Spargoville 5A Nickel Mine
Released
Released
Announcement PDF
ASX:ESR
16 October 2023
Spargoville 5A Interim Feasibility Work Outlines
Excellent Development Opportunity
HIGHLIGHTS
➔ Spargoville 5A Interim Prefeasibility Study demonstrates the viability of the 5A Underground Nickel Mine
➔ Successful trial parcel to Glencore HPAL confirms maximum recovery processing pathway for 5A
➔ Simple decline and 2 level underground mine with long-hole stoping over 6-month time-frame
➔ Probable Reserve of 1043t Ni metal and 24t Co metal from 28kt of mined material
➔ Ongoing discussions with respect to devising optimal operational scenarios
➔ Total estimated capital and operating cost AU$11.0M*, or US$3.20/lb Ni for project life**
➔ Total project life of 10 months including crushing and haulage
➔ Underground decline and stope design undergoing final optimisation
➔ Short-list of preferred contractors selected
➔ Work to begin with individual contractors to optimise design and cost parameters to feasibility level
➔ Mining and Environmental approvals in progress assisted by MBS Environmental
* Costs estimates are within +/- 25%
** Study assumes a USD/AUD XR of 0.67
Figure 1: Proposed Cutback, decline and stope design for the 5A Nickel Mine
_________________________________________________________________________________
Office Address London House, Level 8, 216 St Georges Terrace, PERTH WA 6000 Postal Address GPO Box 2517, PERTH WA 6831
Phone +61 8 9481 0389 Fax +61 8 9463 6103
Email info@estrellaresources.com.au
Estrella Resources Limited (ASX: ESR) (Estrella or the Company) is pleased to announce the current
progress on the Spargoville 5A Nickel Mine, located approximately 20km Southwest of Kambalda.
Appended to this release is the bulk of the current feasibility study showing the significant potential of the
5A high-grade nickel sulphides which lie just below the current open pit.
Estrella is currently working towards commercial terms and financing for the Spargoville Project which,
when completed, will be used to finalise the project economic model and final feasibility.
Estrella Managing Director Chris Daws commented:
“I am very pleased to provide this interim PFS which reflects a step towards the completion of our
Definitive Feasibility Study (DFS). The following report outlines a compelling opportunity with
significant detail on the costs associated with establishing a mining operation. However, some
commercial terms remain outstanding which prevent us from providing further detail to a DFS-level.
The report outlines a small-scale mining operation of a high-grade resource body which presents an
ideal operation for a company of Estrella’s current size.
We are excited to continue to develop the opportunity at 5A, particularly given the successful delivery
of the metallurgical sample to Glencore. Having confirmed the metallurgical properties of our ore,
Estrella has passed a very significant milestone on the way to getting the Spargoville Nickel Project
into production.”
Cautionary and Competent Persons Statements
100% of the Life of Mine (LoM) production target in the PFS is from solely Measured Mineral Resources in
accordance with JORC 2012 Edition Guidelines. There is a high level of geological confidence associated
with Measured Mineral Resources.
The information in this announcement relating to the Mineral Resource estimate for the Spargoville 5A
Deposit was first released by the Company to the ASX on 18 October 2022. The Company confirms that it
is not aware of any new information or data that materially affects the information included in the original
market announcements and that all material assumptions and technical parameters underpinning the
Mineral Resource and Ore Reserve estimates continue to apply and have not materially changed. The
Mineral Resource and Ore Reserve estimates underpinning the production targets disclosed in this
announcement have been prepared by Competent Persons in accordance with the requirements of the
2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves.
Accuracy
This feasibility work has been prepared to an overall level of accuracy of approximately ±20-25%.
Forward-Looking Statements
This announcement contains “forward-looking information” that are based on the Company’s expectations,
estimates and projections as of the date on which the statements were made. This forward-looking
information includes, among other things, statements with respect to the PFS, the Company’s business
strategy, plan, development, objectives, performance, outlook, growth, cashflow, projections, targets and
expectations, Mineral Resources, potential Ore Reserves, results of exploration and related expenses.
