore Reserves that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The
company confirms that the form and context in which the Competent Person’s findings are presented have not been
materially modified from the original market announcement.
Forward Looking Statements
This announcement contains certain forward looking statements which have not been based solely on historical facts but,
rather, on ESR’s current expectations about future events and on a number of assumptions which are subject to significant
uncertainties and contingencies many of which are outside the control of ESR and its directors, officers and advisers.
Share your feedback
Discover