Generally, this forward-looking information can be identified by the use of forward-looking terminology such
as, 'anticipate', 'project’, 'target', 'likely', 'believe', 'estimate', 'expect', 'intend', 'may', 'would', 'could', 'should',
'scheduled', 'will’, 'plan', 'forecast’, 'evolve' and similar expressions. Persons reading this announcement
are cautioned that such statements are only predictions, and that the Company’s actual future results or
performance may be materially different.
The Company believes the forward-looking information in this announcement is based on reasonable
grounds. However, neither the Company nor any other person makes or gives any representation,
assurance or guarantee that the production targets or expected outcomes in this announcement will
ultimately be achieved. The forward-looking information in this announcement is subject to known and
unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of
activity, performance or achievements to be materially different from those expressed or implied by such
forward-looking information. Such risks include but are not limited to future prices and demand of nickel
and cobalt; foreign exchange rates; availability of funding; results of further optimisation activities; changes
2|Page
in project parameters as plans continue to be refined; failure of plant; equipment or processes to operate
as anticipated; possible variations of ore grade or recovery rates; accident, labour disputes and other risks
of the mining industry; delays in obtaining governmental approvals or financing or in the completion of
development or construction activities and general business, economic, competitive, political and social
uncertainties.
A number of key steps need to be completed in order to achieve production at the project. Many of these
steps are referred to in this announcement. Investors should note if there are delays associated with
completing those steps, or completion of the steps does not yield the anticipated results, the actual
estimated production and forecast financial information may differ materially from the PFS results presented
in this announcement.
These risks are not exhaustive of the factors that may affect or impact forward-looking information. These
and other factors should be considered carefully, and readers should not place undue reliance on such
forward-looking information. The Company disclaims any intent or obligations to revise any forward-looking
statements whether as a result of new information, estimates, or options, future events or results or
otherwise, unless required to do so by law.
NEXT STEPS
The Company is advancing its way through the DFS process and is working with a number of specialist
contractors to finalise design and mining, crushing and transport costings to a higher confidence level.
A number of areas remain open to optimisation to further reduce costs or increase revenue. These include:
•
•
•
•
Level development size and resulting ground support regime in line with individual contractor
equipment sizing and availability
Stope backfill and optimisations to control and reduce dilution, increasing mine grades
Obtaining updated crushing and trucking costs and timing based on predicted mining tonnage
Finalising commercial terms around processing, product value and mine development funding
The Company remains buoyed by strong nickel market forecasts and looks forward in getting 5A into a
position of immediate development readiness.
The Board has authorised for this announcement to be released to the ASX.
FURTHER INFORMATION CONTACT
Christopher J. Daws
Managing Director
Estrella Resources Limited
+61 8 9481 0389
info@estrellaresources.com.au
Media:
David Tasker
Managing Director
Chapter One Advisors
E: dtasker@chapteroneadvisors.com.au
T: +61 433 112 936
3|Page
Spargoville 5A Underground Prefeasibility Study
EXECUTIVE SUMMARY
A potential mining opportunity exists for nickel sulphide ore production from a small underground operation
at the Spargoville 5A nickel deposit, which is situated 20km West of Kambalda in Western Australia. The
5A nickel deposit is located on M15/395. The mining lease is operated by Maximus Resources, however
Estrella holds the nickel rights to the tenement and has agreements in place with Maximus to operate a
mine.
Figure 2: Location of the 5A Nickel Mine within M15/395
The possibility to generate revenue from 5A is based around a processing pathway via the Murrin Murrin
HPAL Plant, located in the northeastern Goldfields, where the Company successfully processed a 2,500t
trial parcel of 5A transitional massive sulphide in early 2023.
The 5A deposit is a Kambalda-style nickel sulphide deposit. A Mineral Resource of 124Kt at 1.9% Ni was
estimated in October 2022 by Ashmore Advisory (Table 1). This resource estimate was commissioned as
a result of an infill drilling program, where twenty diamond holes were completed by Estrella in July 2022
to confirm the metallurgical characteristics of the 5A massive sulphide below the existing open pit.
Very high grades were observed from the transitional massive sulphides and as such an appropriate
processing pathway was selected for the bulk trial sample (which was not amenable to traditional flotation
techniques).
4|Page
Table 1: 5A Mineral Resource Estimate Summary by Mineralisation Type (at a 0.5% Cut-off) - October 2022
Type
Disseminated
Matrix/Breccia
Massive
Total
Type
Disseminated
Matrix/Breccia
Massive
Total
Type
Disseminated
Matrix/Breccia
Total
Type
Disseminated
Matrix/Breccia
Massive
Total
Tonnage
kt
25
18
10
60
Measured Mineral Resource
Ni
Cu
Co
Ni
%
%
%
t
0.66
0.04
0.01
160
1.86
0.16
0.03
340
7.73
0.60
0.19
1,140
2.84
0.22
0.06
1,640
Cu
t
10
30
90
130
Co
t
4
10
30
40
Tonnage
kt
28
7
1
36
Indicated Mineral Resource
Ni
Cu
Co
Ni
%
%
%
t
0.64
0.04
0.02
180
1.51
0.12
0.03
110
8.16
0.50
0.20
80
1.02
0.07
0.02
370
Cu
t
10
10
10
20
Co
t
4
2
2
10
Tonnage
kt
23
7
30
Inferred Mineral Resource
Ni
Cu
Co
Ni
%
%
%
t
0.63
0.15
0.02
150
3.02
0.09
0.04
210
1.18
0.14
0.02
350
Cu
t
30
10
40
Co
t
4
3
10
Tonnage
kt
76
32
16
124
Total Mineral Resource
Ni
Cu
Co
Ni
%
%
%
t
0.64
0.07
0.02
490
2.03
0.14
0.03
650
7.76
0.59
0.19
1,230
1.91
0.15
0.04
2,370
Cu
t
50
40
90
190
Co
t
10
10
30
50
The opportunity exists to mine the high-grade massive sulphide and matrix material immediately below the
open pit floor. The proposed underground mining method utilises bottom-up, long-hole open stoping over
two levels, with the bottom level backfilled to maximise stope stability. A 4m x 4m decline is proposed to
access the massive sulphide below the existing pit and facilitate trucking of the ore to surface.
Utilising the resource estimate, proposed mining method, and allowing for foreseeable dilution and relevant
financial and operational considerations, it is estimated that the project has a Probable Reserve of
approximately 28kt tonnes at an average grade of 3.7% Ni for production of just over 1,043t of contained
nickel and 24t of contained cobalt. This is made up exclusively from mineralisation classified in the
JORC2012 Mineral Resource Estimate “Measured” category (Table 2).
The 5A Measured Resource has a high degree of geological confidence and well defined in size. Due to
this the metal content to be extracted within the Measured Resource is not expected to change materially
from that stated in this report, even with further material changes in mine design, costs and other
commercial negotiations.
Therefore, the selection of the Probable Reserve category (over Proven) only reflects uncertainty in
modifying factors such as ongoing commercial negotiations and other optimisations currently being
conducted and is in line with the accuracy expected in a prefeasibility study. It is expected that the Probable
Reserve would wholly convert to Proven Reserve once the uncertainty level in the modifying factors is
better constrained. It is not anticipated, due to the finite size and high-grade of the Measured Resource,
that changes in the modifying factors will lead to a material change in further reserve calculations.
5|Page
Table 2: 5A Measured Mineral Resource Estimate by Ore Type - October 2022
Type
Tonnage
kt
25
18
10
60
Disseminated
Matrix/Breccia
Massive
Total
5A Measured Mineral Resource
Ni
Cu
Co
Ni
%
%
%
t
0.66
0.04
0.01
160
1.86
0.16
0.03
340
7.73
0.60
0.19
1,140
2.84
0.22
0.06
1,640
Cu
t
10
30
90
130
Co
t
4
10
30
40
A total Probable Reserve was estimated utilising a combination of costs received from mining contractors
specialising in narrow-vein underground mining, and actual costs incurred and tracked during the mining of
the trial parcel. The underground design was optimised to mine for maximum revenue and lowest cost
whilst maintaining geotechnical stability and minimal dilution.
The resulting Probable Reserve is presented in Table 3.
Table 3: 5A Probable Reserve Summary - October 2023
Mining
Level
Method
All
Ore Drive
Long
hole
Total
5A Total Probable Reserve
Ni
Mg
Mg
As
As
Co
t
%
t
ppm
t
%
240.1
4.77
340 1,422 10.1 0.08
Ore
kt
7.1
Ni
%
3.38
Co
t
5.8
Cu
Cu
%
t
0.25 18.0
21.1
3.81
802.9
5.02
1,059
1,248 26.3 0.09 18.4 0.29 60.6
28.2
3.70
1,043.1
4.96
1,399
1,292 36.4 0.09 24.2 0.28 78.6
SITE LAYOUT AND INFRASTRUCTURE
Access to the 5A Nickel Mine is via the sealed Coolgardie-Norseman Highway, followed by a 1.5km gravel,
all-weather site entry road. The site layout for the 5A Nickel Project aims to utilise existing disturbed areas
or previous mining structures wherever possible, limiting disturbance to only M15/395 or L15/444.
Due to previous mining on the tenement, three distinct areas will be established and utilised to form the
project site; the primary 5A Open Pit development area, the secondary 5B ROM Pad infrastructure area,
and the Andrews Shaft and Andrews Turkeys Nest support area.
Waste from the 5A ramp cutback and underground development will be added to the existing 5A Waste
Dump. Waste characterisation tests conducted by MBS indicate that all waste will be self-neutralising and
is not classed as acid-forming. However, sulphidic waste will be encapsulated within the waste dump
(Stockpile A) as a precautionary measure. The 5A layout is depicted in Figure 3.
6|Page
Figure 3: Site plan for the 5A work area showing waste dump extension, western ramp cutback and portal location.
Previous mining in the area has resulted in a large, cleared pad at the 5B Nickel Deposit just 1.2km south
of 5A. The 5B ROM Pad was used as the site to dump, crush and blend the 5A Trial Parcel for delivery to
Murrin Murrin in January 2023, and the Company intends to utilise this extensive area for the 5A ROM, site
offices and workshop.
Figure 4: 5B ROM pad, offices and workshop area
7|Page
The Andrew’s Shaft is situated just 400m west of the 5A Nickel Mine and is a ready source of mine water
with an existing, fully lined 1GL capacity turkey’s nest and standpipe. Water return from the mine will be
settled in tanks and returned to the turkey’s nest or Andrew’s Shaft.
OUTLINE OF PROJECT PLAN
The current estimated project life of 10 months within this study is conservative and can reasonably be
expected to be shortened by another month through optimisation of all stages.
Project costs are based on the use of specialist contractors for the five work phases of the project, those
being site establishment and ramp-cutback, underground mining, crushing, haulage and site
disestablishment.
Ramp Cut-back and Site Establishment
Broadly, the intended 5A Underground Mine will mine up to and break through into the existing 5A Open
Pit. To facilitate the geotechnical requirements of a clean, dilution-free breakthrough, an initial period of
open pit work will see the pit ramp moved to the west by 9m to accommodate expected slippage in the
lower western wall of the pit. This induced failure will stabilise a specific structure identified in the base of
the pit so that stope break-through into the pit floor will not cause a potential ramp failure or stope dilution.
The pit floor will then be cleaned up and surveyed. Additional surface works will include waste-dump and
ramp set-up, rehabilitation of the 5B ROM Pad and the setting up of water services and site power supplies.
During the initial one-month set-up period, it is expected that temporary, transportable office and ablution
blocks, along with a transportable “igloo-type” heavy equipment service facility inclusive of self-bunded fuel
tanks and lubricant dispensers will be established on site at the 5B infrastructure area by the underground
mining contractor. Additional facilities such as a small change room for the underground workforce and a
temporary washdown facility will be established.
Underground Mining
A portal will be mined into the northwest corner of the existing 5A pit wall. It is expected that rock conditions
will be generally good for underground development, with the decline designed in the competent western
basalt (geological footwall). Production stoping should encounter reasonable ground conditions, however,
the weaker ultramafic (geological hangingwall) rock on the eastern stope walls will require close
examination and monitoring to ensure expected dilution (overbreak and spalling) does not become
excessive. Some discreet structures exist which may have potential for localised small-scale failure, and
these will also require examination and monitoring upon exposure.
No adverse groundwater problems are anticipated, with relatively minor volumes consistent with other
mining operations in the area expected. A moderate level of pump capacity has been allowed for to ensure
greater groundwater volumes can be dewatered if necessary.
The Reserve is expected to be extracted over a period of six-and-a-half months. Two levels will be
established followed by bottom-up long-hole stoping. The lower stope will require back-filling to ensure the
stability of the upper stopes upon breakthrough into the open pit.
Crushing and Haulage
Ore mined will require a month of campaign crushing and a further one to two months of road train haulage
via public roads to the Murrin Murrin processing facility. Crushing and haulage rates to Murrin Murrin are
yet to be locked in as these will depend upon specific grade-control and other commercial requirements
that are currently under negotiation.
Sensitivity analysis shows the project is very sensitive to mined grade (dilution) and changes in the nickel
price. The development of a robust mining method with known dilution outcomes has been the focus of
studies to date. Further optimisation of the design with respect to expected costs will be the future focus of
study.
8|Page
The proposed 5A underground infrastructure will provide opportunities within the mine to conduct
exploration drilling and expansion of resources at depth.
GEOLOGY AND EXPLORATION
Regional Geology
The project area lies within the Coolgardie Domain, the western most domain of the Kalgoorlie Greenstone
Terrain, which stretches northwards from Norseman to Menzies. The Coolgardie Domain exhibits the
highest degree of metamorphism in the terrain, ranging from middle to upper greenschist facies.
The project is situated within a dominantly north-south striking belt of Archaean greenstone rocks that
extend north from the Widgiemooltha Dome. Three major rock types dominate the geology. These include
sediments, mafic volcanics and ultramafics, ranging from clastic meta-sediments, black shales and
volcanics, through to metabasalts and tholeiites to ultramafics, serpentinites and dunites. Strike slip faulting
and upright isoclinal folding may lead to the multiple repetition of individual units. The Mt Edwards and
Widgiemooltha groups of nickel deposits which lie to the south occur in the same mineralised anticlinal
zone of mafic to ultramafic metavolcanic rocks.
Stratigraphically, the meta-basalt is the oldest unit and is commonly exposed in the cores of anticlinal fold
structures, progressively followed by the ultramafic and meta-sediments. The dip of layering and subparallel metamorphic foliation is predominantly sixty-five degrees (65°) to eighty-five degrees (85°) to the
west, suggesting a westward tilt to the fold axes.
Nickel mineralised bodies at the project commonly form as lenses of massive sulphide up to several metres
thick within ultramafic rocks at or near the ultramafic / meta-basalt contact. A halo of disseminated, lowergrade, mineralisation often extends up to twenty (20) metres thick into the ultramafics and rare veins of
sulphide may be found in the underlying meta-basalt. The major ore bodies are all lensoidal with limited
extent down dip and along strike, suggesting structural control in the form of embayment structures or
depressions in the meta-basalt.
Local Geology
The 5A deposit is characterised as a Kambalda style (komatiite hosted) nickel sulphide deposit. This deposit
sits on the eastern limb of a regional anticlinal structure and is characterised by the accumulation of nickel
sulphides at the base of an ultramafic flow that overlies basalt.
The ultramafic unit that hosts the deposit strikes broadly north-south (015°) and dips vertically to steeply to
the west at -80° (refer to Figure 5). This unit is bounded to the west by meta-basalt and to the east by metasediments.
The oldest lithological unit at the deposit is an approximately three hundred (300) metre thick meta-basalt
unit that is situated to the west of the ultramafic rocks (locally forming the hanging wall, geological footwall).
This meta-basalt unit is fine grained and displays pillowed textures adjacent to the ultramafic contact. A
one (1) metre to ten (10) metre thick zone of black shale is interleaved within this meta-basalt unit
approximately thirty (30) metres to the west of the ultramafic contact. This black shale horizon occurs
parallel to stratigraphy. It is interpreted to be an interflow sediment and is a useful marker horizon in the
mine area.
Overlying the meta-basalt unit is the ultramafic sequence that hosts the deposit. This ultramafic unit is
between twenty-five (25) metres and fifty (50) metres thick and has been overturned by regional isoclinal
folding. The deposit is located along the western contact of this ultramafic unit and is hosted within a
moderate to coarse-grained dunite lens that has been altered to talc + chlorite + carbonate + tremolite.
This dunite lens grades into a medium-grained chlorite+tremolite rock. Towards the eastern edge of the
ultramafic unit, coarse-grained spinifex textures indicate the top of the ultramafic flow.
9|Page
Figure 5: Cross section through he 5A mineral resource
10 | P a g e
Mineralisation
The lens of nickel mineralisation at 5A strikes broadly north-south (015°) and dips steeply west (-80° to 90°) near-surface. At depth, the deposit generally continues to dip towards the west, however undulations
in the ultramafic footwall contact due to either paleo-topography or structural deformation have resulted in
the deposit dipping between -60° west and -50° east.
Three styles of nickel mineralisation occur at the 5A deposit; semi-massive to massive sulphide ore, matrix
ore and disseminated ore. These mineralisation styles have been identified based on sulphide content,
textures and have a direct correlation with ore grades.
Estrella intends to target the massive sulphide ore primarily. This is dominated by violarite and a sulphate
mineral called hexahydrite. The sulphate (hexahydrite) is soluble in water and accounts for up to twenty
five percent (25%) of the nickel content in the ore. It is of critical importance to ESR that wetting of ore piles
for dust suppression is kept to an absolute workable minimum to prevent nickel loss.
MINERAL RESOURCE
Ashmore Advisory Pty Ltd (ASH) was engaged by ESR to complete a Mineral Resource estimate in
accordance with the JORC 2012 Edition Guidelines for the 5A nickel deposit, in September and October
2022. For full details of the Mineral Resource Estimate, please refer to ASX Announcement dated 18
October 2022.
Figure 6: 5A MRE showing the area of the resource targeted by the underground mine
Drilling at the deposit extends to a vertical depth of approximately 340m and the mineralisation was
modelled from surface to a depth of approximately 150m below surface. The estimate is based on good
quality RC and diamond core data. Drill hole spacing is predominantly 10m by 10m across the breadth of
the mineralisation below the open pit, out to approximately 40m by 40m over the remaining areas.
The block model was created and estimated in Surpac using Ordinary Kriging (“OK”) grade interpolation.
The mineralisation was constrained by wireframes prepared using a variety of cut-offs for the various
sulphide mineralisation types. Disseminated sulphide was domained using a nominal 0.4% nickel cut-off,
plus geological logging, matrix sulphide was domained using a nominal 1.0% nickel cut-off, plus geological
logging; and semi-massive to massive sulphide mineralisation was domained using a 4.0% nickel cut-off,
plus geological logging.
The 5A Mineral Resource was classified as Measured, Indicated and Inferred Mineral Resource based on
data quality, sample spacing, and lode continuity. The Measured Mineral Resource was defined in the core
of the deposit that was drilled with close spaced RC and DD drilling of less than 10m by 10m. The Indicated
Mineral Resource was defined within areas of close spaced RC and DD drilling of less than 20m by 20m,
and where the continuity and predictability of the lode positions was good. The Inferred Mineral Resource
11 | P a g e
was assigned to areas where drill hole spacing was greater than 20m by 20m, where small, isolated pods
of mineralisation occur outside the main mineralised zones, and to geologically complex zones.
Material dry densities have been gained from the resource modelling work as indicated in Table 4 below:
Table 4: Summary of Material Densities Used for Resource Estimation
Weathering Type
Lithology
oxide
transitional
fresh
Waste
2.70
2.80
2.85
Disseminated
2.74
2.80
2.85
Matrix/Massive
2.74
Regression
Regression
The Statement of Mineral Resources compiled by Ashmore Advisory is in line with the requirements of the
2012 JORC Code.
Resource Summary
Results of the independent Mineral Resource estimate by Ashmore Advisory for 5A are shown in Table 5
and Table 6 below:
Table 5: 5A Mineral Resource Estimate by Ore Type
Type
Disseminated
Matrix/Breccia
Massive
Total
Type
Disseminated
Matrix/Breccia
Massive
Total
Type
Disseminated
Matrix/Breccia
Total
Type
Disseminated
Matrix/Breccia
Massive
Total
Tonnage
kt
25
18
10
60
Measured Mineral Resource
Ni
Cu
Co
Ni
%
%
%
t
0.66
0.04
0.01
160
1.86
0.16
0.03
340
7.73
0.60
0.19
1,140
2.84
0.22
0.06
1,640
Cu
t
10
30
90
130
Co
t
4
10
30
40
Tonnage
kt
28
7
1
36
Indicated Mineral Resource
Ni
Cu
Co
Ni
%
%
%
t
0.64
0.04
0.02
180
1.51
0.12
0.03
110
8.16
0.50
0.20
80
1.02
0.07
0.02
370
Cu
t
10
10
10
20
Co
t
4
2
2
10
Tonnage
kt
23
7
30
Inferred Mineral Resource
Ni
Cu
Co
Ni
%
%
%
t
0.63
0.15
0.02
150
3.02
0.09
0.04
210
1.18
0.14
0.02
350
Cu
t
30
10
40
Co
t
4
3
10
Tonnage
kt
76
32
16
124
Total Mineral Resource
Ni
Cu
Co
Ni
%
%
%
t
0.64
0.07
0.02
490
2.03
0.14
0.03
650
7.76
0.59
0.19
1,230
1.91
0.15
0.04
2,370
Cu
t
50
40
90
190
Co
t
10
10
30
50
12 | P a g e
Table 6: 5A Mineral Resource Estimate by Oxidation Type & JORC Classification
SP5A Total Mineral Resource by Oxidation Type and JORC Classification
Type
Oxide
Transition
Total
Type
Oxide
Transition
Total
Type
Oxide
Transition
Fresh
Total
Type
Oxide
Transition
Fresh
Total
September 2022 - 0.5% Ni Cut-off Grade
Measured Mineral Resource
Tonnage
Ni
Cu
Co
Ni
kt
%
%
%
t
4
1.61
0.17
0.04
70
53
2.95
0.22
0.07
1,570
60
2.84
0.22
0.06
1,640
Cu
t
10
120
130
Co
t
2
40
40
Ni
%
0.76
1.34
1.02
Indicated Mineral Resource
Cu
Co
Ni
%
%
t
0.06
0.02
150
0.08
0.03
220
0.07
0.02
370
Cu
t
10
10
20
Co
t
4
5
10
Ni
%
0.67
0.72
1.43
1.18
Inferred Mineral Resource
Cu
Co
Ni
%
%
t
0.12
0.02
30
0.25
0.02
40
0.11
0.03
280
0.14
0.02
350
Cu
t
10
10
20
40
Co
t
1
1
5
10
Ni
%
0.88
2.42
1.43
1.91
Total Mineral Resource
Cu
Co
Ni
%
%
t
0.09
0.02
250
0.19
0.05
1,840
0.11
0.03
280
0.15
0.04
2,370
Cu
t
20
150
20
190
Co
t
10
40
Tonnage
kt
20
17
36
Tonnage
kt
4
6
20
30
Tonnage
kt
28
76
20
124
50
Exploration and Resources Potential
The proposed 5A underground infrastructure will provide opportunities to conduct underground exploration
drilling targeting 5A extensions and additional prospects within drill distance of the proposed workings.
Underground drilling is expected to be much simpler and more cost effective than surface drilling, enabling
faster production rates and a lower exploration cost.
Estrella may also target the 5D Andrew’s nickel deposit, which is approximately five hundred metres to the
west of the 5A deposit, along with the Central Komatiite horizon that exists between Andrews and 5A. The
Central Komatiite horizon has received very little exploration in this area of the tenement, despite being
host to the 5B Deposit 1,200 metres to the south.
ESR may consider establishing a footwall exploration drive from which the 5A komatiite channel